Title Page
-
Started on
-
Prepared by
-
Location
Sunday
Day one admin
-
Has site deliveries been checked off and received
-
Has H&S station been set up
-
Have all the contractors been sharing the responsibility to keep the site cleans and free of debris
-
Have all contractors signed their RAMS
-
Has there been any working at height. If yes, please detail out how this was conducted
-
details
General
-
Removal of existing displays and disposal
-
Removal of existing walls
-
Set out and install timbers ready to recive new walls
-
Removal of floors (surface finishes eg cermaics, laminate & LVT)
-
Unplug electrics, high level and displays
-
Allowance to set aside selected fixtures for temporary use
-
Installation of new partion walls
-
Base coat paint partition walls
-
Are there any areas of the programme that need to be reviewed to avoid issues with the completion
Site progress
-
Is the site on programme
-
Are there any areas of the programme that need to be reviewed to avoid issues with the completion.
-
What areas of the programme are ahead
-
What areas are behind
-
Have all contractors arrived on site as per the programme
-
Have any of the contractors overrun the allotted duration on the programme
-
Site Manager to fill out Iauditor
-
Site Manager to complete progress - Iauditor
Monday
H&S
-
Have all the contractors been sharing the responsibility to keep the site cleans and free of debris.
-
Have all contractors signed their RAMS
-
Has there been any working at height. If yes, please detail out how this was conducted
-
Have there been any accidents since the last report. If yes please give details
-
If yes to the preceding question has this been communicated to the PM
-
How many spot light near miss reports have been completed since the last report. What were these?
-
How many good practice spot light reports have been completed since the last report.
-
Have all items identified in the last PM H&S audit been resolved and communicated to them?
- Yes
- No
- N/A
Site Progress
-
Is the site on programme
-
Are there any areas of the programme that need to be reviewed to avoid issues with the completion.
-
What areas of the programme are ahead.
-
What areas are behind
-
Have all contractors arrived on site as per the programme.
-
Have any of the contractors overrun the allotted duration on the programme.
-
Has the PM issued an updated programme if needed and re-issued to all
Visits & communication
-
Has the PM conducted a site visit
-
Following the PM visit, have they left an action list or notes to be completed
-
Has the client visited the site
-
Has the client raised any concerns
-
Has the client requested any changes and have these been communicated to the PM & PC
-
Have any senior managers from RI visited site this week? If so, who?
-
Site Manager to complete progress - Iauditor
General
-
Receive Kitchen Door Display
-
Receive Worktop Selector
-
Receive Work Station - Project Desk
-
Receive Free Issue Tap Cube
-
Receive POS pack
-
Clean and buff vinyl floor area following partition wall removal
-
Site Manager - mark out floor for desk, worktop selectors and door bar display stand positions
-
Filled, sanded and decorated - Walls
-
Install subloor
-
Install floor tiles - see PDL's
-
Assemble carcasses
-
Work Station - Project Desk
-
Electrical :Install all high level containment, hanging wires and cables
-
Electrical: Install and connect hanging pendant to kitchen 2B
-
Electrical: Install and connect track and lights to cabinet world
-
Electrical: Install chrome pole and power drop to new desk (if required)
-
KITS to install new data cable to new desk (if required)
-
Site Manager snag & repair completed works
-
Site Manager to complete progress - Iauditor
Tuesday
H&S
-
Have all the contractors been sharing the responsibility to keep the site cleans and free of debris.
-
Have all contractors signed their RAMS
-
Has there been any working at height. If yes, please detail out how this was conducted
-
Have there been any accidents since the last report. If yes please give details
-
If yes to the preceding question has this been communicated to the PM
-
How many spot light near miss reports have been completed since the last report. What were these?
-
How many good practice spot light reports have been completed since the last report.
-
Have all items identified in the last PM H&S audit been resolved and communicated to them?
Site Progress
-
Is the site on programme
-
Are there any areas of the programme that need to be reviewed to avoid issues with the completion.
-
What areas of the programme are ahead.
-
What areas are behind
-
Have all contractors arrived on site as per the programme.
-
Have any of the contractors overrun the allotted duration on the programme.
-
Has the PM issued an updated programme if needed and re-issued to all
Visits & communication
-
Has the PM conducted a site visit
-
Following the PM visit, have they left an action list or notes to be completed
-
Has the client visited the site
-
Has the client raised any concerns
-
Has the client requested any changes and have these been communicated to the PM & PC
-
Have any senior managers from RI visited site this week? If so, who?
-
Site Manager to complete progress - Iauditor
General
-
Kitchen display 17a
-
install units
-
Kitchen Display 2B
-
Install units
-
Cabinet Area
-
Install POS
-
Install units
-
Electrical: Install and connect track and lights to worktop selector, door bar & surface/décor display wall
-
Site Manager to snag and repair completed works
Wednesday
H&S
-
Have all the contractors been sharing the responsibility to keep the site cleans and free of debris.
