Information
-
Name:
-
Date:
-
Location:
-
Stope:
-
Level:
-
Supervisor:
Pre Blast Inspection
-
Is all gear removed from heading (above and below blast)?
-
Are the mucking wedges moved and set up?
-
Are serviced pulled back (above and below blast)?
-
Are all holes drilled accordinly to print?
-
Are all BT holes flagged and checked?
-
Has the inverse been probed, cleaned and mapped?
-
Have the results been communicated to supervisor and engineer?
-
Has powder been ordered?
-
Is all necessary gear/equipment available?
-
What gear/equipment is needed?
-
Checked electrical service to fan?
-
Are silnuts/barricades required for open holes?
-
Is Central Blast line presinent to standard?
-
Cell Supervisor:
-
Boart Supervisor:
-
Planner: