Title Page
-
Address:
-
Project Code:
-
Contractor:
-
Consultant:
-
On-site contact:
-
Conducted on
-
Prepared by
Audit report. Notes and / or photos can be added at any point by selecting the Menu at the right-hand side (3 dots)
-
Select asset type:
-
Inspected for:
-
Bench and channel condition
-
Joints in manhole lifts
-
Manhole lids - Gatic or other approved by EGW
-
Pressure / vacuum test completed - results recorded
-
Step irons (none except by prior agreement)
-
Other
-
Select asset type:
-
Inspected for:
-
Channel condition
-
Joints in maintenance shaft lifts
-
Maintenance shaft lids - Gatic or other approved by EGW
-
Pressure / vacuum test completed - results recorded
-
Other (e.g. is this actually a 150mm inspection shaft with maintenance shaft lid on it?)
-
Sewer connection points constructed to regulation height / depth, complete with marker tape to surface
-
Reinstatement quality is satisfactory with manholes raised slightly above surface level and graded away
-
Construction / installation of infrastructure conforms with approved drawings (manhole depths, connection offsets etc.)
-
Sewer lines CCTV surveyed for joint inspection, low spots and cleanliness (i.e. no debris).<br>If CCTV survey is required, select menu options to the right and create a Follow Up Action.
-
Other e.g. thrust blocks, air valves etc.
-
Comments:
-
I confirm that this audit is:<br>Select from Compliant, Non-compliant - needs follow up or Waiting for CCTV survey.<br>You can 'Complete' and 'Save' this audit report and return to it later and 'Edit' and 'Save'.
-
Name / Signature