Check services installed to latest issue mechanical drawings.
Finals
-
Is the Dish washer Waste connected, a check valve in place and the Valve in the off position.
-
Is the Kitchen Tap installed and connected?
-
Is the Kitchen Sink Flood Tested
-
Is the Stopcock installed.
-
Is the Water heater installed
-
Is the PRV set to the correct pressure
-
is the Tun dish installed in accordance to British Standards.
-
Is the waterless trap installed in accorance to british standards
-
Is There a HIU
-
Is the HIU Level
-
Is the Scale reducer installed
-
is the Tun dish installed to the british standard
-
Is the water heater Full of water with the power on and left in standby mode
-
Does the Washing machine Valve have a check valve?
-
Is the Toilet Installed
-
Is the Toilet Seat installed
-
Is the Flush plate installed
-
Does the Toilet flush and re fill correctly
-
Is the Basin Installed
-
Is the Basin Level
-
Are the tapes installed and connected
-
is the Waste installed and connected and flood tested
-
Is the Basin Flood tested
-
Is the Shower completed
-
Shower valve installed and working orrectly
-
Shower head installed and working correctly
-
Hand held installed and working correctly
-
Shower tray drains away correctly
-
Is the bath fitted
-
Is the Trap fitted
-
Is the bath Filler Fitted
-
Is the Bath Flood Tested
-
Is there a HIU Fitted?
-
Is the Scale Reducer Fitted
-
Are the Tun-dishes installed as per the British standard
-
Are all pipes of level, clipped and jointed correctly
-
Is the Water less Trap installed
-
Are the heating Pipes installed
-
Has Inhibitor been added to the heating system
-
Are the Heating pipework Tested
-
has the HIU been commissioned?
-
Are the Radiators fitted
-
Are the TMV's Fitted
-
Is the Towel rail fitted
-
Is the Apartment Complete?
-