Title Page
-
Road Name
-
Conducted on
-
Prepared by
-
Operatives name
Untitled Page
-
ELM, correct figure of "8", 2 at top 3 at the bottom
-
OH, Fibre cable routed & dressed away from climbing steps (50mm), minimum bend radius maintained
-
OH, Fibre cable fixed to pole using aluminium strips with bonding nails & washers on each side of the pole at 450mm intervals, "C" clip 1x bonding & washer ensuring pinching/crushing of cable
-
OH, existing wire/cable across carriageway above 5.2m minimum climb height
-
OH, pole capping provided where required, not covering any pole markings
-
OH, ULW tree guard on fibre clamp where needed
-
OH/UG, CBT protective dust caps fitted & fully tightened on all ports
-
Corning CBT has the correct top & bottom mountings have been fitted and 2x cable ties
-
Are the cable ties cut flush?
-
Ate the GEL wraps fitted correct?
-
144F/96F in 25mm/16mm sub duct?
-
Are the ducts cut back and sealed?
-
Has the worksite been left clean & tidy? Fibre shards removed/rubbish cleared?
-
Have any OR defects on site reported via A1024?
-
OR JUF2/JB26 & JB23 no cable support required
-
Potential L2C issues have been highlighted - i.e carrier pole not a "D" pole, trees, toby placement
-
CBT 150 max distance from furthest UPRN entry point (UG/Pole)
-
Is there any equipment on policy "D" poles
-
Have DILOR/road crossing issues considered and identified?
-
Have all AGG, DN, IJ nodes & CBTs correctly marked with the ID using permeant marker pen (gold/white)
-
Are the sub duct & fibre cables correctly supported & restrained. Minimum bend radius maintained?
-
Are the fibre cable pole to UG 3 to 4 metres coiled, supported & restrained in nearest FW/JUF chamber?
-
Is the MOBRA bracket fitted tight & at the top of the chamber?
-
MOBRA arm end cap or black/yellow tape?
-
Corning CBT 150mm clearance from ports
-
SST cable, yellow tape 350mm apart
-
Are the fibre cables entering AGG, DN, & IJ nodes correctly labelled?
-
Sub duct/Fibre cable, in OR chambers poles correct PIANOI number?
-
Any more than 25mm of sub duct/ fibre cable, extra PIANOI number?
-
OH, ELM/NJ node correctly fitted in bottom pole envelope of space?
-
OH, CBT fitted in top envelope of space?
-
I can confirm that this is a true reflection