Title Page
-
Site conducted
-
Conducted on
-
Prepared by
-
Shift
-
Part Number
-
Program/Part Description
-
Who is the Supervisor for this area?
-
Please conduct this audit with the supervisor.
Audit Checklist
-
Are all team members wearing required PPE?
-
Stop work and ask team member to follow all PPE requirements
-
Any slip/trip hazards present(loose cable/ potholes) ?
-
Are all safety checks completed and signed off by team leader ? Is the Lock Out Tag Out (LOTO) placard in place for each machine?
-
Inform Team Leader/Supervisor to correct the nonconformance
-
Is the fire exit route posted and is the route and aisle ways free from anything blocking them?
-
Are fire extinguishers in place and their tags are current?
-
Are any fire extinguisher blocked?
-
Are oily rags stored properly and all flammable items stored in the flammable cabinet?
-
Are any electrical panels blocked?
-
Do all containers for liquids and chemicals have WHIMIS labels on them? Verify the correct WHMIS label used.
-
Are any required error proofing / sensor checks completed and functioning?
-
Stop work and ask operator to complete the check. Inform and assign action to supervisor of non-conformance. If bypassed, confirm there is an active MAR. Otherwise shut down work cell until containment is in place.
-
Cross section checks if in extrusion.
-
Are all red rabbits labeled with calibration sticker? Ensure calibration date is valid.
-
Assign action to Quality Engineer for correction
-
Does the area have an active Quality Alert or Manufacturing Action Request?
-
Record any active Alert number(s)
-
Are the operators signed off on the alert?
-
Stop work, contact line leader to ensure employees are signed off.
-
Are the operators following the alerts instructions?
-
Instruct Line Leader to review alert with operator for re-training.
-
Is there a reference sample available and does it match the current production run? (Not applicable for Extrusion/WIP Product)
-
Assign action to Quality Engineer.
-
Are all required II sheets completed? Confirm frequency of the required checks.
-
Is the First Off/Last Off completed? Verify that the tag is filled out properly and signed off.
-
Are the parts within specification? Confirm that the Line Leader can demonstrate correctly how to measure a part on the fixture at the required frequency.
-
If parts are out of spec, stop the work cell and inform supervisor.
-
Are any required run sheets completed? Are all process parameters monitored at the required frequency? Are the KPI's within spec?
-
Are the out of spec KPI's validated, identified/signed by the Supervisor and is there a MAR in place?
-
Inform Supervisor to correct immediately.
-
Are all operators logged into Dalmatian?
-
Instruct Team Leader to have all operators (except Temporary) log onto Dalmatian.
-
Is the training matrix posted and current with all operators on it?
-
Are there any cleaning tools being used on the parts by operators?
-
Are the required tools and frequency for replacement indicated on the Work Instruction?
-
Assign Action to Manufacturing Engineer for correction.
-
Does this workcell have a GP12 station? If yes, observe the GP12 area for the following questions.
-
Are the GP12 inspectors following a visual inspection instruction dedicated to GP12 criteria?
-
Assign action to Quality Engineer to correct the nonconformance
-
Are the GP12 inspectors trained on the instruction? Look for training sign-off.
-
Assign action to Quality Engineer to correct the nonconformance
-
Is the GP12 station equipped with sufficient lighting and tools/equipment needed for inspection?
-
Assign action to Quality Engineer to correct the nonconformance
-
GP12 inspection is only applicable for workcells with new launches
-
Are there Standard Work Instructions for this workcell?
-
Are operators following Standard Work and signed off on the work instructions?
-
Inform Supervisor to retrain operators on following Standard Work and obtain sign-off
-
Assign action to Manufacturing Engineer for correction
-
Does the correct packaging and labelling of finished product match with Standardized Work (Packaging Instructions)? Are all containers stacked properly?
-
Assign action to Manufacturing Engineer for correction
-
Ask the supervisor / line leader if there is an active Engineering Change taking place in the work cell?
-
Is the change alert posted?
-
Assign action to Program Manager.
-
Is todays date the same or past the effective start date of the alert?
-
Assign action to Program Manager.
-
Are there any instructions to modify the process? (i.e. special labeling requirements)
-
Are the operators following its instruction?
-
Stop work and inform Line Leader to re-train operator.
-
Are the operators using scrap tags to identify nonconforming product and is it being stored/disposed of appropriately?
-
Assign action to Supervisor to correct nonconformance.
-
Is scrapped product being effectively recorded in the workcell? Verify scrap product entries on Dalmation.
-
Assign action to Supervisor to correct nonconformance.
-
Are all WIP racks present and in good condition?<br>Is all Scratch proofing material present and in good condition on all contact surfaces?
-
Assign action to Manufacturing Engineer for correction.
-
Is the Level 2 LPA completed for this workcell in the past month? Verify audit is posted on the Level 1 Production Board.
-
Inform Supervisor to conduct LPA within the first hour of starting production.