1. Site Presentation & Welfare
-
Statutory Notices displayed
-
Previous remedial actions dealt with. - Please comment
-
Detail actions taken.
-
Temporary Signs being displayed
-
Temporary Works
-
Availability of drinking water?
-
Washing / Toilet conditions?
-
Canteen Conditions?
-
Record of site operatives and CSR card numbers ?
-
First aid facilities / boxes stocked / First aider's availability ?
-
Personnel / Inducted - Random check completed ?
2. Personal Protective Equipment
-
Has adequate PPE been provided?
-
Is PPE worn where mandatory or where required?
-
Is suitable clothing provided for the conditions (weather) ?
3. Working Areas
-
Materials stored correctly / waste disposed of properly and timely ?
-
Safe access and egress to the workplace?
-
Barriers / Warning signs, site security, etc in place ?
-
Adequate lighting ?
4. Scaffold / Tower Scaffold
-
Is scaffold or tower scaffold in use?
-
On a firm base, linked and secured?
-
Proper access / Egress ?
-
Handrails / Toe boards (150mm) / Guardrails (910mm)?
-
Being used correctly and in good condition?
-
Erected, altered and dismantled by competent and trained persons?
-
Scaff Tagg in place and signed-off every seven days
-
Insert Photo of Scaffold inspection and scaff tag.
-
Wheels locked in position? (Tower Scaffold)
5. Ladders
-
Are any ladders being used ?
-
Condition / Length / Angle of use?
-
Tied / Footed / Secured / Resting on a sold surface?
-
Correct use - 3 points of contact - correctly positioned?
-
Sufficient height above landing place?
-
Registered and inspected?
-
Are A frame step ladders being used? (confined area)
-
Is there appropriate permit in place?
6. Working at Heights
-
Are there any working at height tasks this week?
-
Barriers / Edge protection adequate?
-
Proper equipment being used ?
-
Is adequate protection provided for fragile roof surfaces?
-
Are crawling boards / ladders provided and used?
-
Proper access / egress to heights?
-
Are Mewp's been used?
-
MEWPs - Use, trained personnell
-
MEWPS being used on level & firm ground
-
MEWP test certs in pace and fit for purpose
-
Boom lift - Used by trained operatives only
-
Boom lift - test certs in place
-
Boom lift used on firm and level ground only
-
MEWP & Boom lift operatives harnessed off with correct harness and anchor point
7. Power Tools / Air
-
Power tools / leads / plugs / sockets - General condition ?
-
Tools maintained / PAT tested ?
-
Compressed air used correctly ?
-
Air lines not leaking ?
8. Plant / Equipment
-
Is there any mechanical plant on site in use this week?
-
Is the plant or equipment fit for purpose and required Procon sticker attached?
-
Has the weekly plant inspection taken place by the contractor/operative?
-
Insert photo of the weekly inspection.
-
Are all statutory inspections up to date?
-
Has all plant and equipment been risk assessed?
-
Have safe systems of work been devised and posted where needed?
-
Is plant and equipment serviced and maintained and weekly inspection sheets filled in?
-
Are operatives trained in the use of plant or equipment
-
Have they provided training certification for plant & equipment being operated?
9. Plant / Lifting Appliances
-
Are there any craning/lifting operations this week?
-
Relevant test certificates and licenses in place ?
-
Slings / Shackles / Clamps - General condition ?
-
Are all lifting equipment and accessories registered?
-
Is there lifting plans in place for lifting operations ?
-
Are cranes only operated by trained employees?
-
Have all statutory inspections taken place?
-
Is the right equipment being used in the right manner ?
-
Planing and preparation of lifting operations
10. Hazardous Substances
-
Hazardous substances identified and controlled?
-
Safe bunded storage /hazardous waste safely removed ?
-
Correct PPE and precautionary measures and signs in place ?
-
Are safety data sheets / COSHH assessments in place ?
11. Fire & Emergency Procedures
-
Fire safety Plan current
-
Hot works permit operating
-
Fire extinguishers in place, full and available ?
-
Alarms warning devices tested
-
Emergency routes / Exits clear of materials / debris?
-
Fire Brigade Access Clear
-
Clear Access for other Emergency Services
-
Flammable materials / liquid storage and signs ?
-
Gas / pressurized cylinders upright & secure ?
-
Welding screens / Blankets available ?
-
Visitors / Contractors information in place ?
-
Safe storage and removal of combustible materials ?
12. Documentation
-
Safety policy / H&S law notice / Insurance displayed?
-
Safe systems of work / risk assessments available ?
-
COSHH assessments / safety data sheets available ?
-
Tool box talks happening ?
-
Accident reports - updated ?
-
Training Requirements Identified
-
Permits to Work – Hot Work, Confined Spaces, etc.
-
Method Statements/Risk Assessments Produced & Communicated
-
Night/Special Working Required
-
NI10 / F10 in place if required and posted on the notice board ?
-
Sign-in sheets maintained and recorded
-
Emergency evacuation plan in place and posted on notice board ?
13. Noise, Vibration & Dust
-
Is suitable ear protection provided and worn
-
Is suitable PPE & RA in place for all vibrating tools ?
-
Is there suitable PPE and suppression provided when working with dust ?
14. Traffic Management
-
Road conditions
-
Are vehicles and people kept separate wherever possible ?
-
Is there adequate space for safe vehicle movement?
-
Is plant and machinery only operated by trained persons ?
-
Are loads on tele-handlers secure and driven in a safe manner ?
-
Are passengers prevented from riding on forklift trucks ?
-
Is there a traffic management plan in action ?
-
Is it posted for all operatives to see?
-
Is it being followed by all plant, machinery and deliveries ?
-
Are banksmen being used ?
15. Environmental
-
Is the site maintained in a tidy manner ?
-
Are the materials and waste stored and disposed of correctly ?
-
Are all waste transfer notes held for further reference ?
-
Are recyclable materials segregated from general waste properly ?
-
Is there a system in place to prevent energy waste, e.g lights and machinery off when not in use , prevention of air leaks etc?
-
Quality checks for incoming goods
16. Temporary Works
-
Are temporary works appointment letters on file
-
Is the Register up to date?
-
Is the Temporary Design being followed
17. Demolitions
-
Demolition plan in place
-
Demolition carried out safety
18. Covid -19
-
Temp Checks being carried out
-
Medical Questionnaires
-
Social Distancing
-
Hand Sanitisation
-
Face Coverings
-
Weekly Inspection sign off.
Weekly Record of Hours Worked
-
Hours worked by directly employed personnel
-
Hours worked by subcontractors inc labour only
-
Total Hours worked
Weekly Safety Return - Notes Sheet.
-
Results of Inspection - Risk factor
-
Action Proposed or Taken
-
Date actioned
-
Signature
-
Action Proposed or Taken
-
Date actioned
-
Signature
-
Action Proposed or Taken
-
Date actioned
-
Signature