Title Page

  • Site Name

  • Address

  • Operation Ref

  • Date and Time

  • Contractor

  • Designer

  • Prepared by

Snagging Report

  • INSTRUCTIONS

    1. Please answer the questions below.
    2. Add photos and notes by clicking on the paperclip icon
    3. To add a Corrective Action click on the paperclip icon then "Add Action," provide a description, assign to a member, set priority, and due date
    4. Share your report by exporting as PDF, Word, Excel or Web Link

Attendees

  • Who is on site completing the audit?

  • Attendee
  • Company

  • Name

1 - Site Access / Health & Safety

  • Please include pictures of the site access.

  • 1.1 - If the pad is more than 250mm AGL has access step & handrail been installed?

  • 1.2 - Have pathway blocks or gravel been placed to allow safe access to working areas?

  • 1.3 - If an access track has been installed, is the access track route in accordance with the drawings & is the width, slope, and condition of the track suitable for year-round access?

  • 1.4 - Are there sufficient drainage or soil erosion measures in place to prevent site access problems, or site problems, in periods of bad weather?

  • 1.5 - If cut & fill works have been undertaken, have sufficient measures been taken to ensure the stability of the ground?

  • 1.6 - Where landscaping/plants are required has appropriate preparation and planting been carried out to ensure survival?

  • 1.7 - Has all ground reinstatement been completed to a satisfactory standard? i.e. Compacted soil and seed / tarmac / concrete / slabs / stone etc.

  • 1.8 - Are there any tripping hazards, other than those clearly identified & marked?

  • 1.9 - Is the site generally clean & tidy with all debris appropriately disposed of and construction vehicles, tools, equipment, heras fencing panels and signage removed from site?

  • 1.10- Barriers/bollards/handrails installed as per the DD's?

  • 1.11 Has all Shared Access H&S signage been installed for the telecoms site in accordance with the construction drawings? i.e. Compound signage, cabinet signage (RFE's, MMU, Mini Pillar), structure signage etc.

  • Is there parking available on site?

  • Please include pictures of the parking.

  • What are the parking arrangements?

  • Are there any physical access restrictions to the site? e.g. gates/height/weight restrictions

  • Please include pictures of the restriction.

  • Please give a description of the restriction.

  • How can construction vehicles get to site?

  • How many meters of track-way are required?

  • Are before and after pictures required?

  • Is matting required?

  • Are before and after pictures required?

2 - Concrete Work

  • Please include pictures of the concrete.

  • 2.1 - Are the concrete tower and cabinet bases located as indicated on drawings?

  • 2.2 - Are the concrete tower and cabinet bases the correct size?

  • 2.3 - Are all external edges chamfered as specified on construction drawings?

  • 2.5 - Is concrete damaged at any location?

  • 2.6 - Is concrete finish acceptable? (free from ridge marks, blemishes, corrosion etc.)

  • 2.8 - Is water ponding on concrete surfaces?

3 - Compound

  • Please include general pictures of the compound.

  • Is this site in a compound?

  • 3.1 - Is the padlock on the gate installed?

  • What is the code?

  • 3.2 - Setting out of the fence is in accordance with drawings?

  • 3.3 - Is the fence the correct height, straight, colour, finish etc?

  • 3.4 - Fence posts are secure and stable, wire mesh is adequate and appropriate tensioning wire is fitted?

  • 3.5 - The trim around the cabinets (MMU / RFE / Mini Pillar) is acceptable?

  • 3.6 - Gate pins, bolt & socket allows gate to operate smoothly?

  • 3.7 - Terram membrane installed under gravel?

  • 3.8 - Sufficient gravel / stone installed within compound around concrete base/s?

  • 3.9 - Is the cable ladder/tray route in accordance with the DD's?

  • 3.10 - Are the cable ladders/trays correctly / securely fixed with adequate support at corners, bends and curves?

  • 3.11 - Is the type of cable ladder / C-rail appropriate for fixing of the accepted cable clamps?

  • 3.12 - Do cable ladders / trays have electrical continuity for lightning protection (visual check) – all ladder gaps should be cross bonded?

  • 3.13 - Are the ends of cable ladder / tray cut lengths protected to prevent damage to cables & adequately treated against rusting?

  • 3.14 - Are covers fitted to cable ladders / trays where cables are likely to be stepped across or damaged by falling ice? Are covers fixed adequately & of sufficient thickness (3 to 4mm)?

  • 3.15 - Is there adequate support provided to the cable ladder / tray at the interface to the structure opes / enclosure or cabinets?

4 - Tower / Monopole

  • Please include general pictures of the structure.

  • 4.1 - Does the galvanising/painted finish appear adequate?

  • 4.2 - Tower / Monopole verticality.

  • 4.3 - Access hatch/es secure?

  • 4.4 - Has all Operator steel work been installed as per the DD's? i.e. Correct number of antenna and RRU support poles and associated brackets for each Op sector at correct height?

  • 4.5 - Has the dish support pole/s and bracket been installed as per the DD's and at the correct height?

