Information
-
Client / Site
-
Conducted on
-
Prepared By:
- John Frattin
- Alan Nield
- Greg Grima
- Ian McCormick
- Graham Davis
- George Lubczenko
- John Toner
- Peter Cations
- Roland Frost
-
Location
-
Personnel on site
GENERAL
-
Daily pre-start conducted and signed by all workers
-
Attendance register current (all persons signed on)
-
Site supervisor on site and off the tools
-
First aider(s) on site
-
ITP in place for current works and signed up to date.
-
Amenities adequate, clean and maintained
-
All persons on site fit for work (including fatigue compliance)
-
Site PPE requirements being met
-
Public safety controls in place (eg fencing, barriers, signage)
-
Site clean and tidy (general housekeeping)
-
Traffic management controls in place as per TMP
-
Hazardous materials storage area (bunded & labelled)
SWMS
-
SWMS in place for current works
-
All persons signed onto SWMS
-
Reviewed in the last 7 days
-
SWMS applicable to the task being performed
-
Work being performed in accordance with SWMS
-
Any other PPE required (site/task specific)
-
Competent for task being undertaken (check tickets)
-
START Cards completed
ENVIRONMENTAL MANAGEMENT
-
Erosion/Sediment control in place, adequate and maintained
-
Waste disposed of in labelled bins. Recycling segregated.
-
Concrete wash out in designated area. Bunded and lined.
-
Sensitive vegetation barricaded and signage in place
-
Soil stockpiles >10m from watercourses*
-
Refuelling >50m from watercourses*
-
Dust suppression adequate
-
Noise/vibration/odour controls adequate
EXCAVATION AND TRENCHING
-
Statutory notification submitted
-
Excavation and Trenching permit in place (Duration as specified)
-
Daily trench inspection documented
-
Trench benched, battered or shored adequately
-
Safe means of entry and exit
-
Barrier and signage to protect workers and public
-
Spoil or materials not placed within 1m of excavation edge
MOBILE PLANT
-
Plant Register current and PHA's available
-
Daily plant prestart check completed
-
Operator competency/license available
-
Operable flashing light, reverse alarm and fire extinguisher
-
Designated pedestrian routes separate from plant movement
WORKING AT HEIGHT
-
Ladders secure and only used for access/egress (unless platform ladder)
-
Scaffolds tagged (monthly)
-
Live edges barricaded (Flagging/mesh min 2m out)
-
Elevated Work Platform (EWP) in good condition, harness in use and on level and stable ground
-
Penetrations protected to prevent fall of people & materials. Covers (incl grid mesh) securely fastened in place.
-
Protection of workers below/falling objects
-
Work at heights controls implemented
CONFINED SPACE
-
CSE permit in place and controls implemented
-
Entry/Exit log maintained (See permit)
-
Gas monitoring in place
-
Observer/standby persons present
-
PPE and signage inplace
-
Rescue Plan in place
ELECTRICAL
-
Electrical tools and leads tested and tagged (3 monthly)
-
Electrical leads elevated and insulated from metal objects
-
Electrical supply panels secure (no unauthorised access)
-
RCDs fitted and tested Monthly (check site sheds)
-
Extension leads single length only
LIFTING AND RIGGING
-
Crane Safe green sticker (Current 12 month)
-
Lift study completed for lifts (Where required)
-
Plant has SWL/WLL clearly marked
-
Lifting gear register current (3 monthly inspection completed)
-
Rigging gear in good condition, SWL marked
-
Rigger/dogman used to control the lifting loads
-
Lift areas delineated and clear of persons
WELDING AND HOT WORKS
-
Hot Work permit in place and controls implemented
-
Flash back arresters, flash protection & weld curtains
-
Earthing in place, leads tagged and in good condition
-
Oxy bottles secured and stored separately
GENERAL COMMENTS:
-
Add additional photos if required:
-
Add a drawing to assist observations and actions required:
-
Worksite Manager:
-
Person Conducting the inspection: