Information

  • Month/Document No.

  • Audit Title

  • Client / Site

  • Elevation assessed & works completed.

  • Conducted on

  • Prepared by

  • Location
  • Personnel

  • Rules of WIR and Progress Reporting
    1. All reports need to be in for the dates that have been agreed on the reporting timetable. If there are any reports missing the reporting manager (AS) needs to make contact with the contracts manager (JHL), finding out why reports are missing and getting confirmation when they will be in. Everybody needs to remember that there is a maximum of three working days over date of when the report needs to be in. It is not an option for reports not be done after three days.
    2. Generally, there should be reports prepared for each elevation, where all assessed levels are listed. Each single report may include more than one elevation. However, it must be clearly described in the introduction which facades have been examined and what works have been completed during the assessment.
    3. When job is being handed over to the project manager/contracts manager, the Reporting manager must prepare a construction plan drawing of the project, number each elevation and then refer to these numbers when conducting Work Inspections.
    4. Construction plan layout drawings with numbered elevations must be saved onto the M Clarkes reporting folder on the Network. Jobs/Projects/Quality.
    5. Each report should include in the introduction (cover page of report) description of the assessed façade (assigned number) along with the description of type of works which were completed as assessed façade (assigned number) along with description of type of works which were completed and assessed by project manager.
    6. We have issued standard detail drawings reference numbers D01, D02, D03, D04, D05 and so on. These are available in "M Clarkes Guidance Booklet” and need to be referred to throughout WIR and clearly show what is required.
    7. The report with error/failure marked RED, must be saved on the system. The next report that will follow must show how the error was rectified. If improvement was not possible, eg: due to soft ground/lack of access, it needs to be described/explained. The answers column still needs to be highlighted red. However, if the error was rectified the section should be changed to green. The comment section is to be used for explanations of how and when error was rectified.
    8. If project manager has found an error during the assessment, it must be noted and fixed before consecutive stages of works progresses, eg: CP board cannot start before Metsec sub frame is properly fixed. Quality Control Manager cannot accept the next WIR report until everything is fixed and up to date on the previous report. This is to make sure that all errors are corrected, and there are no error omissions.
    9. Progress reports need to be genuine and relevant.
    10. It is important that progress reports always have delay events.
    11. All reports have to be sent to main contractor and subcontractor.


  • Elevation assessed & works completed.

  • Completed by Subcontractors:

Acceptance criteria/ Rules of Proper Workmanship 1. No work to be performed unless environmental conditions are as specified in therms of temperature, humidity and wind exposure. 2. Mixing time and proportions must be correct as per specification. 3. Safe systems of work must be enforced for working at height.

A. Pre-start checks.

  • 1. Are conditions, access safe?<br>

  • Add media

  • 2. Were materials properly stored? (Must be covered when not in use)<br>

  • Add media

  • 3. Is substrate dry , clean and free from defects.?

  • Add media

Preparation for Gebrick panel system installation.

  • 4. Have the operatives been provided with sufficient training in the specified system?<br>

  • Add media

  • 4.1 Have movement joints been maintained in the designed locations?<br>

  • Add media

  • 5. Have the operatives been given relevant drawings and details to complete the works?<br>

  • Add media

  • 6. Are EPDM's correctly installed?<br>

  • Add media

  • 7. Is the wall substrate (CP board surface)to correct line and level? <br><br><br>This is of great importance as it would not be possible to make any adjustments to levels during further stages of works i.e application of Gebrik panels.

  • Add media

  • 8. Are sills, pods and flashings installed to the correct design details? Thickness colour and depth?<br>

  • Add media

  • 9. Are cills, pods and flashings installed to suit correct location?<br>

  • Add media

  • 10. Have all vents, brackets, rainwater pipes been taken through the CP board and handed over to the main contractor?<br>

  • Add media

  • 11. Has EPDM been installed to all vents, rain water pipes, louvre bracket fixing centres?<br>

  • Add media

  • 12. Has the correct and specified breather membrane been installed?<br>

  • Add media

  • 13. Has the breather membrane been dressed out and over horizontal flashings, pods and taped and sealed?<br>

  • Add media

  • 14. Has breather membrane been taped at vertical joints and overlapped by 300mm at horizontal joints?<br>

  • Add media

  • 15. Has the breather membrane been taped to and around all openings protrusions, as specified on the Reference Drawing D 03 of "MClarke reference booklet"?<br>

  • Add media

Inspection Results:

  • Signed off by the Project Manager

  • Signed off by the main contractor representative.

