Information
-
CSA
- CSA 01
- CSA 02
- CSA 03
- CSA 04
- CSA 05
- CSA 07
- CSA 08
- CSA 09
- CSA 10
-
Job ID
-
Job Source
-
Address
-
Audit date
-
Auditor name
-
Auditee name
Desktop checks
1.000 Design
-
1.001 All documentation lodged in iTools e.g. scope, CDPs, RMA site plans, lay, hauling and grid plans
-
1.002 iTools progress task dates updated
-
1.005 NetMAP fibre reservations applied and removed when built
-
1.007 Build standards applied in design, manhole and cable size, plant location and position
-
1.015 cabinet alpha code applied for and correct
-
1.022 Tasks completed as per proposed plan
2.000 Handover & collateral delivered to Chorus
-
2.001 Handover procedure followed. WATCH form applied and correct
-
2.009 Bearer connectivity confirmed end-to-end
-
2.015 OTDR traces (all cable fibres at 1310 & 1550nm wavelength) confirmed delivered to Chorus
-
2.019 All network items defined within the CNSP process are used in the network. No non-approved items used
-
2.022 Cable Plant Alteration (CPA) forms completed and correct
-
2.025 As Builts accurately reflect what was built
55.000 Network Records
-
55.006 Recording made to the appropriate standards
-
55.022 Correct site and node codes have been used
-
55.023 Where applicable the bearer has been placed
-
55.024 Correct As Built fibre connectivity has been drawn and matches NetMAP
-
55.026 Correct sized cable has been drawn and labelled as per As Built and matches NetMAP
-
55.028 Adjoining sheets have been referenced, and references are consistent across FOG plans
-
55.087 NetMAP schematic (CDP) complete, correctly drawn and displayed
-
55.099 Exchange end matches GPON port allocations and AOFDF line card
-
55.100 High level trace aligns FOG plan, schematic and the field
-
55.101 CVLS test proves continuity
-
55.102 Pole to Boundary form aligns to Lay plan
-
55.103 Records match what was built/completed in the field
Exchange checks
7.000 Exchange equipment
-
7.018 Fire and smoke stopping around wall cable access holes
11.000 OFDF & Exchange Fibre
-
11.002 OFDF hardware secure, OFDF drawer, cable trough, guides, rack
-
11.003 Network labelling correct at AOFDF and log completed
-
11.005 OFDF single fibre organiser tray not overfilled (< 1.5m tails)
-
11.007 30mm bending radius unconditionally observed at all locations
-
11.012 Laser safety labels (1m safety) at OFDF (inside and front panel)
-
11.013 No fibre task waste, all optical (glass) ends safely contained
-
11.014 Access OFDF patch cords routed through mandrels. Excess length stored at AOFDF end
-
11.018 Access OFDF rack (GR3) cables secured, breakout to OFDF shelves tidy
-
11.022 Patch cords on the POLT side installed and labelled
12.000 Cable well
-
12.001 Main duct entry locations provide permanent seal from gas and water ingress
-
12.005 Cable management systems in place e.g. brackets, trays, support all cable and sub-duct services
-
12.006 Fibre joint closure secured. Excess length tails management loops provided and secure
-
12.007 NetMap label on fibre joint closure. Each fibre cable tail labelled with NetMap label
-
12.008 Cable well manhole lids security maintained
Field checks
13.000 Cable haul
-
13.001 Correct cable installed as per project pack
-
13.022 Fibre cable prepared for joint correctly in manhole, cable management tidy to cable loop bracket
15.000 cable and duct lay
-
15.002 Ducts laid or directional drilled between 450mm and 1000mm in footway
-
15.003 Ducts laid or directional drilled between 600mm and 1000mm in roadway
-
15.004 Duct alignment and configuration correct
-
15.005 Route position correct according to plan
-
15.007 Cable ends sealed with heat shrink
-
15.016 Fibre cable installation - metallic cable location tape installed
-
15.020 Bridge crossing: U channel, brackets, covers and pipe galvanised. All anchor bolts and fittings robust and secure
-
15.026 Duct at customer's boundary for direct install fibre sealed and buried or housed in appropriate enclosure
16.000 Micro duct directional drill and lay
-
16.002 Micro ducts laid or directional drilled between 450mm and 1000mm in footway
-
16.003 Micro duct laid or directional drilled between 600mm and 1000mm in roadway
-
16.005 Duct alignment and configuration correct
-
16.006 Route position correct according to plan
-
16.007 All micro duct ends of runs are sealed with end caps, then a closure fitted
-
16.008 Micro duct end on customer boundary (including ROW) capped, wrapped in heatshrink and labelled, then either buried or housed in appropriate enclosure
-
16.010 Micro duct joints to standard - approved enclosure, correct connectors, earth continuity maintained, water tight etc
