Title Page
-
Doc number
-
Conducted on
-
Prepared by
-
Site conducted
-
Level
- Lower Ground
- Upper Ground
- Ground
- 1st
- 2nd
- 3rd
- 4th
- 5th
- 6th
- 7th
- 8th
- 9th
- 10th
- 11th
- 12th
- 13th
- 14th
-
System tested
BC Box
-
Is BC Box securely fixed?
-
Is pipe coil from FCU to BC Box securely fixed & dressed neatly?
-
Is pipework terminated in correct ports
-
Is BC box adequatly labelled
Testing
-
Has the unit been under strength test for 1hr
-
What pressure was it under? (BAR)
-
Start Image
-
End Image
-
Outcome
-
Has the unit been under working test for 24hrs
-
What pressure was it under? (BAR)
-
Start Image
-
End Image
-
Outcome
Completion
-
Any Additional comments
-
West Coast Signature
-