Title Page
-
Conducted on
-
Prepared by
-
Location
-
Has a risk assessment been prepared
-
Check setting out and bond
-
Check setting out and bond
-
Check line level, plumb and gauge
-
Are joints full and correctly pointed
-
Have bricks been drawn from numerous packs
-
Are mortar mixes properly gauged
-
Are cavity widths correct and clean
-
Are wall ties and insulation properly located
-
Check position of horizontal and vertical DPC's
-
Are openings correctly formed, including lintels
-
Check cavity trays for position and cleanliness
-
Are all work and materials protected
-
Is finished brickwork face clean
-
Is area clean for following trades
-
Take mortar cubes for testing and record location where obtained
-
Check batching procedures for any site mixed mortar. Batch by volume
-
(NOTE: if a 5/3 1/2 mixer is used to mix mortar check that the constituents are added in the correct order)