Production Activities
-
Was the handover from the previous supervisor detailed and was the work area clean?<br>(Photos should be taken to support statements. Handover to cover off on WHSE, Operations and BAU details)
-
Have you reviewed the next day wave requirements and inbound registers to determine staffing level requirements?<br>(This should be based on measure cycle times to TAKT time measurements)
-
Have you conducted the daily toolbox talk?
-
Summarise the main discussion points.
-
Have you received an acceptable number of 5S checks and is your SHINE Plan up to date?<br>(WHSE staffs to set the level requirements)
-
Have all cycle counts been completed?<br><br>
-
Summarise the number of counts required on shift vs the actual number completed.
-
Have the staffs in attendance today, been validated against the roster and output production forecast model? (Note: To be completed by 08:30am daily)
-
Have all staff time sheets been revised for accuracy, validated and submitted?<br>(Detail any staff anomalies - eg. Unauthorised absences. Note: details to be entered into TMS by 08:30 daily)
-
Was overtime observed during the review of time sheets, authorised by you?
-
Do you have excess staffs today based on the production throughput requirements, that can be utilised in other BAU areas.
-
Have the previous day's waves been completed and finalised?<br>(Has corrective action processes been implemented or initiated to rectify the outstanding orders and have the corrective actions been date stamped)
-
Have goods returned, been allocated to the correct process required and located in the correct location?<br>(Damaged pending Samsung response)
-
Have all DFN's been moved to the correct location?<br>(DFN staging; DFN holding)
-
Have all inbound containers been processed and received into WMS?
-
Have putaways been processed and correctly located? (Including any GR'd DFN's)<br>(A visual and systems check should be conducted on each shift with the focus placed on those items carried over from the previous shift)
-
Do all current outstanding operational production issues have a detailed 'history' attached that is time stamped for process measure ability. Do these detail the corrective actions undertaken?)
-
Has the daily production outputs been reviewed for MHE numbers requirements?
-
Has the MHE required for shift been checked for charge and serviceability? <br>Supervisor to confirm prior to shift departure that the team has physically checked the MHE and scanners)
-
Have all allocated RF scanners been accounted for have you confirmed that staffs are signing the register for RF use?
-
Are all RF scanners serviceable?<br>(If broken during the shift, raise a ticket on IT for action)
Training
-
Has RF training been conducted within the last month?
EOS (End of Shift) Process requirements
-
Have all orders (Open Orders Report) that can be processes, been finalised?<br>(Physical inspection required by supervisor at EOS)
-
Have all item movements been recorded and accounted for?<br>(A visual inspection of documentation required by supervisor)
-
Has all transportation documentation been prepared correctly and IAW customer requirements - consignment notes?<br>(Visual inspection required by supervisor to confirm)
-
Have all paradigm entry requirements been emailed to the WHSE team?
-
Summarise any paradigm events that occurred on shift
-
Has the paradigm on line register been reviewed to close out any outstanding action items?<br>(Inform WHSE staff of any actions taken)
-
Has the assigned work area and operational space been inspected for cleanliness and 5S compliance?<br>(Physical inspection required with corrective actions to be implemented before shift dismount)<br>(Bins and or other refuse receptacles are to be empty and any empty pallets to be placed on allocated external stacks)
-
Has all MHE been put away in the correct location and placed on charge?<br>(Visual inspection required for compliance)
-
Was any MHE equipment damaged during the shift? If damaged by a labour hire staff member, this cost can be recovered. Ensure details are captured.
-
Summarise the damages to equipments
-
Photos of damages to equipment required to support the document
-
Was any client or customer stocks damaged during the shift?
-
Summarise any client or customer damages
-
Photos required in support of statement of damages to stocks
-
Was any pallet racking damaged during your shift?<br>(Are the beams still within allowable deflection tolerances?)
-
Details on the damages required
-
Photos required of damaged racking and location
-
Has any damaged racking been marked with a red spray ink 'X'.?
Continuous Improvement
-
Did any 'POP' suggestions present themselves during the shift?<br>(Are they worthy of escalation? Supporting statement, photos, graphics required)
-
Details of POP
-
Photo of POP if within context
-
Drawing to explain the process or topic
-
During the shift, has anyone identified a 'better way' proposal for BAU basics?<br>(Supervisor to canvass staffs for input regularly)
-
Better Ways suggestion to be put forward.
-
Were there any significant events during the shift that were considered noteworthy?<br>(These could be be good or bad... Morale affecting)
-
Event details
-
Have you prepared a detailed handover for the oncoming shift supervisor?<br>(Summary should include WHSE events, operations and production briefs and BAU detail)
-
Summary of handover details
Safety additional items
-
Are emergency exits unobstructed, clearly marked and visible?
-
On review, are all bulk stack loads stable and located within the correct zone?
-
Printed name and signature required in support of comments and actions