Information
-
Document No.
-
Audit Title
-
Site/Location
-
Conducted on
-
Site Supervisor
Risk Assessment
-
Has Site Owners/Clients been logged into or checked in with? Have permits been issued (e.g. ESB)
-
Have all Crew valid Passports relevant to the Project?
-
If lone working, have you contacted your Project<br>Manager to confirm your wellbeing prior to work commencement?<br>
-
Is there safe access and egress to all parts of Site and Works? Have slips/trips/falls been identified?
-
Is the ladder appropriate for the task or would another device such as a<br>platform ladder/ scaffold/elevated work platform be more appropriate?
-
Is there adequate access lighting to site, on access routes<br>& in cabins?<br>
-
Is there safe off-road parking and storage?
-
Is site adequately secured from unauthorized entry? Are members of the Public protected?
-
Is the work area tidy and well organized? Is there safe and neat storage ?
-
Do all workers on site have required PPE, including visitors with basic PPE (helmet, vest & safety boots)?
-
Is vehicle suitable for terrain and in safe condition? Are vehicle audits completed ?
-
Are staff trained and under supervision?
-
Does the work involve manual handling? Are Staff trained?
-
Are there hazardous chemicals or biological substances<br>e.g. asbestos, vermin, bird droppings, dead animals?<br>
-
Is all First Aid Equipment, R.F. /EMF Personal Monitors (Naralerts/Wristlets), RF Meters, Fire Extinguishers, FAPPE, Rescue Kits, Ladders, Gas Meter, or other equipment certified or calibrated in date?
-
Is the 1st Aid kit adequately stocked and a trained 1st Aider on site?
-
Work at Height/Rooftop
-
Will you be working at height? Including Rooftops
-
Are weather conditions suitable for safe work?
-
Is all F.A.P.P.E. tagged and suitable for the works? Is an in-date Fall Arrest system in place? Have you suitable sliders?
-
Is there an adequate emergency readiness plan in place, Emergency contacts details, first aid on site, hospital details, rescue kit in work zone at height etc?
Rooftop
-
MEWP/ Crane works?
-
Have pre use check equipment been carried out ? Have all “ buddy “checks been completed ?
-
Have Drop Zones or Exclusion Zones been set up under or around works?
-
Has a safe rope haul system been established? Is Haul rope, pulleys and equipment certified and inspected in- date?
-
Is work in close proximity to R.F. or EMF Hazards?<br>
-
Are there any unprotected edges or drops with no<br>handrails >950mm in height?
-
Are there fragile surfaces, skylights, hatchways, shafts or openings at person could fall through?<br>
-
Ladders Use
-
Are working platforms / ladders been pre / periodically inspected are tags present/ in date.? Are ladders in good<br>order & safe to use?<br>
-
Have ground conditions and surrounding environment eg stable ground & overhead wires been considered before<br>use?<br>
Plant/Machinery – MEWP/Crane/Excavators
-
Is on-site plant safe to use?
-
Are Crane Lift Plans in place, and Lifting Equipment (incl<br>HIAB) & gear certs in date?
-
Is a MEWP in use and Certs in date?
-
Are hard barriers around plant?
-
Is reach Plant (e.g. cranes, MEWP) suitably earthed?
-
Proximity to High Voltage Overhead Power-lines?
-
Are Traffic Management Plans required and set up?
Electricity
-
Is there a suitably qualified person on-site to work on<br>electricity?
-
Does work involve Electricity? Is it safe?
-
Does work involve Battery handling?
Sign off Checks
-
As PICW what site specific H&S issues were discussed with the crew before works commencement, if lone working what issues were accessed before commencement?
-
Are H&S Plan, Method Statement and Risk Assessments adequate given the present circumstances on site?<br>Considering previous days works or changed site conditions<br>
-
RAMS (Risk Assessment & Method Statement) for the job has been read and understood by all?
-
Any Additional Risk Identified not captured in assessement?
Sign Off
-
P.I.C.W