Information
-
Document No.
-
Audit Title
-
Client / Site
-
Conducted on
-
Prepared by
-
Location
-
Personnel
-
Enter the BMR Case Number associated with this inspection:
-
Enter the date and time of this inspection:
-
Signature of technician performing this inspection:
General Inspection of Site Property
-
Is the Site Access Road in good condition and passable in a 2WD vehicle?
-
Is the Access Road free of overgrown vegetation?
-
Are the various access road gates, fences and locks OK?
-
Are the Hydro poles, lines, service, and meter visually OK?
-
Is the Hydro path free of overgrown vegetation?
-
Photo of Hydro Meter showing Meter Number and the Meter Reading:
-
Enter any numbers found on Hydro Poles or Transformers:
-
Are the various compound gates, fences and locks OK?
-
Is the gravelled area around the site compound OK and free of large holes and/or washouts?
-
Is the compound and tower base area free of overgrown vegetation?
-
Photo of Parking area:
Tower Inspection
-
Photo of the entire tower:
-
Do the Tower Lamps and Housings appear intact (using binoculars)?
-
Are the tower guy paths free of overgrown vegetation?
-
Visual inspection of guy wires, guy anchors, and grounding of same is OK?
-
Is Tower Signage present and affixed to the tower?
-
If present, is the Tower Anti-Climb locked and in good visual working condition?
-
Is the tower base grounding intact and secure?
-
Photo of the tower base:
-
Photos of each guy path from the tower base:
-
Is the Cable/Ice Bridge OK and free of damage?
-
Is the Cable/Ice Bridge grounding intact and secure?
-
Is the Cable Entry Window intact and has no uncovered portals?
-
Photo of Exterior Cable Entry Window:
Exterior Building Conditions
-
Photo of Shelter Exterior Front (Door Side):
-
Photo of Shelter Exterior on Power Room end:
-
Photo of Exterior Fuel Filling area:
-
Photos of the ground in the area outside the Power Room showing any presence of Fuel Leaks:
-
Photo of Shelter Exterior at Rear:
-
Photo of Shelter Exterior on Cable Entry end:
-
Do the Foundations for the shelter, ice bridge, and tower appear OK?
-
Are the stairs into both rooms and to the fuel filling area free of visible damage?
-
Is the Fuel Fill Bowl locked and free of visible damage?
-
Are the shelter exterior roof, walls, sheathing and doors free of visible damage?
-
Are the Intake Vent Air Filters clean?
-
Comments regarding the general overall Shelter Exterior:
Ontario Government owned Collocated Shelters
-
Is the FleetNet Shelter the only ONT GOV owned shelter at this site? If 'No', provide details and an Exterior and Interior picture.
-
if applicable, Is the collocated shelter in Good Condition and free of any Deficiencies?
Radio Room - General Inspection
-
Radio Room Door and Unican system functional?
-
Are the Door Check Chains intact and connected to the doors?
-
Is the Interior Lighting functional?
-
Are the interior ceiling, walls and floors clear of visible signs of water ingress or rust?
-
The Thermostats are confirmed to be set at 15C for Heat and 20C for Vent?
-
The Fan Thermostats are confirmed to be set at 22C for AC Fans and 25C for DC Fans?
-
Are the Damper Motors, Louvres, and Louvre Control Arms OK and functional?
-
Are the AC powered fans functional?
-
If present, are the DC powered fans functional?
-
Are the Heaters functional?
-
Enter the ambient temperature in the Radio Room (degrees Celsius):
-
Are the coax feed lines and connectors visually OK, secure, and intact?
-
Are all the multicouplers and associated cables/connectors visually OK, secure, and intact?
-
Are the Radio Equipment Internal Fans functional and clear of debris/dust?
-
Visual inspection of all wiring in the room is OK?
-
Visual inspection of all racking, mounts, associated fasteners and hardware is OK?
-
Is an up to date Site Information Sign posted near the site phone?
-
The Site Phone has been tested and confirmed operational by checking in with the WNOC?
-
Is the Site Documentation available and up to date?
-
Is there a Logbook present in the Radio Room and is it up to date?
-
Is the Radio Room clean and tidy?
-
Photo of the Radio Room:
Radio Room - Alarms & Sensors
-
Are all of the Radio Room Alarm Connections secure and intact?
-
Are the Door Alarms functional?
-
Are the Smoke alarms functional?
-
Are the Power Plant alarms functional?
-
Is the Dehydrator power ON and are the Air Lines OK?
-
if applicable, Dehydrator pressure reading:
Tower Lighting System
-
Are the Tower Beacon Lights working?
-
Is the Tower Beacon Light alarm functional?
-
Are all the Tower Obstruction Lights (DOL) working?
-
Is the Tower Obstruction Light (DOL) alarm functional?
-
Is the Tower Light Power Fail alarm functional?
-
Is the Tower Lights' Photo Cell functioning properly? (i.e. Lights are OFF in daylight.)
-
Is the Tower Light Ballast Resistor cool during the day? (Hot indicates a defective relay)
Power Room & AC Standby Power System
-
Power Room Door and Unican system functional?
-
Are the Door Check Chains intact and connected to the doors?
-
Is the Interior Lighting functional?
-
Are the interior ceiling, walls and floors clear of visible signs of water ingress or rust?
-
The Thermostats are confirmed to be set at 15C for Heat and 20C for Vent?
-
The Fan Thermostats are confirmed to be set at 22C for AC Fans and 25C for DC Fans?
-
Are the Damper Motors, Louvres, and Louvre Control Arms OK and functional?
-
Are the AC powered fans functional?
-
If present, are the DC powered fans functional?
-
Are the Heaters functional?
-
Enter the ambient temperature in the Power Room (degrees Celsius):
-
Is the Generator Control Panel functional?
-
Has the Generator Control Switch been left in the AUTO/NORMAL position?
-
Photo of Engine Hour Meter Reading:
-
Is the Power Room clear of Fuel Leaks?
-
Is the Power Room clear of Oil Leaks?
-
Photo of the Generator area:
-
Photo of the Fuel Tank area:
-
Photo of Fuel Tank Gauge Reading:
-
Is the Power Room clear of Start Battery Leaks?
-
Are the Start Battery Terminals clear of corrosion?
-
Measure and record the Start Battery float voltage:
-
Is there a bucket of spill absorbent in the room?
-
Estimated quantity of spill absorbent remaining in the bucket is:
-
Is there a Logbook present in the Power Room and is it up to date?
-
Is the Power Room clean and tidy?
Power Room - Alarms & Sensors
-
Are all of the Power Room Alarm Connections secure and intact?
-
Is the Generator Exercise Relay functional?
-
Is the Generator Start Battery alarm functional?
-
Is the Fuel Leak alarm functional?
-
Is the Fuel Gauge Level properly calibrated? (Check reading in T:LAN)
-
General Comments on Power Room:
Completion Steps
-
AC Breakers turned ON inside both rooms for Fans & Louvres?
-
Site verified online via the WNOC upon completion of PM?
-
Interior lights are off, site doors and gates closed and locked?
-
Date and Time inspection completed: