Title Page

  • Document No.

  • Service Mains Replacement Live Audit

  • UEA

  • Conducted on

  • Prepared by

  • Location
  • Personnel

  • Personnel details captured visually

Personnel Requirements

  • Select date

  • Crew Members

  • Short Term Notice Form Used

  • Auditor inducted onto worksite

  • Personnel Qualifications & Training requirements checked

  • CSP authorisation, Authority to Enter Lands card available on site, suitable for work being completed (Level 1, Level 2) & in date

  • General Construction card available on site & in date

  • Qualified Supervisors Certificate or Contractors Licence available & in date

  • EWP operator has High Risk Licence & in date

  • Qualified First Aid Person on site & qualifications are in date

  • Traffic Control Qualifications are appropriate to the work being conducted & in date

  • Copy of Customer Notification letter available

  • Appropriate Work Instructions, SWMS & Policies available onsite

  • Additional comments

Plant, Vehicles, Tools & Equipment

  • Plant, Vehicles, Tools & Equipment inspection completed

  • All vehicles have EE signage

  • Registration of EWP & vehicles in date

  • EWP & vehicle pre-operational checks completed & recorded

  • EWP mechanical, hydraulic & electrical tests in date

  • EWP boom clean with Safe Approach Table & Voltage identification bands clearly visible

  • Control Decent Device operable & in date

  • EWP level indicators affixed & clearly visible

  • Appropriate First Aid Kit on vehicles, with location sticker appropriately affixed & in date

  • Dangerous/Hazardous goods stored correctly with ventilation & signage

  • Appropriate Spill Kit available with instructions

  • Safety Data Sheets available & appropriate

  • Testing & tagging of all tools & equipment completed & in date

  • Suitable fire extinguisher available testing & tagging in date with correct signage

  • Bushfire equipment available with 9litre knapsack, shovel, rake, water

  • Bushfire hazards assessed, appropriate controls in place

  • Staff aware of noxious weeds, plant/animal disease controls & appropriate controls in place

  • Additional comments

Worksite Preparations

  • Risk assessment completed, identifying all relevant hazards with correct control measures in place prior to & whilst conducting work

  • Appropriate customer consultation prior to commencing work (including hazards & precautions)

  • Confirmation that all Premises affected by Distribution &/or Service Mains replacement/s have been notified

  • Appropriate Safety Equipment, PPE available & used with in date testing

  • Appropriate Traffic Control Plan selected & implemented

  • Plant Safety Observer & Working Aloft rescuer nominated & situ where required

  • Effective communication during toolbox/work site brief to assign tasks & identify hazards/controls.

  • Safe work manual, work instructions, SWMS available & utilised where required

  • Additional comments

Work Task at Switchboard

  • Correct PPE & equipment used according to risk assessment

  • Close approach performed prior to accessing or working on switchboard

  • Switchboard safe to carry out works (electrical, mechanical & hazardous materials identified)

  • Phase sequencing recorded

  • What Phase sequence was found

  • Isolation time

  • Main Switches, circuit breakers & fuse positions recorded

  • What Main Switches, Circuit Breakers & fuse circuits were energised on arrival

  • All Main Switches Isolated

  • What Main Switches were isolated

  • Appropriate Premise isolation & Danger Tagging

  • What Premise isolation device was used

  • Confirmation that the isolation device used has de-energised the installation

  • Appropriate testing device used to prove de-energised

  • Additional comments

Work Task at Streetlight Control Switchboard

  • Work to be conducted on a Streetlight Service Control Switchboard

  • Correct PPE & equipment used according to risk assessment

  • Close approach conducted to Streetlight Control SWB

  • Switchboard safe to carry out works (electrical, mechanical & hazardous materials identified)

  • Streetlight isolation device used

  • What isolation device was used

  • Confirmation that the isolation device used has de-energised the Streetlight & circuit

  • Appropriate testing device used to prove de-energised

  • Appropriate Streetlight Control isolation, danger tagged & locked

Asbestos Controls

  • Asbestos Controls Required

  • Correct PPE & equipment used

  • Correct segregation/delineation of work area

  • Windows, doors & vents considered & appropriate controls utilised

  • Effective personal decontamination

  • Effective equipment, tools & work area decontamination

  • Correct switchboard preparation & decontamination

  • Asbestos equipment & waste bagged, packed, stored correctly

  • Asbestos Sticker on switchboard

  • Additional comments

Work Tasks at DIST, PCC & POS

  • Safety Observer can promptly identify how to operate base controls

  • EWP appropriately parked, chocked & levelled

  • Appropriate Traffic & Pedestrian controls utilised, monitored & adjusted to suit conditions

  • Appropriate PPE, equipment & tools used in accordance with the risk assessment

  • Perform close approach to assets prior to conducting work

  • Conduct pre-climb/work asset inspection before climbing or changing structural loads

