Title Page
-
Conducted on
-
Prepared by
-
Location
Attendance and ppe
-
please attach photo of weekly singing in sheets
-
Are all members of team wearing the correct ppe
-
ask Arc Site manager to toolbox talk and photo signed copy.
-
-
Are harness required
-
Are all harness checked and safe for use
-
Stop work from harness until the correct ppe is supplied
-
Has the correct fall arrest or fall restraint System been supplied
-
Stop work and ask for the correct ppe
-
Has a risk assessment been produced for harness use
-
Stop work until risk assessment has been amended
Scaffolding
-
Is the scaffolding safe for use
-
Don’t allow operatives on roof Ask site management to provide a safe working system for our operatives and take photos
-
Are toe boards in place to stop falling debris and materials and take photos
-
Ask site to arrange scaffolders to install
-
do the loading bays look fit for purpose
-
Ask site management to check
Materials
-
Are materials stored on roof level
-
Make sure operatives Sore materials in a safe manor protect materials from rain and ballast
-
Proof of All materials on roof
-
Make sure materials are stored in a safe manor and protected for rain
Roofing works
-
Photos of all flat flooring works
-
Photos of completes up stands
-
Number of outlets complete
-
Photos of outlets
-
Number of svp complete
-
Photos of svp complete
-
Any issues holding us up
-
Do we require more materials
-
Make a list of the materials
Balconies
-
Amount of balconies complete since last audit
-
Any issues holding us up
-
State the balcony flat numbers and photos of the issues on site
-
Do we require materials
-
Make a list
Roofs balconies or green roofs about to start
-
Photos of next roof ready to start and markup on the Ariel plan
-
Do we require materials
-
Start requisition process
-
Do we have labour appointed to the task
-
Let senior contracts manager know
-
Any issues holding us up from starting on.
-
-
Take photos of the issues h
-
Do we require new risk assessments
-
Go through H&s pre start system in place
Completed roofs
-
Amount of left over materials
-
Are leftover materials going onto next roof ready to start
-
Make a note of all materials for collection
-
Are all materials protected stored downstairs ready for collection
-
-
Are all materials off roof ready for collection
-
Has the roof been leak tested
-
Does the roof require a revisit