Does the conduit size & type comply with issued construction drawings and relevant specifications?
-
Are conduits stamped for AS2053 for Energex as applicable?
-
Has the conduit route and/or site boundaries been pegged where required?
-
Have all know services been located (electronically, visually) as required before excavation commences?
-
HOLD POINT - Photographs of set out
-
Have any issues been identified onsite that will affect the installation meeting ENERGEX or ASNZ3000 requirements?
Conduit details
-
Conduit run station numbers
-
Conduits in Roadway or Footpath/verge
-
Conduit Size?
- 100mm HD
- 80mm HD
- 50mm HD
- 40mm HD
- 125mm LD
- 100mm LD
- 80mm LD
- 100mm Coms HD
- 50mm Coms HD
Conduit Installation
-
Does the trench width & depth comply with the issued construction drawing requirements?
-
Photo of trench depth
-
Has bedding sand been installed as per Energex / ASNZ3000 Specifications?
-
Photos of bedding sand
-
Have all conduit joints been cleaned primed and glued?
-
Has the depth of cover from the finish surface level been confirmed prior to the backfilling the trench as per ENERGEX or ASNZ3000 requirements?
-
Photos of finish level
-
Has marker tape/hard cover to AS2648 Part 1 and individual authority requirements been installed as applicable?
-
Does the trench compaction for existing pavement, new pavement & footpaths comply?
-
For trenches in existing roadway has the lean mix concrete been installed & compacted as per MRD standard drawing 1149, Energex 6229-A4 [C2-3.3] or BSD2042?
-