-
Have all contractors signed their RAMS
-
Has there been any working at height. If yes, please detail out how this was conducted
-
Have there been any accidents since the last report. If yes please give details
-
If yes to the preceding question has this been communicated to the PM
-
How many spot light near miss reports have been completed since the last report. What were these?
-
How many good practice spot light reports have been completed since the last report.
-
Have all items identified in the last PM H&S audit been resolved and communicated to them?
Site progress
-
Is the site on programme
-
Are there any areas of the programme that need to be reviewed to avoid issues with the completion.
-
What areas of the programme are ahead.
-
What areas are behind
-
Have all contractors arrived on site as per the programme.
-
Have any of the contractors overrun the allotted duration on the programme.
-
Has the PM issued an updated programme if needed and re-issued to all
Visits & communication
-
Has the PM conducted a site visit
-
Following the PM visit, have they left an action list or notes to be completed
-
Has the client visited the site
-
Has the client raised any concerns
-
Has the client requested any changes and have these been communicated to the PM & PC
-
Have any senior managers from RI visited site this week? If so, who?
-
Site Manager to complete progress - Iauditor
General
-
kitchen 17a
-
Install worktops, sink and appliances
-
Kitchen Display 2B
-
Install worktops, sink and appliances
-
Cabinet Area
-
Finishing internals
-
Tile kitchen displays
-
Install Gradus strips to floor tile area
-
Electrical: Install and connect power drop to Kitchen 2B
-
Site Manager snag & repair completed works
-
Site Manager to complete progress - Iauditor
Thursday
H&S
-
Have all the contractors been sharing the responsibility to keep the site cleans and free of debris.
-
Have all contractors signed their RAMS
-
Has there been any working at height. If yes, please detail out how this was conducted
-
Have there been any accidents since the last report. If yes please give details
-
If yes to the preceding question has this been communicated to the PM
-
How many spot light near miss reports have been completed since the last report. What were these?
-
How many good practice spot light reports have been completed since the last report.
-
Have all items identified in the last PM H&S audit been resolved and communicated to them?
Site progress
-
Is the site on programme
-
Are there any areas of the programme that need to be reviewed to avoid issues with the completion.
-
What areas of the programme are ahead.
-
What areas are behind
-
Have all contractors arrived on site as per the programme.
-
Has the PM issued an updated programme if needed and re-issued to all
Visits & communication
-
Has the PM conducted a site visit
-
Following the PM visit, have they left an action list or notes to be completed
-
Has the client visited the site
-
Has the client raised any concerns
-
Has the client requested any changes and have these been communicated to the PM & PC
-
Have any senior managers from RI visited site this week? If so, who?
-
Site Manager to complete progress - Iauditor
General
-
Kitchen Display 2B
-
Finishing detail
-
Cabinet Area
-
Finishing detail
-
Kitchen Door Display
-
Worktop Selector
-
Sample Boards
-
Free Issue Tap Cube
-
POS - point of sale materials
-
Site Manager to phone Hire Companies and check everything is booked for collection
-
Site Manager snag & repair completed works
-
Site Manager to complete progress - Iauditor
Friday
H&S
-
Have all the contractors been sharing the responsibility to keep the site cleans and free of debris.
-
Have all contractors signed their RAMS
-
Has there been any working at height. If yes, please detail out how this was conducted
-
Have there been any accidents since the last report. If yes please give details
-
If yes to the preceding question has this been communicated to the PM
-
How many spot light near miss reports have been completed since the last report. What were these?
-
How many good practice spot light reports have been completed since the last report.
-
Have all items identified in the last PM H&S audit been resolved and communicated to them?
Site progress
-
Is the site on programme
-
Are there any areas of the programme that need to be reviewed to avoid issues with the completion.
-
What areas of the programme are ahead.
-
What areas are behind
-
Have all contractors arrived on site as per the programme.
-
Have any of the contractors overrun the allotted duration on the programme.
-
Has the PM issued an updated programme if needed and re-issued to all
Visits & communication
-
Has the PM conducted a site visit
-
Following the PM visit, have they left an action list or notes to be completed
-
Has the client visited the site
-
Has the client raised any concerns
-
Has the client requested any changes and have these been communicated to the PM & PC
-
Have any senior managers from RI visited site this week? If so, who?
-
Site Manager to complete progress - Iauditor
-
How many working hours have been completed this week?
General
-
Sparkle Clean
-
Site Manager snag & repair completed works
-
POS final install
-
Pack up site box ready for transfer, check off return items via the picklist
-
Remove Hoarding and store securely
-
Ensure all tools/materials removed from Unit
-
Ensure all waste removed from the unit and skipped
-
All hire equipment to be collected - HSS, Scissors
-
Skip collection-late PM
-
Sweep site compound
-
Site Manager to complete B&Q H&S handover with store manager
-
Site Manager to complete Handover - Iauditor
-
PM to confirm all works are complete