  • Appendix 2 - Photo Report for ENGINE Audit

  • Steering gear oil storage tank actual rob of oil in the tank and max capacity of the tank

  • MSB and ESB, 440V and 220V, low insulation alarm setting values x 3

  • Clear photos of sounding pipes in engine room floor platform x 2

  • Emergency generator fuel level tank showing clearly oil level minimum oil level required level marking. X 2

  • Fuel posted on emergency gen fuel tank

  • Engine room – all decks. X 3

  • Steering gear room entrance from engine room to steering gear room. X 3

  • Purifier Room

  • Bilges X 2

  • Generator room X 2

  • Emergency Fire Pump X 2

  • Chemical Store X 2

  • Workshop – Showing notices placed near grinder

  • Emergency fire pump starting procedures

  • Operating instruction posted at fixed fire extinguishing systems X 2

  • Engine Alarms Panel and outstanding alarms X 2

  • Bunker Pipelines showing current condition. Pressure testing date of bunker pipelines photo of stencilled area X 2

  • Emg. Overboard discharge valve warning notice X 2

  • OWS 3way valve and surrounding piping X 2

  • Latest seal nos clearly showing seal nos attached to emergency bilge suction valve and Entry in Log Book (date clearly showing in Log Book X 2

  • Engine Room all Emergency exit doors in closed and open position X 2

  • Emergency generator fuel level tank showing clearly oil level minimum oil level required level marking

  • Calculations Sheet of Minimum Quantity of Fuel Required for Emergency Gen running on Full load for 18 Hrs

  • Approved smoking area in ACCOMODATION AND ENGINE ROOM, clearly showing arrangement of exhaust fan X 4

  • Appendix 3 - Photo Report for Operational tests for ENGINE Audit

  • Operation of Emergency Steering X 2

  • Operation of 3- way Valve or stopping of the OWS Pump when 15PPM alarm sounds

  • OWS 15 PPM ( 0 to 15 PPM alarm to be displayed on the Screen)

  • Test Fire detector fitted near hot- well cascade tank for the boiler and show its

  • Provide photograph of the setting for the low insulation alarm

  • Show operation of any one Quick closing valve X 2

  • Operation of Emergency Fire Pump and Discharge Pressure at Pressure gauge on Bridge Wing X 2

  • Operation of Incinerator Emergency Stop

  • Bilge alarm Test

  • Sewage Treatment Plant in operation

  • Oil mist Detector Alarm X 2

  • Operation of Sounding Pipe Self Closing mechanism

  • Engineers call alarm X 2

  • Operation of Funnel Flaps X 2

  • Operation of Engine Room Blowers Shut Off X 2

  • Operation of Purifier Room Damper X 2

  • Operation of Emergency Generator

  • Operation of Reefer Room Alarms X 2

  • Operation of Dead Man Alarm System X 2

  • Sludge Tank Overfill alarm

  • Bilge Tank Overfill alarm

  • Overflow Tank Overfill alarm X 2

  • Scavenge Drain Tank Overfill alarm

  • Testing of the Low Insulation Alarm Fault for Switch Board – 220 V and 440 V

  • Overflow alarm function on Purifier

  • Operation of UMS panel in Mess Room

  • Operation of ME scrubber – high Value Alarm ( if fitted) X 2

  • Emergency Stop on Workshop Machinery X 2

  • Operation of Engine Room Crane X 2

  • Operation of Emergency Generator Fuel Valve Cut off

  • Man engine local control test

  • Details of Updated PMS Screen , including Outstanding Jobs Overdue Jobs X 2

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.