Audit
Job Number
Job Name
Report Prepared By
Floor
Area
Room/Corridor
Layout and sizing verified with contract and shop drawings?
Pipes Straight and Square?
Brazing or soldering is visually inspected?
All valves and components lead free as required?
All valves and components accessible?
Balancing Valves are installed on hot water return?
Check Valves in correct direction/position?
All future valves installed and capped?
Back flow preventers installed at 5' AFF or less
Back flow drain installed/ran to floor sink?
Piping has been hydro tested per spec?
Inspection drawings are up to date and signed?
Water hammer arrestors/trap primers installed?
Access Panels are laid out?
Dissimilar metals have been isolated?
Hangers installed at locations/spacing per spec?
Hanger size and model per submittal?
Vertical hanger rods are plumb?
Inserts and Shields are installed on Hot Water if required?
All hanger rod nuts and cross bolts are tight?
Seismic/Sway bracing installed as required?
Piping secured per spec and is not loose
Dissimilar metals have been isolated?
All stub outs are secure?
All stub out heights have been verified?
Riser clamps are installed as required?
All fixture backing installed as required?
Insulation installation complete per spec?
Shields and inserts installed if required?
Fire/sound caulking is installed correctly?
Labels and directional arrows are correct?
Notes, Impacts, or Comments: