Title Page
-
AGFAB ENGINEERING PROJECT AUDIT SCHEDULE
-
Client / Site
-
Conducted on
PROJECT STARTUP
-
(Freq) Once - (Resp) PM - (Audit) Contract - (Output) Contract Executed
-
(Freq) Once - (Resp) PM - (Audit) Transmittal Form - (Output) IFC Drawings
-
(Freq) Once - (Resp) PM - (Audit) Register - (Output) IFC Drawings
-
(Freq) Once - (Resp) APM - (Audit) Transmittal Form - (Output) IFC Specifications and Supporting Documentation
-
(Freq) Once - (Resp) PM - (Audit) Plan - (Output) Project Workplace Risk Assessment (WRA)
-
(Freq) Once - (Resp) PM - (Audit) Plan - (Output) Project Work Breakdown Structure (WBS)
-
(Freq) Once - (Resp) PM - (Audit) Plan - (Output) Project Quality Management Plan
-
(Freq) Once - (Resp) PM - (Audit) Plan - (Output) Project Safety Management Plan
-
(Freq) Once - (Resp) PM - (Audit) Plan - (Output) Project Environmental Management Plan
-
(Freq) Once - (Resp) PM - (Audit) Plan - (Output) Project Emergency Management Plan
-
(Freq) Once - (Resp) PM/SS - (Audit) Contract - (Output) Site Establishment Activity Method Statement (AMS)
-
(Freq) Once - (Resp) PM - (Audit) Plan - (Output) Site Environmental Plan
-
(Freq) Once - (Resp) PM - (Audit) Timeline - (Output) Project Schedule
-
(Freq) Once - (Resp) PM - (Audit) Register - (Output) Agfab Fabrication Drawings/Sketches
-
(Freq) Once - (Resp) PM - (Audit) Update Register - (Output) Request for Information
-
(Freq) Once - (Resp) PM - (Audit) Update Register - (Output) Variation Log
-
(Freq) Once - (Resp) PM - (Audit) Update Register - (Output) Induction and Training records
-
(Freq) Once - (Resp) PM - (Audit) Update Register - (Output) Noncompliance
-
(Freq) Once - (Resp) PM - (Audit) Update Register - (Output) MSDS and Chemical Register
-
(Freq) Once - (Resp) PM - (Audit) Update Register - (Output) Incident Tracking Register
-
Freq) Site Est - (Resp) PM - (Audit) Site Signage - (Output) Confirm Adequate Site Signage
-
Freq) Site Est - (Resp) PM - (Audit) Regulatory Signage - (Output) if You Are Injured Displayed - Emergency Instructions
-
Freq) Site Est - (Resp) PM - (Audit) Regulatory Requirements - (Output) return to Work Coord Nominated
ONGOING SITE/PROJECT COMPLIANCE
-
(Freq) Ongoing - (Resp) PM /SS - (Audit) Update Register - (Output) IFC Drawings
-
(Freq) Weekly - (Resp) APM - (Audit) IFC Drawings - (Output) Red Line Mark-ups up to date
-
(Freq) Ongoing - (Resp) APM - (Audit) Update Register/File - (Output) Agfab Drawing/Sketch register up to date
-
(Freq) Ongoing - (Resp) PGR - (Audit) Update Register - (Output) RFI register up to date and issues under control
-
(Freq) Ongoing - (Resp) PM/APM/SS - (Audit) Update Schedule - (Output) Project Schedule - Confirm Progress Against Schedule
-
(Freq) Ongoing - (Resp) PM - (Audit) Update Register/File - (Output) Variations up to date and issues under control
-
(Freq) Ongoing - (Resp) SS - (Audit) Update Register/File - (Output) Induction and Training records current
-
(Freq) Ongoing - (Resp) PM - (Audit) Hard Hat Sticker - (Output) Site workers - Customer Inductions Current
-
(Freq) Ongoing - (Resp) PM - (Audit) Update Register - (Output) Noncompliance Report/Actions
-
(Freq) Ongoing - (Resp) PM - (Audit) Update Register - (Output) Customer project feedback compliance - CMO
-
(Freq) Once - (Resp) PM - (Audit) Update Register - (Output) MSDS and Chemical Register up to date
-
(Freq) Ongoing - (Resp) PM - (Audit) Form - (Output) Incident Notification and Investigations under control and filed at Agfab Office
-
(Freq) Ongoing - (Resp) PM/APM/SS - (Audit) Site Whiteboard - (Output) Weekly Planning Meeting current
-
(Freq) Ongoing - (Resp) PM - (Audit) Minutes - (Output) Project Site Meeting
-
Freq) Daily - (Resp) PM/S (Audit) Daily Pre Stars/ Weekly Toolbox - (Output) Availability of Records
-
(Freq) Monthly - (Resp) PM - (Audit) Register - (Output) Agfab Engineering Project Action register up to date
-
(Freq) Ongoing - (Resp) PM - (Audit) Invoice - (Output) Progress Claims, Red lines, site performance report, Stat. Dec.
