Title Page
-
Project
-
Date & Time
-
Form Completed By
-
Location
Plant/Lifting Equipment
-
Contractor Hiring Lorry Loader
-
Lorry Loader Hire Company
-
Lorry Loader Type (Make & Model)
-
Vehicle Registration
Load to be Lifted
-
Load to be Lifted
Documentation
-
Confirmation By the contractors Lifting Supervisor: Please ensure the following items have been checked and confirmed prior to the use of Hiab’s on this project. The following documents are with the unit and in order:
-
Current 12 monthly thorough examination
-
Current 6 monthly thorough examination certificate for lifting accessories. (Chains, Shackles, etc.) NB. *Webbing slings are not to be used on a Clipfine contract after 6 months from the date of the original certificate of test and thorough examination.
-
The results of weekly inspections of the working gear anchorages, automatic safe load indicator, de-ricking interlock, and other safety devices entered on a statutory inspection report.
-
The unit operator is in possession of a CITB CPCS A36 Card ALMLMI Card or RTITB Hiab Card. ( Note No other cards are accepted for carrying out Hiab operations)
-
There is an adequate lifting plan in place for each lift to be undertaken.
Signed by Contractors Lifting Supervisor
-
Signed by Contractors Lifting Supervisor
Visual Inspection
Visual Inspection
-
Confirmation by the Hiab Operator: I have carried out a visual inspection of the following and have not observed any defects, which will affect the safe operation of the Hiab. Important - If there is any defects do not use the crane, advise Clipfine and get the defect rectified before use.
-
Hook block safety catch.
-
Operation of ASLI and alarm.
-
Hydraulic tank and pipes.
-
All crane lights
-
Ropes (for spooling and kinks).
-
General safety assembly and operation of the boom.
-
Fly assembly with over-run device attached.
-
Over hoist limits, if fitted
-
Operation of controls.
-
Outrigger floats.
-
Outrigger timber pads.
-
Rope anchor and pins
-
Tyres in good condition and at the correct pressure.
-
Suspension locking system operational
-
Lorry Loader Operator - I have carried out the visual inspections and understand the Guidance notes.
Guidance Notes
-
1 No crane / Hiab must work on site unless all the appropriate certificates are with the crane and in order (photocopies of certificates to be kept in the Construction office).
-
2 All lifts to be undertaken are to be vertical unless authorised in writing by an engineer.
-
3 The weight of the load being lifted must be known.
-
4 Ground conditions must be suitable for the weight of Hiab and load.
-
5 Outriggers must always be used and be adequately supported as per the provider's lift plan.
-
6 Observe safe clearances of electric power cables.
-
7 The Rated Capacity (SWL) is never exceeded.
-
8 Check that there is adequate clearance around the lift area.
-
9 When lifting, stop briefly when the load is just off the ground and check the stability of Hiab.
-
Lorry Loader Operator - I have carried out the visual inspections and understand the Guidance notes.