Starter Rail and Securing Components

  • 16. Has the rail been set out in accordance with the datum prior to application of Gebrick panels.?<br>

  • Add media

  • 16.1 Has a bead of PU foam been injected along the top edge of the secured rail to prevent water ingress up and behind the system.<br><br><br><br>

  • Add media

  • 16.2 Has a bead of PU foam been injected along the internal corner of the secured rail to prevent water ingress between the system and the rail.?<br>

  • Add media

  • 16.3 Has 5mm joint been removed from the first course of panels so the brick edges sits on the rail?<br>

  • Add media

  • 16.4 Has foam been notched at the back of the first course to the depth of the rail to avoid a "bell" effect at the base?<br>

  • Add media

  • 17. Has basetrack been fitted with appropriate fixings at 600mm centres?<br><br>

  • Add media

  • 18. Has base track been set out in proper line and level?<br>

  • Add media

  • 19. Has the Gebrik Corner Piece been installed as a first element, which while combined with properly set starter rail sets a right angle for installation of the first row of panels?<br><br>(Reference: MClarke Gebrick installation Guide)

  • Add media

  • 20. Have panels been drilled through in prelocated fixings locations?<br>

  • Add media

Sealing system. Purpose: To ensure water tightness, prevent heat loss and minimise air leakage. This also avoids movement between panels, which creates cracks in the subsequent mortar joints.

  • 21. Were chambers organised on site to cut components.<br><br>

  • Add media

  • 22. Were chambers fully filled at every vertical and horizontal abutment (foam should expand to (or out of) the pre-located openings across the top of the panels)<br><br>

  • Add media

  • 23. Are panels and corners flat.? (fixings to be tightened if necessary) <br><br>

  • Add media

  • 24. Has brick face been cleaned from any remains of PU?<br><br>

  • Add media

  • 25. Have fixings been fitted properly, not over tightened/under tightened . (If cracks are visible additional fixing must be used.)<br>

  • Add media

  • 26. Has the first panel been positioned on the starter rail, and tightly abutting the corner element panel?<br><br><br>

  • Add media

  • 27. Have panels been fixed into substrate with correct length and correct number of fixing as per specification?<br><br><br><br><br>I. Panels area of less than 10m2 to be fixed with 9no of fixings.<br>II. Panels area between 10-18 m to be fixed with 12no of fixings.<br>III. Panels area of more than 18m2 to be fixed with 16 no of fixings.

  • Add media

  • 28. Has specified/recommended PU Foam been injected to an abutment chamber using a system designed pistol applicator?<br><br><br>

  • Add media

  • 29. Have specified/recommended PU cutters and plugs been used, so as to make sure that facade is watertight?<br><br><br>

  • Add media

  • 30. Have abutments of the elements been stitched together with matching single brick slip glued into the location with specified adhesive, so stretcher bond pattern of bricks was achieved ?<br><br>

  • Add media

  • 31. Have perp joints been aligned as traditional brickwork ? (typically should be positioned half way between the brick immediately above and below) <br>

  • Add media

  • 32. Have all locations of fixings and abutments of the elements been pointed with recommended mortar, in order to maintain traditional brick appearance?<br><br>

  • Add media

  • 33. Have specified compressible sealant and additional flexible sealant been used at points where panels join Cills and frames of the openings?<br><br><br><br>(Reference: Gebrik installation guide, jamb detail D07, and cill detail drawings D06)

  • Add media

Brick slip application. Using cement based adhesive. Purpose: To maintain traditional brickwork appearance and prevent brick slip delamination.

  • 34. Was appropriate mix of cement based adhesive and water used ?(typically 9.25 l to 25 kg dry mix pro rata)<br>

  • Add media

  • 35. While mixing, was consistence of mixed adhesive smooth, left for few minutes and mixed again?<br><br>

  • Add media

  • 36. Was maximum allowed time for working with mixed adhesive obeyed? (approx. 3 hours, water can not be added once it is mixed)<br><br><br><br>

  • Add media

  • 37. Was proper amount of adhesive used ?( too much adhesive should not be used as the slips will sit proud of the panels and cast shadow in different angles of sunlight.<br><br>

  • Add media

  • 38. Are applied slip flat with adjoining Gebrick panels and corners.<br><br>

  • Add media

  • 39. Is brick face free from excess of adhesive.?<br><br><br><br>

  • Add media

Pointing: Purpose: To maintain traditional brickwork appearance and final protection from water ingress.

  • 40. Has mortar been batched?<br><br>

  • Add media

  • 41. Has the mortar been protected from subsequent inclement weather and direct sunlight until cured to avoid efflorescence and cracking?<br><br>

  • Add media

  • 42. Are joints fully filled so as to avoid lime staining?<br><br>

  • Add media

  • 43. Is brick face free from mortar staining?<br><br>

  • Add media

Inspection results:

  • Signed off by the project manager?

  • Signed off by the main contractor representative:

Post installation checks.

  • 44. Have scissor lifts /mast climber/cherry picker been cleaned? <br><br><br><br>

  • Add media

  • 45. Has adequate protection been used?<br><br><br><br>

  • Add media

  • 46. Has work area been left clean on completion?<br><br><br><br>

  • Add media

  • signed by main contractor representative.

  • signed by project/contract manager.

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.