-
(Freq) Ongoing - (Resp) SS - (Audit) I-Auditor - (Output) Project Site Audits
-
(Freq) Ongoing - (Resp) SQEC - (Audit) Report - (Output) Internal Audits
-
(Freq) Monthly - (Resp) PM - (Audit) Review - (Output) Project Workplace Risk Assessment (WRA)
-
(Freq) Ongoing - (Resp) PM - (Audit) AGFAB Administration - (Output) Agfab - Site Performance Report/KPI's
-
(Freq) Ongoing - (Resp) PM - (Audit) Contract Administration - (Output) Customer - Site Performance Report
-
(Freq) Ongoing - (Resp) PM - (Audit) Back-Up - (Output) Site Laptops/server being backed up
-
(Freq) Once - (Resp) PM - (Audit) Agfab Template - (Output) Commissioning Plan
SUPPLIER MANAGEMENT
-
(Freq) Ongoing - (Resp) APM, SS, Office Admin - (Audit) Certificates - (Output) Supplier Insurances - Public Liability; Workers Compensation; etc.
-
(Freq) Ongoing - (Resp) PM - (Audit) Supplier Documents - (Output) Sub-contractor contract in place and signed
-
(Freq) Ongoing - (Resp) APM/SS - (Audit) Supplier Documents - (Output) Supplier Plant Management - Risk Assessments
-
(Freq) Ongoing - (Resp) APM/SS - (Audit) Supplier Documents - (Output) Supplier Plant Management - Maintenance Records
-
(Freq) Ongoing - (Resp) PM/APM/SS - (Audit) Form - (Output) Agfab Purchase Orders up to date
-
(Freq) Ongoing - (Resp) PM/APM/SS- (Audit) Transmital Form - (Output) Agfab Purchase Orders to Accounts
IAuditor - SWMS
-
I Auditor SWMS ( Output) Evidence of Consultation and Review - Start Cards in Use Where Required
IAuditor - WRA/AMS
-
I Auditor WRA/AMS ( Output) Evidence of Key Risk and Control - Review
IAuditor - ITP
-
I Auditor ITP( Output) Hold Points- Supportive Documents Retained - Sign Off for Current <br>Works<br>
IAuditor - SQE
-
I Auditor SQE
PROJECT COMPLETION
-
(Freq) EOP - (Resp) Nil customer NCR due to a Safety Incident - (Audit) Contract Review - (Output) Project Management Review
-
(Freq) Ongoing - (Resp) Electrician - (Audit) Energy Safe Victoria Form - (Output) Certificate of Electrical Safety - Prescribed/Non-Prescribed
-
(Freq) Completion - (Resp) PM/(CME) - (Audit) Supplier Documents - (Output) Manuals and Data Sheets
-
(Freq) Practical Completion - (Resp) PM - (Audit) documentation O&M Manuals- (Output) Being prepared prior to end of project