CONTROL/CHECK
-
Check EPDM for tears and holes
-
Check for sharp edges (galv /alu corners, insulation nails etc. )
-
Check temperature and record for application. If necessary ensure heater is being used.
-
Check the application surface is dry and clean before Novoproof Kleber FA/I application?
-
Check the EPDM surface is dry and clean before Novoproof Kleber FA/I application?
-
Is Kleber FA/I fully applied to the sealing surface with a spatula and at the correct width? (40~60mm)
-
Is the EPDM notched with the right tools as per drawings?
-
Once the EPDM temporary fix to the surface is roller used to ensure full sealing?
-
Check EPDM interior/exterior corners if sealed properly.
-
Has the area been cleaned and waste including COSHH materials removed to allocated bins?