Title Page
-
Conducted on
-
Prepared by
-
Location
INSTALLATION DETAILS
-
Installation Engineer Name:
-
Installation Date:
-
Start Time:
-
Finish Time:
-
Store Name:
-
Store Number:
-
Server Serial Number:
-
Asset Number:
-
Store Location Details
HARDWARE LIST - Please select all hardware used
-
Is the Payment Server a Fujitsu Esprimo DL956/LL (Win10 Pro _ Argos Contactless Build)?
-
Is there a CONTACTLESS PAYMENT SERVER label attached to the front of the PC?
-
Please label and provide a picture
-
Was the server powered using the supplied 3m IEC C13 to IEC C14 ?
-
Power cable - 3m IEC C13 to 3-pin cable (comes with server) - was this used?
-
Was the server patched using the supplied 2m blue patch leads?
-
Quantity used:
-
Are the patch leads labelled at both ends?
-
Shelf used - was this the 2u Black Cantilever Shelf, 400mm depth ?
-
Type of KVM lead used :
-
Was the Standard DisplayPort to VGA adaptor used?
-
Please list anything else supplied but not listed above, also list unused kit removed from site:
ETHERNET PORT AVAILABILITY SURVEY - Please test one available port per till position(include jewellery tills) and indicate the port ID
-
Till 1 - Is there a usable Ethernet port at till and is it labelled correctly in the patch panel ?
-
Port Number:
-
Is there a PED key available and does it work?
-
Please check with Store Manager and confirm key location
-
Till 2 - Is there a usable Ethernet port at till and is it labelled correctly in the patch panel ?
-
Port Number:
-
Is there a PED key available and does it work?
-
Please check with Store Manager and confirm key location
-
Till 3 - Is there a usable Ethernet port at till and is it labelled correctly in the patch panel ?
-
Port Number:
-
Is there a PED key available and does it work?
-
Please check with Store Manager and confirm key location
-
Till 4 - Is there a usable Ethernet port at till and is it labelled correctly in the patch panel ?
-
Port Number:
-
Is there a PED key available and does it work?
-
Please check with Store Manager and confirm key location
-
Till 5 - Is there a usable Ethernet port at till and is it labelled correctly in the patch panel ?
-
Port Number:
-
Is there a PED key available and does it work?
-
Please check with Store Manager and confirm key location
-
Till 6 - Is there a usable Ethernet port at till and is it labelled correctly in the patch panel ?
-
Port Number:
-
Is there a PED key available and does it work?
-
Please check with Store Manager and confirm key location
-
Till 7 - Is there a usable Ethernet port at till and is it labelled correctly in the patch panel ?
-
Port Number:
-
Is there a PED key available and does it work?
-
Please check with Store Manager and confirm key location
-
Till 8 - Is there a usable Ethernet port at till and is it labelled correctly in the patch panel ?
-
Port Number:
-
Is there a PED key available and does it work?
-
Please check with Store Manager and confirm key location
-
Till 9 - Is there a usable Ethernet port at till and is it labelled correctly in the patch panel ?
-
Port Number:
-
Is there a PED key available and does it work?
-
Please check with Store Manager and confirm key location
-
Till 10 - Is there a usable Ethernet port at till and is it labelled correctly in the patch panel ?
-
Port Number:
-
Is there a PED key available and does it work?
-
Please check with Store Manager and confirm key location
-
Till 11 - Is there a usable Ethernet port at till and is it labelled correctly in the patch panel ?
-
Port Number:
-
Is there a PED key available and does it work?
-
Please check with Store Manager and confirm key location
-
Till 12 - Is there a usable Ethernet port at till and is it labelled correctly in the patch panel ?
-
Port Number:
-
Is there a PED key available and does it work?
-
Please check with Store Manager and confirm key location
INSTALLATION CONFIRMATIONS
-
1. Confirm that server has been installed in the cabinet. Y/N
-
Attach photos of front and back – showing power plug connected
-
2. Confirm that the final config report text file appeared following the Provisioning Tool Script completion. Y/N
-
Attach photo
-
3. Confirm that server has been patched. Y/N
-
Attach photo showing patch panels and cable management
-
4. Confirm Server Name
-
5. Confirm NIC1 IP Address:
SIGN OFF
-
Installation Engineer Signature:
-
Store Manager/Supervisor Name:
-
Store Managers/Supervisors Signature:
-
Please add any other comment relevant to the installation:
-
PLEASE NOW EXPORT THE REPORT AND SHARE WITH THE PROJECT MANAGERS OFFICE IMMEDIATELY