Title Page
-
Form Number (Level/Gridline)
-
Subcontractor
-
Location
undefined
-
Are the correct revision of drawings being used? Add picture for demonstration
Untitled Page
-
1. Setting Out brick work as masonry setting out layout, working to openings an laid to gauge.
-
2. Brick type, colour and mortar colour and pointing correct.
-
3. VCL -installed correctly and in accordance with manufacture instructions.
-
4.Horizontal Fire Barriers - Installed correctly and in accordance with manufacturers instructions.
-
5. Vertical Fire Barriers - Installed correctly and in accordance with manufacturers instructions.
-
6. DPC/Trays - Installed correctly and in accordance with manufacturers instructions.
-
7. Insulation - Installed correctly and in accordance with manufacturers instructions, including any insulation clips.
-
8. Channels and Wall Ties - Installed Correctly and in accordance with manufacturers instructions.
-
9. Cavity closers - Installed Correctly and in accordance with manufacturers instructions.
-
10. Expansion Joints - Installed Correctly and in accordance with manufacturers instructions.
-
11. Lintels - Installed Correctly, correct type and catch etc.
-
12. Air Bricks/Vents - Are these installed correctly as per drawings and in accordance with manufacturers instructions.
-
13. Cleaned Cavity - External Cavity Clear of Debris.
-
Signature of Sub Contractor
-