Information

  • Audit Title / Project Description

CMUX Project Details

Project Details

  • CP Number

  • SP Number

  • Project (Sequence) Nbr

  • Site Name

  • Site Address

Installer Details

  • Name / Signature

  • Company

  • Phone Number

  • Date

1 Housing

1.1 Housing alignment

  • 1.1.1 Check alignment marker

  • 1.1.2 Check door alignment

1.2 Check of all hold down bolts

  • 1.2.1 Nylon washers installed

  • 1.2.2 Flat washer installed

  • 1.2.3 Nuts tightened correctly

1.3 Housing level

  • 1.3.1 Housing is level in both directions

1.4 Operation of doors & latches

  • 1.4.1 Main Equipment Compartment

  • 1.4.2 Cross Connect Unit

  • 1.4.3 Power Compartment

1.5 Vermin proofing

  • 1.5.1 All cable entry holes and flexible conduit are sealed

1.6 Check for physical damage

  • 1.6.1 Shock indicator intact

  • 1.6.2 No damage to housing

1.7 Conduits

  • 1.7.1 For Standard Housing Installation: 2 x 100 mm conduits installed

  • 1.7.2 For Adjunct Housing Installation: 3 x 100 mm conduits installed

1.8 Hauling ropes

  • 1.8.1 Check hauling ropes in place in Conduits and Pipes

1.9 External Battery Pit

  • 1.9.1 External Battery Pit

  • 1.9.2 Drain as per specifications

  • 1.9.3 Airlock installed

1.10 Communications Earth

  • 1.10.1 Earth electrode installed as per specifications

  • 1.10.2 Earth bar installed as per specifications

  • 1.10.3 FOR ADJUNCT HOUSING ONLY: 16 sqmm earth bonding cable installed between RIM housing and CMUX adjunct housing

2 Power

2.1 Mains power cable

  • 2.1.1 Cable has been secured with cable ties between the entry hole and the mains input junction box

  • 2.1.2 Sliding out the loaded battery trays (top and bottom) will not foul the mains input cable

2.2 Spare mains cable

  • 2.2.1 1 metre of spare cable left in each electrical pit

2.3 AC earth stake

  • 2.3.1 AC earth stake is connected and painted

2.4 AC mains installation

  • 2.4.1 AC mains installation as per work instruction and / or complies with local power authority requirements

2.5 Battery lug connections

  • 2.5.1 Battery lug connections are tightened

  • 2.5.2 Battery terminals sealed with Vaseline (Battery Pit Only)

2.6 Insulation boots & link Caps

  • 2.6.1 Battery terminals covered with insulation boots or link caps as specified.

  • 2.6.2 Battery terminals sealed with petroleum jelly. (Only applicable for batteries in battery pit)

2.7 Temperature sensor cable

  • 2.7.1 Temperature sensor cable has been connected to the specified battery terminal

2.8 Battery sensor leads

  • 2.8.1 Battery sensor leads checked for correct connection

3 Site

3.1 Slab/Footpath contouring

  • 3.1.1 Slab/Footpath contouring performed correctly

3.2 Pits

  • 3.2.1 Pits installed correctly (conforming with surrounding landform)

3.3 Pit lids

  • 3.3.1 Correct pit lids fitted

3.4 Pipe / Conduit Sealing

  • 3.4.1 All pipes / conduits sealed in pits - temporary sealing for distribution pipes, permanent sealing on electrical conduits

3.5 Site cleaning

  • 3.5.1 All packaging and rubbish removed from site

3.6 Trenches

  • 3.6.1 All trenches backfilled & compacted

3.7 Formwork

  • 3.7.1 All concrete formwork removed from site

3.8 Hazards

  • 3.8.1 Site is left clean and free of public hazards

3.9 Concrete Quality

  • 3.9.1 Slab concrete quality is good (no powdering)

3.10 Slab surface

  • 3.10.1 Slab surface is broomed with tooled edge

3.11 Pooling

  • 3.11.1 No pooling on slab

4 Earth Resistance Testing

  • Refer to work instruction 8AM 49160 0062 ASZZA for specifications on earth testing

4.1 Communications Earth System

  • What was the resistance of the communications earth system? (Ohms)

4.2 Electrical (Protective) Earth

  • What was the resistance of the electrical (protective) earth? (Ohms)

4.3 Combined Electrical (Protective) and Communications Earth

  • What was the resistance of the combined electrical (protective) and communications earth? (Ohms)

5 Documentation Submitted (left on site)

  • The following documentation has been submitted and one copy left on site.

  • 5.1 Installation check list

  • 5.2 Record of battery cell voltages

  • 5.3 Battery Assurance Release Note

  • 5.4 Marked up site plan

6 Electrical Details

  • 6.1 Electricians Name

  • 6.2 Electricians License Number

7 Power Isolation Point Details

7.1 The Power Isolation Point is:

  • 7.1.1 a) a Pole Mounted CTB

  • 7.1.2 b) a Power Pedestal

  • 7.1.3 c) a Fuse Panel Insert

7.2 The Power Isolation Point is located on

  • 7.2.1 a) the right side of the housing

  • 7.2.2 b) the left side of the housing

  • 7.2.3 c) on the same side of the road

  • 7.2.4 d) on the opposite side of the road

7.3 The distance between the housing and the Power Isolation Point

  • Indicate the distance in metres (m)

Non Conformance Report

  • Record any Non Conformances. Any non-conformances must also be noted on non-conformance register

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.