Information

Project Details (Completion of all of the following fields is mandatory. Forms submitted without all fields completed will not be assessed.)

  • Audit Title/Project Description

  • Design Pack ECB Link ID (eg. ABC-1234)

  • Work Parcel/Contract No.

  • Separable Portion No.

  • Order No.

  • Site Address
  • Project Manager

  • Team Manager

  • Authority Number

  • Installer Name

  • Installation Date

Section 1

Superstructure

  • a. Wall bars correct height

  • b. Superstructure isolation material installed correctly

  • c. Superstructure correctly mounted and assembled

  • d. Top iron/tie bar spacing correct and aligned over centre line of suite

  • e. Suite support frames mounted at correct intervals & vertical (within 5 mm)

  • f. Protectors fitted to U bar ends

  • g. Cable runway mounted correctly

  • h. Power cable tray mounted correctly

  • i. Lighting correctly installed

  • j. Metal chips, dirt etc cleaned from work area

  • k. Surface treatment of superstructure undamaged

  • Ref: TM00011 CN1234 CSD 26203

  • *Mandatory photo required - Fairly wide shot of the whole rack, may need to use arrows to highlight where your rack is.

Section 2

Superstructure Safety Rails

  • a. Safety Rail Installed correctly

  • b. Landing gate self closes

  • c. “helmet ”warning plate attached

  • d. Access ladder correctly installed

  • Ref: TM00011 CN1234 CSD 26203


  • *Mandatory photo required - Superstructure access ladder

Section 3

Type 04 Rack DWDM Expansion (Vendor Value Add)

  • Photo of rack before installation of S/Rs.

  • a. Correct Rack Layout delivered eg, Layout 240

  • b. No damage to rack (structural /paint /plating)

  • c. Subrack mounting rails in the 170mm mid-mount position

  • d. All cage nuts installed as per rack layout

  • e. PDP installed as per rack layout

  • f. Fibre storage tray/s as per rack layout

  • g. Subrack support bar installed as per rack layout

  • h. ESD socket installed in SU21 or SU22 LHS only

  • i. Correct Earth tree fitted

  • Ref: Design Pack TM00046 Iss 6 TAF0001-232593[1]_Installation Addendum TAF0001-118783(8) Rack Layouts



  • *Mandatory photo required - Rack photo showing rack at delivery.

Section 4

Type 04 Rack DWDM Expansion Top photo

  • a. Scratches, exposed rivets covered with supplied patches

  • b. Rack installed in the correct floor position

  • c. Rack installed at the same s/structure height as adjacent racks

  • d. Rack level and plumb (check with spirit level)

  • e. Rack securely attached to superstructure or wall using correct mounting kits and earthing practices

  • f. High superstructure kit “thick washers installed below RH C-channel”

  • g. SDH / Non SDH racks isolated (undamaged paint provides insulation) <br>

  • h. Rack earthed to SRPP or MSRPP cable via flying lead & IPC connectors correctly torqued

  • i. Rack connected to site optic ducting with 2 x 50mm convoluted tubes (LHS)

  • j. Rack ducting / Convoluted tubing correctly mounted and as straight as possible secured with minimal cable ties

  • k. Convoluted tube enters rack by approximately 65mm (clears the top tongue of the rack optic duct) and is tied to the rack optic duct using both anchor points<br>

  • l. Rack labelled with SRPP label

  • m. Rack labelled with rack header label

  • Ref: Design Pack TM00046 Iss 6 TAF0001-232593[1]_Installation Addendum

  • *Mandatory photo required - Photo of Expansion rack top half with superstructure connection

Section 5

Type 04 Rack DWDM Expansion Bottom photo

  • a. Vertical Rack optic duct position adjusted to 80mm

  • b. Hook & Loop pads fitted to the rear of the rack optic ducts as per Rack Layout

  • c. Fibre storage tray guide clips installed in correct positions

  • d. Rack correctly located over floor tiles (raised floor only)

  • e. Rack securely bolted to floor, using supplied anchors & feet set at 45 degree angle to frame edges

  • Ref: Design Pack, TM00046 Iss 6, TAF0001-232593[1]_Installation Addendum

  • *Mandatory photo required - Photo of Expansion rack bottom half.

Section 6

HC-PDP (Vendor Value Add)

  • a. HC-PDP installed in the correct position and secured correctly

  • b. 40A CBs installed to power subrack

  • c. Secondary power terminations secure with no bare copper exposed

  • d. Secondary power cables labelled in HC-PDP, label has correct orientation away from termination point

  • Ref: TM 00046 A01

  • *Mandatory photo required - Photo of HC-PDP at delivery. Alarm wires are not Vendor Add.