  • Pole top rescue kit immediately available & prepared at the base of the ladder

  • Ladder appropriately secured whilst conducting work

  • Existing Service Mains height identified

  • Competent assistant/working aloft rescuer allocated & readily available

  • Inadvertent contact with energized conductors controlled

  • Correct Distribution &/or Service conductor identified to disconnect & load confirmed isolated

  • All Service Mains have been disconnected before Distribution Service is disconnected

  • Distribution &/or Service conductor actives & neutral electrically identified prior to disconnection

  • Correct disconnection method used, actives followed by neutral

  • Disconnected Distribution &/or Service conductors, individually proven de-energised whilst secured

  • Close approach conducted at PCC or POS confirming conductor disconnected

  • Neutral Service bond disconnected at the POS

  • Service secured & lowered correctly

  • Vegetation Clearing completed & sufficient

  • Insulation test conducted on Distribution/Service conductors

  • HSC's connected as per manufacturers specifications

  • Connection Point neutral bond is disconnected prior to testing, connecting & energizing the Service Mains

  • Correct testing, identification & marking of Distribution conductors

  • Electrically identify & confirm all Service conductors before connection

  • Polarity and Neutral Identification testing completed correctly

  • Potential difference checked before each conductor connection

  • Conductors scratched and greased before new connections made

  • Connections completed correctly, as per manufacturers specifications

  • Redundant hardware removed from Distribution network & Pole/s

  • Correct testing & connection of the service bond at the POS (0-5volt test completed)

  • All electrical testing & connections witnessed by 2nd electrically qualified staff member

  • Drop zone clear whilst work was being conducted

  • Additional comments

Work Task at Streetlight

  • Work to be conducted on a Streetlight Service

  • Safety Observer can promptly identify how to operate base controls

  • EWP appropriately parked, chocked & levelled

  • Appropriate Traffic & Pedestrian controls utilised, monitored & adjusted to suit conditions

  • Appropriate PPE, equipment & tools used in accordance with the risk assessment

  • Perform close approach to assets prior to conducting work

  • Conduct pre-climb/work asset inspection before climbing or changing structural loads

  • Pole top rescue kit immediately available & prepared at the base of the ladder

  • Ladder appropriately secured whilst conducting work

  • Existing Streetlight Service Mains height identified

  • Competent assistant/working aloft rescuer allocated & readily available

  • Inadvertent contact with energized conductors controlled

  • Streetlight load confirmed isolated

  • Isolation device available or operable

  • New isolation device to installed or to be installed

  • Correct Distribution &/or service conductor identified to disconnect & load confirmed isolated

  • Streetlight Service Mains have been disconnected before Distribution Service Main is disconnected

  • Distribution &/or Streetlight Service conductor actives & neutral electrically identified prior to disconnection

  • Correct disconnection method used, actives followed by neutral

  • Disconnected Distribution &/or Service conductors, individually proven de-energized whilst secured

  • Streetlight service secured & lowered correctly

  • Vegetation Clearing completed & sufficient

  • Insulation test conducted on Distribution/Streetlight Service Mains

  • Correct testing, identification & marking of Distribution conductors

  • Electrically identify & confirm all Distribution/Streetlight conductors before connection

  • Polarity & Neutral Identification testing completed correctly

  • Potential difference checked before each conductor connection

  • Conductors scratched & greased before new connections made

  • Connections installed as per manufacturers specifications

  • Redundant hardware removed from Distribution network & pole/s

  • Neutral Integrity & Final test completed on Streetlight including (0-5volt test)

  • Neutral Integrity test completed

  • Streetlight not operational due to PE cell, bulb or ballast failure

  • Final Test completed with load box as simulated Streetlight operating

  • Streetlight left isolated & Essential Energy staff notified

  • All electrical testing & connecting witnessed by 2nd electrically qualified staff member

  • Drop zone clear whilst work was being conducted

Work Task 2 at Switchboard

  • Perform close approach testing prior to conducting final SWB testing

  • Phase sequencing confirmed as previously recorded

  • Neutral ID, polarity test and final test conducted correctly (with artificial load)

  • Acceptable voltages & currents assessed and recorded

  • Final Test Result

  • All electrical testing observed by 2nd electrically qualified staff member

  • All main switches returned to positions as initially found

  • What Main Switches were re-energised

  • Reconnection time

  • Appropriate metering & control equipment is sealed

  • Additional comments

Work Task 2 at Streetlight Control Switchboard

  • Work Task 2 at Streetlight Control Switcboard

  • Perform close approach testing prior to conducting final SWB testing

  • Acceptable voltages & currents assessed and recorded

  • All electrical testing observed by 2nd electrically qualified member

  • All isolation devices returned to positions as initially found

  • Appropriate metering & control equipment is sealed

  • Additional comments

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.