Information

  • Document No.

  • Audit Title

  • Client / Site

  • Conducted on

  • Prepared by

  • Location
  • Personnel

  • Enter the BMR Case Number associated with this inspection:

  • Enter the date and time of this inspection:

  • Signature of technician performing this inspection:

General Inspection of Site Property

  • Is the Site Access Road in good condition and passable in a 2WD vehicle?

  • Is the Access Road free of overgrown vegetation?

  • Are the various access road gates, fences and locks OK?

  • Are the Hydro poles, lines, service, and meter visually OK?

  • Is the Hydro path free of overgrown vegetation?

  • Photo of Hydro Meter showing Meter Number and the Meter Reading:

  • Enter any numbers found on Hydro Poles or Transformers:

  • Are the various compound gates, fences and locks OK?

  • Is the gravelled area around the site compound OK and free of large holes and/or washouts?

  • Is the compound and tower base area free of overgrown vegetation?

  • Photo of Parking area:

Tower Inspection

  • Photo of the entire tower:

  • Do the Tower Lamps and Housings appear intact (using binoculars)?

  • Are the tower guy paths free of overgrown vegetation?

  • Visual inspection of guy wires, guy anchors, and grounding of same is OK?

  • Is Tower Signage present and affixed to the tower?

  • If present, is the Tower Anti-Climb locked and in good visual working condition?

  • Is the tower base grounding intact and secure?

  • Photo of the tower base:

  • Photos of each guy path from the tower base:

  • Is the Cable/Ice Bridge OK and free of damage?

  • Is the Cable/Ice Bridge grounding intact and secure?

  • Is the Cable Entry Window intact and has no uncovered portals?

  • Photo of Exterior Cable Entry Window:

Exterior Building Conditions

  • Photo of Shelter Exterior Front (Door Side):

  • Photo of Shelter Exterior on Power Room end:

  • Photo of Exterior Fuel Filling area:

  • Photos of the ground in the area outside the Power Room showing any presence of Fuel Leaks:

  • Photo of Shelter Exterior at Rear:

  • Photo of Shelter Exterior on Cable Entry end:

  • Do the Foundations for the shelter, ice bridge, and tower appear OK?

  • Are the stairs into both rooms and to the fuel filling area free of visible damage?

  • Is the Fuel Fill Bowl locked and free of visible damage?

  • Are the shelter exterior roof, walls, sheathing and doors free of visible damage?

  • Are the Intake Vent Air Filters clean?

  • Comments regarding the general overall Shelter Exterior:

Ontario Government owned Collocated Shelters

  • Is the FleetNet Shelter the only ONT GOV owned shelter at this site? If 'No', provide details and an Exterior and Interior picture.

  • if applicable, Is the collocated shelter in Good Condition and free of any Deficiencies?

Radio Room - General Inspection

  • Radio Room Door and Unican system functional?

  • Are the Door Check Chains intact and connected to the doors?

  • Is the Interior Lighting functional?

  • Are the interior ceiling, walls and floors clear of visible signs of water ingress or rust?

  • The Thermostats are confirmed to be set at 15C for Heat and 20C for Vent?

  • The Fan Thermostats are confirmed to be set at 22C for AC Fans and 25C for DC Fans?

  • Are the Damper Motors, Louvres, and Louvre Control Arms OK and functional?

  • Are the AC powered fans functional?

  • If present, are the DC powered fans functional?

  • Are the Heaters functional?

  • Enter the ambient temperature in the Radio Room (degrees Celsius):

  • Are the coax feed lines and connectors visually OK, secure, and intact?

  • Are all the multicouplers and associated cables/connectors visually OK, secure, and intact?

  • Are the Radio Equipment Internal Fans functional and clear of debris/dust?

  • Visual inspection of all wiring in the room is OK?

  • Visual inspection of all racking, mounts, associated fasteners and hardware is OK?

  • Is an up to date Site Information Sign posted near the site phone?

  • The Site Phone has been tested and confirmed operational by checking in with the WNOC?

  • Is the Site Documentation available and up to date?

  • Is there a Logbook present in the Radio Room and is it up to date?

  • Is the Radio Room clean and tidy?

  • Photo of the Radio Room:

Radio Room - Alarms & Sensors

  • Are all of the Radio Room Alarm Connections secure and intact?

  • Are the Door Alarms functional?

  • Are the Smoke alarms functional?

  • Are the Power Plant alarms functional?

  • Is the Dehydrator power ON and are the Air Lines OK?

  • if applicable, Dehydrator pressure reading:

Tower Lighting System

  • Are the Tower Beacon Lights working?

  • Is the Tower Beacon Light alarm functional?

  • Are all the Tower Obstruction Lights (DOL) working?

  • Is the Tower Obstruction Light (DOL) alarm functional?

  • Is the Tower Light Power Fail alarm functional?

  • Is the Tower Lights' Photo Cell functioning properly? (i.e. Lights are OFF in daylight.)

  • Is the Tower Light Ballast Resistor cool during the day? (Hot indicates a defective relay)

Power Room & AC Standby Power System

  • Power Room Door and Unican system functional?

  • Are the Door Check Chains intact and connected to the doors?

  • Is the Interior Lighting functional?

  • Are the interior ceiling, walls and floors clear of visible signs of water ingress or rust?

  • The Thermostats are confirmed to be set at 15C for Heat and 20C for Vent?

  • The Fan Thermostats are confirmed to be set at 22C for AC Fans and 25C for DC Fans?

  • Are the Damper Motors, Louvres, and Louvre Control Arms OK and functional?

  • Are the AC powered fans functional?

  • If present, are the DC powered fans functional?

  • Are the Heaters functional?

  • Enter the ambient temperature in the Power Room (degrees Celsius):

  • Is the Generator Control Panel functional?

  • Has the Generator Control Switch been left in the AUTO/NORMAL position?

  • Photo of Engine Hour Meter Reading:

  • Is the Power Room clear of Fuel Leaks?

  • Is the Power Room clear of Oil Leaks?

  • Photo of the Generator area:

  • Photo of the Fuel Tank area:

  • Photo of Fuel Tank Gauge Reading:

  • Is the Power Room clear of Start Battery Leaks?

  • Are the Start Battery Terminals clear of corrosion?

  • Measure and record the Start Battery float voltage:

  • Is there a bucket of spill absorbent in the room?

  • Estimated quantity of spill absorbent remaining in the bucket is:

  • Is there a Logbook present in the Power Room and is it up to date?

  • Is the Power Room clean and tidy?

Power Room - Alarms & Sensors

  • Are all of the Power Room Alarm Connections secure and intact?

  • Is the Generator Exercise Relay functional?

  • Is the Generator Start Battery alarm functional?

  • Is the Fuel Leak alarm functional?

  • Is the Fuel Gauge Level properly calibrated? (Check reading in T:LAN)

  • General Comments on Power Room:

Completion Steps

  • AC Breakers turned ON inside both rooms for Fans & Louvres?

  • Site verified online via the WNOC upon completion of PM?

  • Interior lights are off, site doors and gates closed and locked?

  • Date and Time inspection completed:

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.