Hand over process.

  • No ARUP QA report previously issued?

  • Has the school received the Operations and Maintenance manuals?

  • Has the school been issued with the as build drawings?

  • Has the school received a copy of the Certificate of Occupancy?

  • Is the C of O displayed in the foyer?

  • Has the school been issued with all the warranties, guarantees, and contractor contact information?

  • Has the keys for the new building been keyed to the school system?

  • Has the contractor provided spares? Locks x1, ceiling tiles x 10m2, Carpet tiles x 10m2

  • Have all school raised outstanding issues been resolved?

  • Has the school signed the final Certification?

Roof

  • Is the use of mastic appropriate?

  • Has the drainage and overflow been installed to the plans and specifications?

  • Are rivets free of rushing?

  • Is the roof free from construction debrie?

  • Are the roof sheets free from rusting?

  • Are the open ends of the roof sheets filled in?

  • Are ends of the roof sheets turned down?

  • Is the cutting and trimming of the roof sheets well executed?

  • Is the flashing detail well executed?

  • Are leaf guards present?

  • Are roof fixings free of over tightening?

  • Are all down pipes correctly supported?

  • Is the mosquito mech installed to the rainwater tank?

  • Is there a first flush system fitted and is it accessible for maintenance?

  • Free from other roof observations?

  • Free from other roof observations?

  • Free from other roof observations?

  • Free from other roof observations?

  • Free from other roof observations?

External works

  • Have all hot water pipes been lagged?

  • Are external paving areas laid with suitable fall?

  • Are weep holes above external paving level?

  • Is concrete paving acceptable?

  • Has the Ableflex been installed between the building and paving?

  • Has Ableflex joints been finished with calking?

  • Has all construction derbies been removed from site?

  • Free from other external works observations?

  • Free from other external works observations?

  • Free from other external works observations?

  • Free from other external works observations?

  • Free from other external works observations?

Internal Works

  • Is the BMS operating correctly?

  • Have hand trapes been installed on large sliding doors?

  • Have all external doors been installed with correctly adjusted door seals?

  • Have all outlets, switches, emergency/exit lights, and data outlets been individually identified and or numbered?

  • Has an emergency lighting log-book been provided and completed with initial discharge tests?

  • Have RCD's been tested with trip times and inserted into a logbook?

  • Free from other internal observations?

  • Free from other internal observations?

  • Free from other internal observations?

  • Free from other internal observations?

  • Free from other internal observations?

  • Coffey Projects

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.