Information

  • Audit Title

Project Details

  • Inspection Date

  • Site Name

  • Site Address

  • SP/WO, Network

  • Staff Attending Site

  • Contact Details

  • Designer Name

  • Contact Details

  • Alternate Contact

Material and Site Delivery

  • Does the Top Hat Cabinet proposed location meet standards? Document number 010259W04

  • Is the Cabinet casing in good condition?

  • Is the DSLAM cabinet damaged- Check CCF, Check MEC, Check Locks on all doors, Check for ants nest etc<br>Document AKD-4386

  • Are all Pits installed at the cabinet location clear and level with the ground?

  • Is the Pillar in good condition for upgrade? (only required if new copper to be installed)

  • Is there parking for delivery truck? Note the parking requirements for the site

  • Are there any overhead obstruction. (Trees, power, lights etc)

  • Is there a presence of Asbestos in the pits where work is proposed?

  • Comments:

Photos & Standard Measurements

Site Delivery Point

  • Show the surrounding area from North, South, East & West. Also above.

  • Comments

Proposed TOP HAT & DSLAM Cabinet

  • Show the surrounding area from North, South, East & West of the cabinet. Trees and vegetation surrounding the proposed site location

  • Document & Photograph any damage to cabinet internal and external

  • Comments

Area of proposed Infrastructure/ Suite Build

  • Telstra Pit/Manhole

  • Closest Cross Road

  • Vegetation

  • Effect Customers

  • Back of Kerb or Fence line to proposed cabinet, >300mm

  • Nearest Power supply

Test the lean on the existing cabinet

  • Photo

  • Comments

  • The existing housing shall be within 50mm of level measured from the top of the housing to the bottom. Using a plumb bob, no more than 50mm lean from top to bottom corner.

  • * If this check fails then complete this section and advise David Stanley and the planner for a repair solution and cost approval via e-mail.

  • Is the cabinet on a lean?

  • Measured lean is __ mm

Measure distance to other structures

  • Minimum distance from rear of RIM/DSLAM cabinet to fence is 300mm.

  • * If this check fails then complete this section and advise David Stanley and the planner for a repair solution and cost approval via e-mail

  • If FAIL – Measured Minimum distance __ mm

  • Photo

  • Comments

Proposed Fibre FAP/s Joint

  • Show ports available

  • Show TAGS on proposed fibre sheath

  • Comments

Pillar Details (If required on project)

  • Pillar Location surroundings

  • Pillar with casing removed

  • Spare cable ports

  • Manhole & Pits (opened & closed)

  • Copper Joints

  • Comments

Fibre & Copper Conduits (If required on project)

  • Existing congested conduits

  • New conduits route and manhole/pit entry

  • Comments

Existing DSLAM

  • Show cabinet closed

  • Show Cabinet opened

  • Show any damages

  • Comments

Provide additional feedback

  • Photos

  • Comments

DSLAM Top Hat information

DSLAM Top Hat Site Survey Rack and Infrastructure Details

  • Site Name

  • Exchange ESA code

  • DSLAM RAU Code

  • Pillar ID

  • Copper Range

  • Cutover Joint Location

  • Top Hat port count

Proposed Fibres from ESA (Exchange end):

  • Exchange

  • F/S/R

  • Sheath ID

  • Fibres

Splicing

  • Fibre Splicing Locations

  • Comments

Build

  • (1) Is the Top Hat site clear of obstructions? (Maximum height of cabinet with Top Hat is 2.07m)<br>

  • If No, What type of obstruction

  • Can this obstruction be cleared? Please provide reason

  • (2) Is the DSLAM sturdy and level<br>

  • If No, What are the issues

  • Type of fibre is feeding the DSLAM from last FAP?

Additional details

  • Please provide details for additional preparation work for the Top Hat installation

Cabinet/Pillar Location information

  • (1) Is there any work required at an existing cabinet or pillar?

  • if ‘YES’ are there any obstruction preventing the increase to cabinet/Pillar size

  • Are there spare ports in the Cabinet or Pillar? (How Many?)<br>

  • (2) Is there sufficient space in the Cabinet feeding pit for an additional OJ?

  • (3) Please record any details not requested above and may be of interest for future design

  • (4) Are there any Environment issues visible

  • if ‘YES’ what are they?

  • (5) If new copper to be hauled is there any conduit to be upgraded due to congestion between the DSLAM and the Cabinet/Pillar - Nominate the congested conduits

Power Supply Info (to be used for Metering Pedestal)

  • All Victorian Top Hats will require a metering pedestal. Other states need only use this page if a new Green Boy Pedestal is to be installed.
    All measurements are to be accurate with a wheel or tape measure.

Site information for power supply - Underground

  • Power Pit Supply Location

  • Distance from Top Hat

  • Distance to Nearest cross road

  • Distance from nearest structure (Not DSLAM)

  • Distance from Back of curb

  • Green Boy Measure from Cabinet, power pit & BOC

  • Location of nearest Aerial power

Site information for power supply - Aerial

  • Power Pit Supply Location

  • Distance from Top Hat

  • Distance to Nearest cross road

  • Distance from nearest structure (Not DSLAM)

  • Distance from Back of curb

  • Green Boy Measure from Cabinet, power pit & BOC

  • Location of nearest Aerial power

Second Power Pit

  • Is there second power pit within 100m

Site information for power supply - Underground

  • Proposed Pit Supply Location

  • Distance from Pit - Top Hat

  • Distance from Pit to Nearest cross road

  • Distance from pit to nearest structure (Not DSLAM)

  • Distance from pit to Back of curb

  • Green Boy Measure from Cabinet, power pit & BOC

  • Location of nearest Aerial power

Site information for power supply - Underground

  • Proposed Pit Supply Location

  • Distance from Pit - Top Hat

  • Distance from Pit to Nearest cross road

  • Distance from pit to nearest structure (Not DSLAM)

  • Distance from pit to Back of curb

  • Green Boy Measure from Cabinet, power pit & BOC

  • Location of nearest Aerial power

Other Information

  • Supply the closest aerial power pole location? HV,LV or HV & LV

  • Addition Power information or comments

Optical Fibre Table

Line System

  • Line System

  • A End

  • B End

  • Circuit

Optical Fibre Table

    Optical Fibre
  • Site

  • Work Required

  • Connect From

  • Location From

  • Conn Type

  • Length

  • Conn Type

  • Location To

  • Connect To

Additional Optical Infrastructure

  • Are Additional Fibre sheaths available

  • ESA

  • Sheath ID

  • Fibre Count

  • Vacant Fibres

  • New OF Joints

Additional Data

  • Additional Data

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.