Project Details (Completion of all of the following fields is mandatory. Forms submitted without all fields completed will not be assessed.)

  • Audit Title/Project Description

  • Design Pack ECB Link ID (eg. ABC-1234)

  • Work Parcel/Contract No.

  • Separable Portion No.

  • Order No.

  • Site Address
  • Project Manager

  • Team Manager

  • Authority Number

  • Installer Name

  • Installation Date

Section 1

Superstructure

  • a. Superstructure Correctly assembled.

  • b. “H” Frames are correctly spaced.

  • c. Superstructure free of OH&S hazards.

  • d. Optic ducts correctly assembled.

  • e. Power runways correctly assembled.

  • Ref: TM00011 CN1234 CSD 26203

  • *Mandatory photo required - a fairly wide shot of the whole rack, may need to use arrows to highlight where your rack is.

Section 2

Rack Overall Photo

  • a. Correct rack used

  • b. Rack installed in the correct floor position

  • c. Rack level and plumb (check with spirit level)

  • d. Rack frame undamaged (Metal work, paint)

  • e. No doors on either front or rear of the rack.

  • Ref : TM00011 CN1234 CSD 26203 TM00315

  • *Mandatory photo required - a fairly wide shot of the whole rack.

Section 3

Rack Top Photo

  • a. Correct Rack Layout

  • b. Rack is Labelled correctly

  • c. Rack securely attached to superstructure or wall using correct mounting kits and earthing practices

  • d. Rack ducting / Convoluted tubing correctly mounted and as straight as possible secured with minimal cable ties

  • e. Earth Bonding bar installed correctly.

  • Ref: TM00011 TM00315

  • *Mandatory photo required - a photo of top of rack including labelling.

Section 4

Rack Bottom Photo

  • a. Bolted to floor in 4 places (each corner)

  • b. Rack electrically isolated from floor.

  • Ref: TM00011

  • *Mandatory photo required - a shot of fixing to floor and electrical isolation

Section 5

Fibre Labelling

  • a. Brady label style label used

  • b. Label is printed

  • c. Label shows NE Slot number and port name/number and EQ IN/OUT.

  • Ref: Design Pack TM00044 TM00315

  • *Mandatory photo required - close up shot to see fibre labelling and type of label.

Section 6

Fibre Drop Into MSE Rack

  • a. Yellow fibre ducting used. Cannot use convoluted tubes

  • b. Ducting not overfilled, 100 square max 300 fibres max. <br>

  • c. Fibre supported and secured no sharp edges

  • d. Velcro ties used to support optic fibre patch cords in rack

  • e. Excess fibre stored neatly

  • f. Fibres routed correctly - MBR 30mm maintained.

  • g. Ventilation hole in top of rack is not blocked by optic duct

  • Ref: TM00183-A01 TM00315

  • *Mandatory photo required - a photo of fibre ducting

Section 7

Power to MSE

  • a. MSE 8840 router shall be power from a minimum of two Low Ohmic Distribution (LOD) panels

  • b. MSE 8840 requires eight 32 amp circuit breakers at the LOD panel

  • c. LOD Circuit Breaker/Fuses correctly Labelled. (Destination Rack Identified)

  • d. Power cable lugs crimped correctly/ securely at LOD

  • Ref: TM00315

  • *Mandatory photo required - close up Photo of front of LOD

Section 8

Power Cables

  • a. The two input DC blocks and earth post lug from the rear left hand side are to be cable tied to the rear left hand side cable tray of the rack. The other two input DC blocks and earth post lug from the rear right hand side are to be cable tied to the rear right hand side cable tray of the rack. Ensure that they are cable tied side by side to the cable tray of the rack and not cable tied in a bunch

  • b. Power cables must have crimped double ringed cable lugs connected and secured to terminal screws on the rear of the subrack.

  • c. Power cables are cable tied side by side to the cable tray of the rack (should not be cable tied in a bunch)

  • d. Ensure that plastic cover for the DC power blocks is fitted

  • e. Correct colour power cables used (should be Red insulated power cable to return terminals, blue insulated power cables connected to -48V terminals, and green / yellow insulated cables connected to earth terminals)

  • f. Power cables are labelled with the following information on both feeds; Feed / DPU No / Floor / Suite / Rack / CB size & No e.g. FEED B/ DPU 2 / 7 / 10 / 3 / 32a

  • g. Heatshrink on all lugs

  • h. Cables not damaged/ against a sharp edge

  • Ref: TM00315

  • *Mandatory photo required - photo of power cable terminations and slack in bottom of rack.

Section 9

MSE Subrack

  • a. Tellabs MSE 8840 located in correct position in rack

  • b. Tellabs equipment mounted on shelf & secured to rack rails

  • c. Slots without cards have blanking panels installed

  • d. Correct cards put in slots. Cards put in correct order.

  • e. Correct colour data cables used (red for rollover, blue for straight etc)

  • Ref: TM00315

  • *Mandatory photo required - photo of 8840 and fibre management

Section 10

Comms Cables and BITS clocks

  • a. BITS Clock Cable; Tellabs 8840 router requires two direct separate Building Integrated Timing Supply (BITS) clock feeds per node. . The BITS clock feeds are to connect to the IN A, DB-15 connectors at the rear of the chassis using a metal shell connector.

  • b. Ensure the BITS Clock cable is terminated at the DDF

  • c. Screen/Drain Wire of BITS Clock Cable from Router must not be Earthed/terminate at the DDF

  • d. Cables labelled correctly

  • e. Two screened cables for BITS clock shall be cabled and tied to the rear right hand side cable tray of the rack. Ensure that there is separation from DC power cables

  • *Mandatory photo required - a shot to include the bits cables running on correct side of rack and terminated and plugged into rear of chassis. Try to include labels – may not be able to see all text

Section 11

Comms Cable Management connection

  • a. CAT5 cable that connects to the rear serial RS-232 port of the MSE 8840 router shall have approx 2 meter’s of slack coiled up. It is to be connected to Serial RS-232 port with a DB-9 at the rear of the chassis. The other end of the cable is to connect to a serial port on the OOB Cisco 2511 terminal server

  • b. Serial DB9 and Ethernet RJ45 management cables shall be cabled and tied to the rear left hand side cable tray of the rack.

  • c. Ensure that there is separation from the DC power cables. (Min 50 mm)

  • d. Cables labelled correctly with Brady labels

  • Ref: TM00315

  • *Mandatory photo required - a shot to include the bits cables running on correct side of rack and terminated and plugged into rear of chassis. Try to include label.

Section 12

Fibre Storage in Rack

  • a. A minimum of two optical fibre storage trays must be installed above each Tellabs 8840 router.

  • b. Ensure that there is enough space between the two storage trays to access the cords, 1 to 2 RU space shall be left between each tray. All new installations must have 3 storage trays.

  • c. Fibre trays must have minimum of 4 su’s between top of MSE and lowest fibre tray to allow for Copper management.

  • Ref: TM00315

  • Please insert photos.

Completion

  • General Comments

  • This is the end of Photo Audit. Your audit result can be found under "Audits" menu. You can edit, preview and send your result via Email

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.