Title Page
-
Document No.
-
Audit Title
-
Client / Site
-
Conducted on
-
Prepared by
-
Location
-
Personnel
4.1 General Energy Control
-
4.2 Site specific procedures include provision for type of energy sources to be isolated, control required for the activity, communication, group lockout and authorization of personnel
-
4.3 Site specific procedures include provision for one or more shift changeovers
-
4.4 Isolation is achieved by the use of locking devices, physical barriers or separation
-
4.5 Personal locks are uniquely keyed (i.e. are not a combination lock)
-
4.6 Personal locks don’t have a master key
-
4.7 Each personal lock has only one key kept under the sole control of the lock owner
-
4.8 There is a compliant Lock Removal Process in place.
-
4.9 Isolation points are clearly labelled to identify the circuit or system they directly control
-
4.10 Lockout boxes and stations are available where required
-
4.11 All designated isolation points fitted with personal locking devices are tagged.
-
4.12 The tagging system includes the name and picture of the worker
-
4.13 Reason for isolation as well as date and time is clearly identified on the tag
-
4.14 Tags are highly visible to prevent inadvertent operation.
-
4.15 Zero energy state (ZES) is achieved (and tested) prior to commencing the required repair or maintenance activity unless involved in commissioning and troubleshooting
-
4.16 If live electrical work is being performed, the requirements of CSA Z462 or equivalent are followed
-
4.17 Multiple levels of sign off (at least two) are obtained where a zero energy state, a test/try of isolation, or use of a locking device is not possible.
-
4.1 Site specific procedures (including roles and responsibilities) have been developed, documented, and implemented for the control of hazardous energy
Commissioning and Start Up
-
4.18 There is a commissioning manager and start-up plan with clear responsibilities and actions including commissioning safety requirements
-
4.19 The commissioning and start-up plan defines division of responsibility between construction, commissioning personnel, and the client
-
4.20 There is clear communication between construction, commissioning and the client to ensure lockout program is effective
-
4.21 Daily coordination meetings are conducted to ensure affected personnel are aware of commissioning activities and their associated hazards
-
4.22 Decommissioned systems are identified by signage marked "DECOMMISSIONED" at all points of isolation and on the main system components.
-
4.23 Deficiencies on the project punch list and handover documents are managed following the project deficiency management procedure and the handover process
Corrective Actions
Audit Review
-
Operations Review
-
HSE Review
-
Supervisor Review