BCaR inspections - Procon Projects

  • Site conducted

  • Conducted on

  • Prepared by

  • Location

Inspection Schedule

Factory Inspections - External Walls

  • Material in walls is correct (plasterboard, Glassroc, insulation, etc..).

  • Pattressing in place, where required.

  • Any damage to external cladding.

Factory - Internal Walls

  • Material in walls is correct (plasterboard, fire breaks within walls are correct, insulation, etc..).

  • Letterboxing in fire walls constructed correctly.

  • Pattressing in place, where required.

  • Location of sockets in walls in correct position (Reset buttons in disabled in correct position.

  • Where 300mm leading edge required on certain doors as per DAC requirements identified on DAC plan.

Factory - Floor Construction

  • Material used in floor are correct (Cemrock, insulation, VCL, etc..).

  • Sufficient fixing in the floors.

External Windows & Doors

  • Cill heights correct to drawings rooms, corridors & toilets areas.

  • Cill heigh for Smoke vent woindows 1100mm and opening in sash correct.

  • Correct size windows installed according to schedule & daylight analysis.

  • Are all the restrictors fitted in accordance with Purge calculations. FF bottom sashes restricted to 100mm

  • Correct ironmongery installed to external doors (**mag locks/keypads by electrical contractor).

OnSite - UAWC Rooms

  • Layout is as per part M and identified diagram as per floor plan.

  • Shelves are fitted as per part M.

  • Sinks have overflow and plugs.

  • Handrails fitted as per part M.

  • Doors has all correct ironmongery horizontal rail, coat hook & correct lock.

OnSite - Standard Cubicles - Vanity Units

  • 450mm turning circle within cubicle between door and edge of toilet as per part M requirement.

  • Has the vanity unit a lower sink area and the handrails fitted.

  • Mirrors fitted.

  • Is the vanity unit fitted in correct location - as drawing.

OnSite - Ambulant and Enlarged Ambulant Cubicles

  • If no close coupled toilet cystern in room - Shelves are fitted as per part M

  • WC is at 480mm to top of seat.

  • Coat hooks installed.

  • Handrails fitted as per part M.

Part M Toilets/Shower or Changing rooms

  • Layout is as per part M and identified diagram as per floor plan.

  • Shelves are fitted as per part M.

  • Mirrors are fitted as per part M.

  • Sinks have overflow and plugs.

  • Handrails fitted as per part M.

  • Doors has all correct ironmongery horizontal rail, coat hook & correct lock.

  • Shower hose in correct location.

  • If heights adjustable sinks are required.

  • Changing bed required and in correct location.

  • Is there a floor drain required.

  • Shower enclosure fitted if required.

  • Has the seat in the shower been fitted?

  • Is there a requirement for more than 1 pull cord.

  • Is there a host required

SEN Classbase Classrooms:

  • Has the FF&E been fitted according to the plans.

  • Have high level locks been fitted to the internal doors?

  • Are the lower locks to internal door escape locks?

  • Are the cylinders in the internal door keys both sides?

  • Is there slip resistant flooring in front of the sink on the FF&E?

  • Have locks been fitted to the cabinets in the FF&E including the sliding doors?

  • Has access control been fitted to the external doors?

  • If this is primary school has a dedicated drinking water tap been fitted.

  • Has dado trunking for the teacher desk location been fitted in the correct position?

Standard Classrooms:

  • Has dado trunking for the teacher desk location been fitted in the correct position?

  • Are the internal doors fitted with apartment locks - escape over ride handles?

  • Are the cylinders in the internal door keys both sides/half cylinders?

Specialist Classrooms:

  • Has dado trunking for the teacher desk locationbeen fitted in the correct position?

  • Are the internal door apartment locks - escape over ride handles?

  • Are the cylinders in the internal door keys both sides or half cylinders?

  • Is the FF&E layout correct, according to the framework spec the rooms were tendered for.

  • Is there a requirement for locks to be fitted to any of the FF&E according to the framework spec the rooms were tendered for.

OnSite - External Windows & Doors:

  • Are all windows opening correctly i.e. not catching?

  • Are all the restrictors @ 100mm to FF bottom sashes?

  • Are the external doors operating correctly?

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.