Information

  • CSA

  • Job ID

  • Job Source

  • Address

  • Audit date

  • Auditor

  • Auditee

Desktop checks

1.000 Design

  • 1.001 All documentation lodged in iTools e.g. Scope, CDPs, RMA site plans, lay, hauling and grid plans

  • 1.003 NetMAP design not in conflict with other design work

  • 1.007 Build standards applied in design, manhole and cable size, plant location and position

  • 1.009 Spares considered and where applicable required as part of design

  • 1.012 Work priced correctly using template, FS codes and quotes as applicable

  • 1.040 Tasks completed as per proposed plan

2.000 Handover and collateral delivered to Chorus

  • 2.005 Deployment codes and template pricing applied correctly - fit for purpose solution

  • 2.008 NetMap updated, integrity checked and confirmed. PRA passes

  • 2.019 All network items defined within the Chorus Network Specified Product (CNSP) process are used in the network. No non-approved items used

  • 2.022 Cable Plant Alteration (CPA) forms completed and correct

  • 2.025 As Builts accurately reflect what was built

4.000 Codes

  • 4.004 Correct statement of works codes used

  • 4.005 Decision tree applied for correct lead in method

55.000 Network Records

  • 55.002 Correct standard has been used

  • 55.006 Recording made to the appropriate standards

Field checks

13.000 Cable Haul

  • 13.001 Correct cable installed as per project pack

  • 13.003 Correct duct used, or changes recorded on As Builts

  • 13.016 All cable ends sealed with heat shrink, coiled and secured ready for use

  • 13.022 Fibre cable prepared for joint correctly in manhole (cable management tidy to cable loop brackets)

  • 13.023 Manhole/joint chamber lids free of material, bung fitted in lifting hole, lid locked

15.000 Cable and Duct Lay

  • 15.005 Route position correct according to plan

  • 15.008 Warning tape installed

  • 15.009 Buried cable crossings - depth and protection

  • 15.010 Reduced cover - protection installed

  • 15.026 Duct at customer boundary for direct install fibre sealed and buried or housed in approved enclosure (e.g. Pedestal or handhole)

16.000 Micro Duct Directional Drill and Lay

  • 16.006 Route position correct according to plan

  • 16.008 Micro duct end on customer boundary (including ROW) end capped, wrapped in heatshrink and labelled, then either buried or housed in approved enclosure (e.g. Pedestal)

  • 16.012 Micro duct joints protected

  • 16.013. Microduct joints external to manholes. At customer boundaries for ROWs

  • 16.026 1-way micro duct correctly labelled

19.000 Fibre Jointing and Closure

  • 19.001 Joint closure secured on manufacturer's bracket

  • 19.002 NetMap label on closure and each cable tail

  • 19.010 30mm bending radius unconditionally observed at all locations

  • 19.014 No fibre or task waste, all optical (glass) ends safely contained

41.000 BDD Terminal/Channel Pit

  • 41.001 Pit lids secure/locked, with bung fitted where appropriate

  • 41.002 Pit installed correctly

  • 41.017 all cables/microduct, including lead in zip-tied or taped together in a tidy loop within pit

42.000 Pedestal/IFDB

  • 42.001 Pedestal vertical, firm, at correct depth

  • 42.008 Foam bung fitted/ in correct position

  • 42.023 Network labelling in place to suit requirements

  • 42.025 Starter pipes installed to facilitate provisioning of NGA services

  • 42.026 Microduct and connectors installed in vertical positions only

68.000 Fibre Access Terminal

  • 68.001 Entry tubes sealed

  • 68.002 Two fibres per tray only

  • 68.005 Tube holder installed

  • 68.007 Silica gel pack installed/replaced

  • 68.008 Triangle symbols on dome and base match

  • 68.009 All latches locked - ports blocked/sealed

  • 68.010 O-ring installed

  • 68.011 Fibre correctly managed within FAT and trays

  • 68.013 Slack managed in fibre management coil (1.5 - 2m)

  • 68.014 Swing arm and bracket in working order/or mounted on manufactured bracket

