Title Page

  • Site conducted

  • Conducted on

  • Inspection Team Members

  • Period

  • Shift

  • Work order Number

Engineering safety Inspection AUDITORS: All non-conformances identified during the audit must be recorded on this Safety Action Plan. There must also be an Event Notification form (Hazard Report) filled out for each non-conformance and signed by the FLM for the line. Maintenance Requests Z2's also to be recorded.

WORK IN-PROGRESS BENCH

  • All equipment to be stored neatly

  • In-progress parts to be identified

  • Benches clean

BENDING MACHINE 1 (S.N0.1543112000)

  • Area clean and clear of tripping hazards

  • Start & Stop controls clearly marked

  • Emergency Stop button clearly marked & working

'EPIC GUILLOTINE (S.NO.1543112000)

  • Cut-off area clean

  • General surrounds clean

  • Light working

  • Safety signs visible

  • Emergency Stop button clearly marked & working

SHEET METAL ROLLER (MCT0017)

  • General surrounds clean

  • Eye protection sign visible

  • Floor area clean

  • On/off switch operative

  • Emergency Stop button clearly marked & working

WELDING BAY

  • All exits have clear access

  • All lighting working

  • Hearing and eye protection signs visible

  • All hoses rolled up

  • Electrical leads rolled up & in good condition

  • All gas bottles securely stored

  • Benches clean

  • Floor area clear of obstacles

  • Electrical cabinets locked

  • Welder stored neatly

  • Ventilation working

  • Fire Extinguisher in place and operable (Red CO2)

  • Fire blankets (1) on welding screen hooks

  • Welding apron “ “ “ “

  • Welding hood “ “ “ “

PESESTAL GRINDER (MCT0012)

  • General surrounds clean

  • Light working

  • Eye protection sign in place

  • Spark cover in place

  • Tool post set correctly

  • Emergency Stop button clearly marked & working

  • Start & Stop controls clearly marked

  • Power cables are in good condition

HYDRAULIC PRESS (PRS0004)

  • Floor area clean

  • Press area tidy

  • Eye protection sign in place

  • No evidence of oil leakage

  • Power cables are in good condition

POLISHER

  • Floor area clean

  • Stop switch working

  • Power cables are in good condition

  • Eye protection sign in place

PEDESTAL DRILL (S.N0.2351)

  • General surrounds clean

  • Machine and cut off area clean

  • Eye protection sign visible

  • Floor area clean

  • On/off switch operative

  • Emergency Stop button clearly marked & working

  • Power cables are in good condition

HORIZONTAL GRINDER (MCT0005)

  • General surrounds clean

  • Eye protection sign in place

  • Spark cover in place

  • Emergency Stop button clearly marked & working

  • Power cables are in good condition

MILLING MACHINE (MCT0009)

  • General surrounds clean

  • Eye protection sign in place

  • Guard in place when in use

  • Power cables are in good condition

CENTRE LATHE- (MCT0008)

  • General surrounds clean

  • Machine and cut-off area clean

  • Eye protection sign in place

  • Emergency Stop (Foot activated) working

  • Guard in place when in use

  • Safety notice on back panel visible

  • Power cables are in good condition

  • Swarf remover available

  • Start & Stop controls clearly marked

  • Light working

CENTRE LATHE (MCT0007)

  • General surrounds clean

  • Machine and cut-off area clean

  • Eye protection sign in place

  • Emergency Stop (Foot activated) working

  • Signs and guard visible

  • Power cables are in good condition

  • Swarf remover available

  • Start & Stop controls clearly marked

  • Light working

BAND SAW (MCT 0003)

  • General area tidy and unobstructed

  • Eye protection sign in place

  • Emergency stop button working

  • Single phase cables not a danger or trip hazard

  • Start & Stop controls clearly marked

OIL/GREASE TABLE

  • All equipment in a tidy condition

  • Grease guns and containers correctly stored

  • Fire extinguisher in place and operable (Dry Chemical)

PARTS WASH TANK

  • Light working

  • Protective gloves available

  • Eye protection sign in place

ENG. STORE and FIRE EXIT TO ALLEYWAY

  • Stairway to office clear, non-slip strips on steps

  • Fire ext. in place and operable (1 – CO2, 1 – Dry chem.)