Section 7

HC-PDP

  • a. Anderson connectors for each primary feed RF1 & RF2 cable tied to prevent accidental pulling apart

  • b. Correct alarm cable and colour code

  • c. Alarm cables terminated correctly on Krone Terminations

  • d. Alarm priority switches set to correct position

  • e. No Excessive Cable Lengths in APDP

  • f. No permanent alarms on APDP

  • g. APDP Subrack label correct size

  • h. Label subrack Position correct format

  • i. RF1 & RF2 , Fuse / Breaker Location correct format

  • j. Circuit Breaker designation for relevant subracks

  • k. Correct ACCADS/TESAMS alarm IDF location

  • l. ACCAD/TESAMS Alarm IDF labelled

  • Ref: TM 00046 A01

  • *Mandatory photo required - Close up Photo of front cover label and panel

Section 8

Rack Primary Feed Cables

  • a. Rack power cables correct size (16mm2)

  • b. Rack power cables segregated from the LOD Primary Power 150 mm2 cables

  • c. Rack power cables contained within the power tray

  • d. Cables not damaged/ against a sharp edge

  • e. Rack feed A& B fed from different s/racks/planes but same CB position (unless specified in Design Pack)

  • f. Power cable lugs crimped correctly/ securely at LOD

  • g. Heatshrink on all lugs

  • h. LOD CBs correct type and rating

  • i. LOD CBs securely fitted on “Din” rail

  • j. LOD CB Locking clip is in the “closed” position

  • k. Rack feed cables labelled at APDP end (RF1 & RF2)

  • l. Rack feed cables labelled at LOD

  • m. LOD labelled for correct CB allocation

  • Ref: CSD 26204

  • *Mandatory photo required - Photo of primary connections at distribution point

Section 9

DWDM Expansion Subrack

  • a. Subrack installed in correct position as per rack layout

  • b. Power cables run correctly down RHS of rack.<br>

  • c. Bridge cables run correctly down RHS of rack

  • d. Subrack label location and data correct

  • e. Laser warning labels fitted to outside of hinged fibre cover

  • f. Fibre pinching warning labels fitted to inside hinged fibre cover

  • g. Subrack earthed correctly

  • Ref: TAF0001-232593[1]_Installation Addendum

  • *Mandatory photo required -Photo of Expansion subrack

Section 10

DWDM Expansion Subrack RHS LTU area

  • a. Power Cables not too long/short at LTU end

  • b. Subrack power terminations correct and secure

  • c. Bridge cabling routing correct, neatly run & secured with cable ties (cut flush)

  • d. Card modules securely installed in the correct slot as per supplied Inventory sheets

  • Ref: TAF0001-232593[1]_Installation Addendum

  • *Mandatory photo required - Photo of power and bridge cable connection field

Section 11

DWDM Expansion Subrack Optical Fibres

  • a. Optic cords correctly run and maintained at the rear of the rack optic duct with Velcro ties

  • b. Minimum bending radius of 30mm maintained for all optic cord bends

  • c. Fibres run correctly in S/R fibre trays – no extra length stored at this point.

  • d. Line/External optical fibres labelled with port number and direction, EQ IN or OUT

  • e. Internal interconnect optical fibres labelled with correct factory labelling

  • f. All optic interfaces LCPC checked for cleanliness

  • Ref: TAF0001-232593[1]_Installation Addendum

  • *Mandatory photo required - Photo of subrack and fibres

Section 12

DWDM Expansion filter Unit

  • a. Subrack installed in correct position as per rack layout

  • b. Subrack label location and data correct

  • c. Optic cords correctly run and maintained at the rear of the rack optic duct with Velcro ties

  • d. Optic cords run correctly in subrack fibre guides

  • e. Fibres labelled with correct factory labelling

  • f. All optic interfaces SC checked for cleanliness

  • Ref: TAF0001-232593[1]_Installation Addendum

  • *Mandatory photo required - Photo of filter units

Section 13

MSRPP / SRPP

  • a. Single Point of Connection Bar marked as “SPC”

  • b. MSRPP / SRPP connected to the building earth only at one point SPC

  • c. CCB Bar mounted on insulated spacers

  • d. MSRPP/ SRPP has no direct electrical contact with non-SDH earth planes

  • e. Mechanical rack supporting is electrical insulated from superstructure

  • f. SDH superstructure is temporarily earthed for safety by a dedicated conductor to the SPC (typically16 mm2) Note: This to be removed once the first NON SDH rack has been installed and bolted to the superstructure

  • g. Bare copper ends of MSRPP / SRPP covered with heat shrink end caps

  • h. Common Collector Bar labelled with “MSRPP / SRPP”

  • i. Internal Common Collector Bar in Small Station SDH rack labelled with SRPP

  • j. MSRPP / SRPP label on Either End of CCB to SPC connecting cable

  • k. MSRPP / SRPP label at 1 Metre interval above/below equipment racks

  • l. MSRPP / SRPP label on either end of the SUITE cable

  • Ref: CSD 26204, 007334 Sect 5 Paper 1

  • *Mandatory photo required - Photo of rack earth connection.

Section 14

Optic Ducting

  • a. Duct installed as per design

  • b. Overhead fibre ducting correctly mounted

  • c. Duct level and centred above suite (where possible)

  • d. All joints fully pushed home and secure

  • e. No broken slots

  • f. All ducting is secure and supported both Horizontally & Vertically with no lateral movement

  • g. No internal protrusions

  • h. Ramp drop-offs correctly installed

  • i. ODF/OFDP drop-off correctly positioned

  • j. Ducting within alignment +- 5 mm

  • k. No Refuse/litter in ducting

  • l. Duct capacity not exceeded (50mm in 100,200 & 300mm duct)

  • m. Warning signs present

  • Ref: CSD 26203, TM00138 A01

  • *Mandatory photo required - Optical ducting

Completion

  • General Comments

  • This is the end of Photo Audit. Your audit result can be found under "Audits" menu. You can edit, preview and send your result via Email

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.