  • 68.015 Lid locked and lock bung fitted

  • 68.016 30mm bending radius unconditionally observed at all locations

  • 68.018 Heat shrink splice protectors secured from movement

  • 68.019 No fibre or task waste, all optical (glass) ends safely contained

  • 68.020 FAT labelled correctly

  • 68.021 Fibre strain relief installed correctly

  • 68.024 Feeder/fibre cables labelled correctly

78.000 Building Distributor

  • 78.001 Correct reducers used and protection installed, appropriate external pipe and fixings used

  • 78.002 BUDI installed correctly - vertical, lid secure, labelled and coils managed correctly

  • 78.004 Feeder/fibre cables labelled correctly. Incoming fibre secured to anchor point with foam and zip tie

  • 78.006 All micro ducts labelled, capped and secured to wall or tray in riser

  • 78.007 Micro ducts trimmed to the correct height, 220mm from base of cabinet

  • 78.008 Micro ducts capped

  • 78.009 Gas blocker installed

  • 78.010 Continuity wires installed and labelled

  • 78.011 Tray retention strap in place

  • 78.013 Two fibres per tray only

  • 78.014 Fibre routed and laid up correctly in tray. All unused connectors capped

  • 78.015 Slack managed in fibre management coil. 30mm bend radius unconditionally observed at all times

  • 78.021 Network labelling in place to suit requirements

  • 78.023 Splitter installed and labelled

  • 78.024 Correct number and type of trays installed. Tray retention strap in place

  • 78.026 Fire and smoke barriers reinstated in accordance to AS/NZ3000 standard

  • 78.029 GPON feeder fibres to future PON splitters reserved in NetMap

  • 78.030 MDU lead in cables and IBDN recorded in NetMap

  • 78.034 Duct tape off box secured to wall or tray in riser and labelled correctly. All tubes jointed correctly where they exit the top.

  • 78.036 Outer door locks work smoothly and door closes without jamming

  • 78.037 Feeder fibres installed on far left hand side

  • 78.038 Distribution frame: Correct trays installed and labelled

  • 78.039 Distribution frame: Data card inside drawer and labelled with the splitter, unit and level numbers

  • 78.043 Correct number of mandrels installed. Patch cords correct length and routing

  • 78.044 Minimum bend radius maintained when drawers are opened and closed

  • 78.045 Splitter installed and labelled, and splitter legs secured in parking bay

  • 78.046 Verticassa cable secured to wall/tray in riser

  • 78.047 Window cut does not exceed the breakout limit

  • 78.048 Cable protection cover installed on unused window

  • 78.049 Gravity loop in place for all cables and secured neatly

  • 78.060 Gas block connectors, end stops, 5mm divisible seal installed

  • 78.061 Drop lead access hatches installed correctly, straight and sealed. Work area on ceiling clean

  • 78.062 Pathways installed as per plan/standard. All pipes straight, junction boxes sealed and correct saddles and spacing so used

  • 78.063 Drop leads (2f/tube) coiled neatly, well contained and hidden

80.000 Aerial cable

  • 80.003 Cable down pole secured with down-lead clamp

  • 80.005 Fibre on lower section of pole protected with cover

Customer Premise checks

44.000 Service Lead

  • 44.019 Correct surface mount fastenings used/spacing to suit surface. Spacing max 600mm supported, 300mm unsupported

47.000 Business Premises

  • 47.007 No fibre or task waste, all optical (glass) ends safely contained

General Workmanship checks

72.000 Reinstatement

  • 72.001 Property damage made good

  • 72.002 Ground reinstatement complete around poles

  • 72.003 Reinstatement/backfill satisfactory around buried service leads

  • 72.006 Concrete flush with footpath or surrounding ground, no trip hazard

  • 72.007 Excess vegetation removed

  • 72.008 Reinstatement complete around pedestal

  • 72.009 Reinstatement complete around hand holes

  • 78.011 Reinstatement appropriate around cable haul

  • 72.020 Surplus soil removed

  • 72.021 Reseal completed - footpath/vehicle resurfaced

  • 72.022 Grass reinstated and replanted

73.000 Site tidy

  • 73.001 Site tidy, no task waste - Poles

  • 73.004 Site tidy, no task waste - Pillar terminal/IFDB

  • 73.005 Site tidy, no task waste - Pit

  • 73.008 Site tidy, no task waste - Service lead

  • 73.009 Site tidy, no task waste- ETP

  • 73.010 Site tidy, no task waste - Customer/business premises

  • 73.014 Site tidy, no task waste - Cable haul

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.