-
16.026 1-way micro duct labelled correctly
-
16.027 Locate peg installed at buried lateral location or soft surface
17.000 Manhole, joint chamber and ducts (new and existing)
-
17.002 Manhole sited correctly, to plan and parallel to boundary line
-
17.003 Manhole correctly sized, as per design job spec
-
17.004 Manholes frames flush to ground, no trip hazard
-
17.010 All micro duct entry grouted, duct reamed, sits flush to wall
-
17.011 Non-concrete joint chamber duct entry protrudes 50mm into chamber, reamed and sealed to wall
-
17.012 Manhole cable management brackets installed to accept arms
-
17.013 Manhole cable management arms installed as required. Cable management correct
-
17.014 Manhole/joint chamber lids locked, in working order and rubber bung fitted
-
17.015 Ducts entry positioned close to adjacent wall for easy cable management
-
17.016 Ducts sealed where necessary to prevent ingress of water, moisture, gas, or pests into buildings and cabinets
-
17.021 New ducts into existing manholes - correct hole size and location cut in manhole wall for new duct entry
-
17.022 Direct fibre feed hauling tape installed
-
17.023 Direct fibre feed hauling tape secured at each end
-
17.027 Pit correctly bedded - metal surrounding sides of pit compacted
18.000 Manhole cable management
-
18.001 All cables managed tidily on brackets and arms
-
18.003 Fibre cable protection when required, tread plate, split sub-duct, bandit tape
19.000 Fibre Jointing and Closure
-
19.001 Joint closure secured on manufacturer's bracket
-
19.002 NetMap label on closure and each cable tail
-
19.003 Laser safety label (Starburst) visible outside and inside closure
-
19.004 Heat shrink fittings correct (thermal paint change, glue extruding)
-
19.005 Mechanical closure fittings correct (fittings,seal)
-
19.007 Non-metallic strength member anchored. Metallic strength member isolated
25.000 Poles
-
25.003 Pole in good condition, no splits or burrs
-
25.005 Pole hole depth correct, pole vertical and height correct
-
25.007 All new poles have network pole tag installed 3m above ground
-
25.012 Plant positioned correctly and safely, plant clearances correct
-
25.017 All tagged poles labelled in NetMap
39.000 Aerial terminal/OFDC
-
39.001 Correct terminal used
-
39.002 Terminal mounted and secured correctly
-
39.004 Terminal lid secure
-
39.013 Network labelling in place to suit requirements
-
39.014 Terminal on correct pole face
-
39.015 Flexi pipe secured directly below terminal (galv saddle on wooden pole)
-
39.016 Flexi pipe secured directly below terminal (bandit tape on concrete pole)
-
39.017 20mm or 32mm conduit secured to pole (wooden - galv saddles for White PVC pipe, plastic saddles for grey/beige 32mm HDPE pipe, secured with clouts or bandit straps. 600mm spacing)
-
39.018 20mm or 32mm conduit secured to pole, spacing < 1.5m (concrete bandit tapes)
-
39.019 Protective cable casing installed (as required - concrete or wood)
41.000 BDD terminal
-
41.001 Pit lids secure/locked, with bung fitted where appropriate
-
41.002 Pit installed correctly
42.000 Pedestal
-
42.001 Pedestal vertical, firm and at correct depth
-
42.003 Lid secure
-
42.008 Foam bung fitted/in correct position
-
42.019 Plastic bags secured, separate bags for loop/cable end and underground leads
-
42.025 Starter pipe(s) installed to facilitate provisioning of NGA Services
68.000 Fibre Access Terminal
-
68.001 Entry tubes sealed
-
68.002 Two fibres per tray only
-
68.009 All latches are closed - ports blocked/sealed
-
68.010 O-ring installed
-
68.011 Fibre correctly managed within FAT and trays
-
68.013 Slack managed in fibre management coil (1.5 - 2m)
-
68.014 Swing arm and bracket in good working order/or mounted on manufacturer's bracket
-
68.016 30mm bend radius unconditionally observed at all locations
-
68.018 Heat shrink splice protectors secured from movement
-
68.019 No fibre or task waste, all optical (glass) ends safely contained
-
68.020 FAT labelled correctly
-
68.021 Fibre strain relief installed correctly
-
68.022 FAT in manhole situated in a suitable place for provisioning
-
68.023 FATs installed as per design
-
68.024 Feeder/fibre cables labelled correctly
-
68.029 Gel seal installed in correct FAT port
-
68.031 RAT installed at time of communal build
74.000 Hand holes
-
74.002 Hand hole locked, with lock facing the customer boundary and openable
-
74.003 Starter pipe(s) installed to facilitate provisioning of NGA services
-
74.004 Flush with ground
-
74.006 Lateral labelled and sealed. End cap and heat shrink applied
-