  • Walkways clear

  • Lighting working

  • Fire exit door to alleyway unobstructed

  • Fire hose operable

STORES / OFFICE & CLEAN ROOM

  • Work benches / Desks are clean & organised

  • Correct bin colours are being used

  • Correct storage of equipment / parts / Tools

  • Adequate ventilation in working order

  • Adequate lighting in working order

  • General Housekeeping

  • Walkways clear from obstruction & clearly marked

MOBILE EQUIPMENT

GENIE (GS2032)

  • Log books available & correctly completed

  • Clean & in good working order

  • Stored in correct location

  • On / Off & E Stop controls clearly marked & working

SNORKEL (AB46JE)

  • Log books available & correctly completed

  • Clean & in good working order

  • Stored in correct location

  • On / Off & E Stop controls clearly marked & working

GENIE (GS1932)

  • Log books available & correctly completed

  • Clean & in good working order

  • Stored in correct location

  • On / Off & E Stop controls clearly marked & working

ENGINEERING WORKSHOP GENERAL

  • All emergency exits (4) have clear access and exit signs illuminated

  • All overhead lighting working and clean

  • All walkways clear

  • Painted lines define walkways

  • Bench tops tidy

  • Electrical test board tidy

  • Area under benches clear of rubbish

  • Electrical switchboards locked

  • Emergency eyewash station available

  • Fire extinguishers in position and operable

  • Any chemical bottles located in the vicinity are appropriately labelled

LOCKOUT BOARD

  • Lockout board kept tidy – all locks accounted for & available

  • Lockout book in good condition – available space

OILS AND GREASES

  • Oil and grease containers sealed

  • Storage racks in good order

  • All chemicals clearly marked

  • ( MSDS sheets in Eng. Workshop)

  • Oil drums stored in a safe manner

  • Floor area clear

PAINTS

  • Flammable liquids, sign visible

  • No smoking sign visible

  • Authorised personnel sign visible

  • Fire extinguisher present,tagged and operable (dry foam)

  • Main entrance door lock working

  • Interior light working and in good condition

  • All chemicals clearly marked

  • Explosion cabinets, all door lock working

  • Paint etc. stored correctly

  • Floor area clean and in good condition

  • Acids/alkalines stored in seperate bunded areas

  • MSDS sheets visible

OTHER AREAS

  • LPG RECEIVER

  • Flammable gas sign visible

  • No smoking sign visible

  • Authorised personnel sign visible

  • LPG tank clearly marked

  • Floor area clear

  • Emergency Cut-Off Wire operable

GAS BOTTLE STORAGE CAGE

  • All bottles secured

  • Floor area clear of refuse

  • Door lock working

WASTE OIL CONTAINERS

  • Area tidy

  • Catch tray maintained

CUT-OFF SAW (Outside)

  • Floor area clear

  • Light working

ALLEY WAY and STEEL RACKING

  • All steel stored correctly on racks (2)

  • Emergency exit door unobstructed

SUBSTATIONS HIGH VOLTAGE TRANSFORMERS -Substation at front gate

  • Doors locked

  • Danger signs visible

  • Access to escape door clear

  • Roof clear of debris (if applicable)

  • Bollards protection in place

  • Cable run high voltage signs every 4 metres

SUBSTATION HIGH VOLTAGE TRANSFORMERS- Substation near chips plant room.

  • Doors locked

  • Danger signs visible

  • Access to escape door clear

  • Bollards/protection metres in place

  • Cable run high voltage signs every 4 metres

SUBSTATION HIGH VOLTAGE TRANSFORMERS-Substation near, air compressors

  • Doors locked

  • Danger signs visible

  • Access to escape door clear

  • Bollards/protection metres in place

  • Cable run high voltage signs every 4 metres

SUBSTATION HIGH VOLTAGE TRANSFORMERS-Substation next to W/House Embankment

  • Doors locked

  • Danger signs visible

  • Access to escape door clear

  • Cable run high voltage signs every 4 metres

SUBSTATION HIGH VOLTAGE TTRANSFORMERS-Substation next to DAF plant

  • Doors locked

  • Danger signs visible

  • Access to escape door clear

  • Bollards/protection metres in place

SUBSTATION HIGH VOLTAGE TRANSFORMER-Substation next to Sparkle Plant

  • Doors locked

  • Danger signs visible

  • Bollards/protection metres in place

  • Cable run high voltage signs every 4 metres

SIGNATURES

  • FLM

  • AUDITORS

AUDIT COMPLETION:

  • When audit has been completed, please select yes to submit.

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.