  • 4.6 - Is the tower / monopole location & orientation in accordance with the DD's?

  • 4.7 - Is this structure climbable?

  • 4.8 - Is the ladder orientation in accordance with the DD's or installed in a safe location so not to block the direction of the proposed antenna faces?

  • 4.9 - Is the mast ladder & ladder brackets securely fixed, functional?

  • 4.10 - Ladder safety device (Latchway or Metreel) is installed where required and the system is tagged and in date?

  • 4.11 - Is the mast climbing and safety device adequately & securely installed with “stop” fitted at top of system?

  • 4.12 - Is an anti-climb guard installed with padlock fitted & functional?

  • 4.13 - What is the pad lock code?

  • 4.14 - Is the fall arrest system installed a Latchway system?

  • 4.15 - Latchway intermediates fixings/spacings installed?

  • 4.16 - System tensioned correctly and Latchway disc can spin freely?

  • 4.17 - Condition of system / cable?

  • 4.18 - No damage to tower anchor bolts, and all nuts are installed and adequately tightened?

5 - Lightning Protection

  • Please include pictures of the lightning protection installation.

  • 5.1 - Is Lightning Protection installed as per the DD's specification?

  • 5.2 - If the site is within a compound, are all the compound fence posts connected to the LP system?

  • 5.3 - If the site is adjacent to any fencing is the LP system bonded to the fence accordingly as per the DD's?

  • 5.4 - Is the structure connected to the LP system accordingly as per the DD's? i.e. There should be 2no LP connections to the structure.

  • 5.5 - Are all steelwork items bonded to the LPS?

  • 5.6 - Are all external earthing tapes PVC coated?

  • 5.7 - Are all earthing tape runs straight?

  • 5.8 - Are all changes in direction 90deg with proprietary joints?

  • 5.9 - Are the correct number of earth pits installed?

  • 5.10 - Have the correct number of earth bars for the PDB and Op cabinets been installed as per the DD and connected to the LPS accordingly?

  • 5.11 - Are earth tapes labelled in earth pits?

  • 5.12 - Has denso tape or contact paste been applied to all external LP connections?

  • 5.13 - Resistance earth from any part of the system does not exceed 10 ohms for the completed LP installation (although individual electrodes may have independent readings higher than 10 ohms).

  • 5.14 - Is the compound gate cross bonded and linked to the LPS?

  • 5.15 - Are all cabinets and PDB's bonded to the LPS?

6 - Cabinets

  • 6.1 - Has the correct type and number of cabinets been installed in accordance with the DD's? i.e. Mini pillar, RFE or MMU?

  • 6.2 - Are the mini pillar and RFE or MMU cabinet/s located in the correct location and set out as indicated on the DD's?

  • 6.3 - Are the mini pillar and RFE or MMU cabinet/s galvanised adequately and in good condition? i.e. free from external damage.

  • 6.4 - Have the cabinets been installed and fixed correctly and securely and free from movement?

  • 6.5 - The cabinet support / foundation is level with no obvious signs of deflection?

  • 6.6 - Cabinet doors & panels are secure & lockable?

  • 6.7 - No signs of water ingress?

  • 6.8 - Has a mini pillar been installed?

  • 6.9 - Has a VC2 chamber been installed to the front of the mini pillar to ESB standards?

  • 6.10 - Has the correct amount of underground ducting been installed for the telecoms site as per the DD's?

  • 6.11 - Are all underground ducts the right size and colour and in the correct location as per the DD's?

  • 6.12 - Have all underground ducts been sealed / foamed or caps fitted accordingly?

7 - ESB Route

  • 7.1 - Has the ESB power route been installed and directed as per the route agreed with the site provider / third party and ESB ?

  • 7.2 - Has the trenching and ducting for the power route been completed in accordance with ESB standards? i.e. Correct electrical warning tape installed above the duct at 300mm BGL, 125mm smooth red duct installed with draw cord / rope 600mm BGL, sand fill surround ducting in trench etc.

  • 7.3 - Have trenches been back filled, compacted and reinstated to a good standard? NOTE: Ground reinstatement to trenches should be slightly proud of the surface to allow for any settlement.

8 - PDB / Electrical Installation

  • 8.1 - Are PDB's installed in the correct location on galvanized frames as outlined in the DD's?

  • 8.2 - Are the correct breakers installed in the PDB?

  • 8.3 - Earth bars are isolated from the galvanised PDB frames?

  • 8.4 - Maintenance socket fitted to PDB?

  • 8.5 - Insulator covers fitted to the live parts of RFE / MMU?

  • 8.6 - Labelling of devices in RFE / MMU?

9 - General

  • 9.1 - Have HOP As-built photographs been taken and issued to Shared Access?

  • 9.2 - Do unused ducts have a draw rope & are they sealed?

  • 9.3 - Is site clean and tidy and ready for inspection and handover?

Overall Assesment

  • Civil

  • Rigging

  • Electrical

  • Roofing

  • Steelwork

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.