74.008 Lid free from concrete/ seal
-
74.009 Sited correctly (close to customer boundary, hard surface, foot traffic only)
-
74.010 Single way Ribbonet, 1 turn only, end sealed wit heat shrink
-
74.011 Maximum of 4 single way Ribbonets installed
-
74.014 30mm bend radius unconditionally observed at all locations
77.000 UFB Channell Flash 9 installation
-
77.001 50mm of inner black sheath past outer green sheath
-
77.003 Earth wire managed and secured to pit wall
-
77.006 Micro duct tubes routed correctly in pit - minimum bend radius not exceeded
-
77.008 Velcro ties secured to the pit wall
-
77.009 Locking collar on closure is secured with locking bolt. ID label facing upwards
-
77.011 Correct micro duct connectors used to join and seal micro duct (5mm and 12mm)
-
77.012 Correct size gas blocks installed on 12mm micro ducts outside of closure containing optic fibre cable
-
77.013 All spare or unallocated 5mm and 12mm micro ducts capped with duct end caps within closure and pit
-
77.015 Correct size divisible gas seal used on populated 12mm micro ducts inside closure
-
77.016 Incoming and outgoing fibre cables in correct 12mm tubes
-
77.017 Closure base 'O' ring clean, dry, undamaged and correctly sealed. Spare O ring in closure
-
77.019 Pit lid free of reinstatement materials(T/seal cone)
-
77.020 All 5mm micro ducts trimmed to 80mm in height from base
-
77.021 All 12mm micro ducts trimmed to 40mm in height from base
-
77.022 Lid closure labelled correctly with NetMap ID and facing upwards
-
77.023 12mm micro duct carrying cable is correctly labelled with NetMap elements
-
77.024 Spiral wrap buffer tube protection installed and secured at the UMS with a cable tie
-
77.025 Metal lock zip tie securing fibres at base of organiser tray
-
77.026 Fibre routed and laid up correctly in trays
-
77.027 All microducts are labelled
-
77.029 Joint bundle wrapped in Eziwrap or A3 - 250 micron clear plastic and secured
-
77.032 Splitter and its input leg splice is installed on correct tray
-
77.034 Figure 8 grommet port sealed correctly in base
-
77.035 Cable sheath between 10mm and 20mm above grommet
-
77.036 Feeder fibre enters UMS on RHS and transitions to the LHS of the UMS then enters tray on RHS
-
77.038 Cables labelled with section ID using Critchley system
-
77.039 1.2m of fibre in SC trays
-
77.040 Uncut buffer tubes stored between verticals within plastic sleeve
-
77.041 Spur cable, 48f, 116f or micro cable installed with 19mm and no.8 grommet
-
77.042 Micro ducts 1 - 26 enter through 3 RH ports (viewed from swing arm)
-
77.044 100mm duct capped at pole
-
77.045 Direct buried ADSS fibre protected at pit entry with 50mm duct
-
77.046 Minimum bend radius achieved inside pit (149mm for 116f, 110mm for 48f)
-
77.049 Correct number of SC trays installed
-
77.050 Correct number of SE trays installed
-
77.051 Enclosure support bracket in place
-
77.052 Tray retention strap in place
-
77.053 Lid in place on the top SC tray
-
77.054 Lid in place on the top SE tray
-
77.055 UMS tray cover in place
-
77.060 ABFU buffer stripped at bottom of tray with acrylate peeled to allow access to both fibres
-
77.061 Chamber lid secured
-
77.062 ABFU fibre correctly routed from microduct to tray
-
77.063 Splice protectors retained within splice comb
-
77.064 Water ingress - no water access to closure
-
77.065 End stops on all 5mm and 12mm tubes
-
77.066 5mm divisible seals on all working trays
-
77.067 Pressure testing completed
80.000 Aerial Cable
-
80.001 Anchor clamp/dead end grip terminated correctly
-
80.002 ADSS cable correct tension
-
80.003 Cable down pole secured with down-lead clamp
-
80.004 Threaded rod protected with zinc paint
-
80.005 Fibre on lower section of pole protected with cover
-
80.006 Aerial cable within 800mm of existing low voltage envelope
-
80.007 No new road crossings created
-
80.008 Sag matches that of existing lines as best as possible
General Workmanship checks
6.000 Work Areas & Safety
-
6.008 Network security correct (exchange)
-
6.009 Joint chamber/manhole lid closed and secure
-
6.014 Any defects to existing network outside of scope of project referred to be rectified in the future
-
6.015 All power clearances maintained (underground and overground)
72.000 Reinstatement
-
72.001 Properly damage made good
-
72.014 Any road markings damaged by works are restored
-
72.018 Ground reinstatement completed
-
72.020 Surplus soil removed
-
72.021 Reseal completed - footway / vehicle resurfaced
-
72.028 Reinstatement completed to standard
73.000 Site tidy
-
73.001 Site tidy, no task waste - poles
-
73.024 Site tidy, no task waste - general