Title Page
-
Date Of Inspection
-
Inspector
-
Engineer Name
-
Employment Type (PAS/BG/Partner)
-
Location
-
Select weather conditions at the time of inspection
- Clear Sky
- Cloudy
- Raining
- Windy
- Hazy
- Snow/Hail
- Sunny
Objective
-
To ensure that all engineers have the correct tools, equipment and PPE to perform their job safely
-
To ensure that all engineers can perform all mandatory electrical safety tests and understand the sequence of tests as well as the reasons for the safety procedures. This is achieved by monitoring, coaching and training. Photos of the engineer performing the tests are required
-
Please refer to Pacifica Appliance Services - Safe Isolation Process located on LearnUpon
-
To confirm that the engineer is competent and safe to work
Resident Inspection Authorisation & COVID 19 Questions
-
Can the Operative clearly outline the procedure to prevent the spread of COVID?
-
Is the Operative aware of the COVID symptoms?
-
Does the Operative have all COVID PPE available as supplied by the Company (Sanitizer, wipes, disposable gloves, face visor, masks)? Please photograph items
Site Safety and Customer Service
-
Do Operatives carry valid ID Cards [I.E Company ID, Gas Safe, OFTEC, NICEIC]
-
Is the works vehicle parked safely?
-
Is the works vehicle tidy? Photos of vehicle required (inside & out)
-
Does the Operative have access to current RAMS? (LearnUpon)
-
RAMS
-
Evidence Site Safety Set-Up: Have Operatives set up the work area in an orderly fashion, keeping access/ egress routes free from obstruction?
-
Are the Operatives using the correct floor protection?
-
Has the customer been suitably advised on the repair process and potential hazards associated, including the safe zone, work zone locations and able to carry out a dynamic risk assessment?
Electrical Equipment Checklist (Please photograph the serial number & Calibration date)
-
Earth Loop Impedance Meter / Capture photo of serial number & calibration date
-
Insulation Resistance & Continuity / Capture photo of serial number & calibration date
-
2-Pole Indicator condition
-
Personal RCD
-
All Lock Off Equipment & Devices Condition
Electrical - Safe Isolation Process (Please photograph the engineer performing each test)
-
REQUIRED - Engineer MUST Demonstrate Safe Electrical Isolation Process
-
Can the Operative make correct use of the non-contact Volt Detector (Volt Stick x2 available)? Photos of the engineer carrying out the test required.
-
Inspector - refer to attached Electrical Safety Training Presentation & Provide Training
-
Following training given, I "The Operative" can confirm I have read, received and will adhere to all information provided
-
-
Can the Operative perform an Earth Loop Impedance Test (ELI)? Photos of the engineer carrying out the test required.
-
Inspector - refer to attached Electrical Safety Training Presentation & Provide Training
-
Following training given, I "The Operative" can confirm I have read, received and will adhere to all information provided
-
Can the Operative perform an Earth Continuity Test? Photos of the engineer carrying out the test required.
-
Inspector - refer to attached Electrical Safety Training Presentation & Provide Training
-
Following training given, I "The Operative" can confirm I have read, received and will adhere to all information provided
-
Can the Operative perform an Insulation Resistance Test? Photos of the engineer carrying out the test required.
-
Inspector - refer to attached Electrical Safety Training Presentation & Provide Training
-
Following training given, I "The Operative" can confirm I have read, received and will adhere to all information provided
-
Can the Operative make use of the 2-Pole Indicator to prove dead? Photos of the engineer carrying out the test required.
-
Inspector - refer to attached Electrical Safety Training Presentation & Provide Training
-
Following training given, I "The Operative" can confirm I have read, received and will adhere to all information provided
PPE & Work Equipment
-
Picture of full PPE [Empty Contents and Check Equipment Stock Levels]
-
Does the Operative have the correct PPE/Work Equipment in order to undertake the work safely? [Including COVID PPE]
-
Does the Operative have a fully stocked, in date First Aid Kit including eyewash?
-
PPE / Equipment Checklist
- Test Socket Adaptor
- FFP3 Face Masks
- Socket & See [Earth Loop Tester]
- Voltage Detector / Volt Pen
- Surface Protection Mats
- RCD
- PPE Storage Kit Bag
- Electrical Lock Off Equipment
- Cable Ties
- Padlocks
- Safety Glasses
- Bump Cap
- First Aid Kit Including Eyewash
- Dustsheets / Floor Protection
- Cut 3 Gloves
- Cut 5 Gloves
- Non-slip Overshoe
- Hi-Viz
- Safety Footwear
- Socket and See (RCD Tester)
- Kevlar Sleeves
- PPE / Equipment Storage Bag
-
Any equipment damaged or missing - arrange replacement
-
Work being carried out in a safe manner using appropriate, serviceable PPE?
-
Operatives Gloves & Work Clothing
-
Is all hand tools / field equipment free from damage?<br>(if at risk, remove from use immediately and replace)
-
Personal RCD available
-
Does the Operative have X1 1KG Powder Fire Extinguisher Available? [Fully Pressurised and Maintained]
-
Extinguisher Condition
-
Is safety footwear in good condition and of the correct type?
-
Are staff aware of the correct PPE for the tasks they are trained to perform?
-
Access Equipment / Lifting Equipment in good condition and free from any defects? (Check feet, platforms **where applicable)
-
Does the Operative have correct paperwork [Warning Labels, Electrical and Gas]
Sign Off
-
Auditor Feedback (Please detail your observations and any coaching provided to engineer)
-
Auditor Sign
-
Engineer Sign