Title Page
-
Site conducted
-
Location
-
Conducted on
-
Prepared by
Department Managers Daily Session Audits.
Cat4
-
Date
-
Session 1
Task
-
Fire extinguishers in place and fire exits clear
-
Is OAL running on the Assembly Lines
-
Why is it not running?
-
Are Finished Products Build Sheets on the Line in the correct order and being followed to standard?
-
Is dirty tooling being sent for cleaning when required?
-
Is Paperwork being managed correctly and showing good quality and visual standards
-
Concerns Raised/Identified
-
Remedial Action Taken
-
Why has action not been carried out?
Session 2
-
Time
Task
-
CAYG assessment of area/lines (Remove STF hazards)
-
Why has action not been carried out?
-
is OAL running on Assembly Lines?
-
Why not? is this machine or operator error?
-
Are Finished Products Build Sheets on Lines in the correct order and being followed to standard
-
Why has action not been carried out?
-
Are Gloves left laying around on the line?
-
check condition of steps/platforms
-
What have you done to resolve the issue?
-
Monitor giveaway on the lines
-
What are you doing to resolve this issue?
-
Any other Concerns Raised/Identified
-
What other issues did you identify?
-
What Remedial Action Has Been Taken?
Session 3
-
Time
Task
-
Correct use & storage of pallet trucks
-
Is OAL running on Assembly Lines
-
Why is OAL not running? is this operator error or system error
-
Are Finished Products Build Sheets on Lines and in the correct order and being followed
-
Why are they not on the line?
-
Are Proseal tools left laying around when not in use?
-
Why have they been left laying about? what action is being taken to rectify the issue?
-
Are there any air leaks?
-
Check gas/print on the lines (Check they are running to standard)
-
Any other Concerns Raised/Identified
-
What have you done to fix these issues?
-
What Remedial Action Has Been Taken?
Session 4
-
Time
Task
-
Pallet stored correctly and steps removed from line
-
What have you done to fix this issue?
-
Is OAL running on Assembly Lines?
-
Why is OAL not running? is this operator error or system failure
-
Are Finished Products Build Sheets on Lines and in order and being followed
-
Why not? what have you done to fix this issue?
-
Have you completed your Final area walkaround of the day?
-
Are Check weigher bins empty,film and labels removed from area
-
Why are they still on the line?
-
Have all machines at end of shift been turned off?
-
What machines been left on?
-
Any other Concerns Raised/Identified
-
What Remedial Action Has Been Taken?
Department Manager Sign Off
-
Print Name
-
Add signature