Information
-
Job Number:
-
Address:
-
QA Completed By
-
Conducted on
-
THIS QA CHECKLIST IS TO BE COMPLETED IN CONJUNCTION WITH THE INSTALLAUS INSTALLATION GUIDELINES
Whole job review
Site Requirements & Safe Work Method Statement (SWMS)
-
Have you completed the read and understand the SWMS?
-
Do you agree you are not permitted to perform high risk work on site?
-
Do you have a copy of the relevant SWMS?
-
Are there any other hazards not covered in the SWMS such as manual handling? (Contact your site coordinator to report the site specific hazards)
Pre Start Checklist - Site Conditions
-
Have you read the projects site specific coordination plan, taking note of specific hazards?
-
Is there safe access to your work area?
-
Take photo of specific Job Board
-
Have you inspected the site for hazards that could injure you or other workers?
-
Amenities available and in reasonable condition, first aid kit in vehicle and emergency information current?
-
Stairwells including temporary stairs are in place and secure, stairs have clear access and no step greater than 190mm?
-
Do you and others onsite have the right PPE and safety equipment?
Delivery Checklist
-
Was the job pack in the crate sufficiently wrapped with secure tape with no damage?
-
Enter Comment
-
Are all Sinks and Basins delivered?
-
Enter Comment
-
Has Wet Seal been completed?
-
Enter Comment
-
Has Plaster been completed?
-
Enter Comment
-
Is house lockable?
-
Enter Comment
-
If double story house are stairs in at time of delivery?
-
Enter Comment
-
Where all parts free of damage when delivered?
-
Enter Comment
-
Was the delivery sufficiently wrapped with security tape with no damage?
-
Take photo's of delivered product onsite
Completed
-
It is important that the information you have provided is complete and correct. Please confirm that all information required has been entered.
-
Has Job been delivered or returned
-
Please provide any other information that would be useful.
-
Please sign before submitting this form
-
Thankyou