Information
-
Document No.
-
Audit Title
-
Client / Site
-
Conducted on
-
Prepared by
-
Location
-
Personnel
-
Process
-
Customer
-
Part No
-
Description
-
Prime Contractor
-
Po/Rev Level
-
Part Quantity
-
Serial/Lot No
-
Alloy/Heat Treat Condition/Hardness
-
Processing Spec
-
other PO Requirements
6.1.2 Paperwork review
-
are part no, specs, and rev levels flowed down correctly
-
Are frozen processes identified and if so has customer approval been obtained
-
If a follow on order, have PO requirements been reviewed for change
-
Are processing and inspection test requirements flowed down correctly
-
Does the shop paper provide the following
-
Traceable part identification
-
All processing steps identified including procedure numbers as applicable
-
All inspection and test requirements identified
-
All inspection and test results recorded on shop paper or traceable in shop records
-
All relevant variable data from process parameters controlled by operator recorded on shop paper or traceable to job in shop records
-
All operations, inspections and tests done in sequence recorded or traceable to specific process line/workstations, operator/inspector/technician and date done
-
If rework is done are all operations documented
-
All test coupons identified and traceable to specific pieces/lots. Coupons processed through all processing steps on piece/lots they represent including pre- and post cycles and/or mechanical cleaning and thermal cycles
-
All process, test and inspection equipment calibrated and traceable to part shop documents
-
List Equiptment
6.1.3 Process observations
-
Recieving,paperwork generation, requirement review and Recieving inspection
-
Pre-process cleaning (Record pre cleaning method e.g vapour degrease or none required)
-
Pre-thermal operations (record time and temp or none required)
-
Time limits between preparation and paint application
-
Masking (record masking type tape,wax, none required)
-
Do paint materials meet specification/technical data sheet requirements and are materials within shelf life
-
Fixuring/racking (record basket,hook,wire,tool)
-
Processing (record only if non compliant)
-
Post process cleaning (record method)
-
Post thermal operations (record time and temperature, time delay since processing, none required)
-
Final inspection
-
Packing and shipping (record method)
-
Solution and/or material testing( reviewed and acceptable, if material testing (paint) what was done
-
Periodic and/or lot testing (record testing done e.g lot, visual, thickness. Monthly - salt spray, coating weight etc)
-
Was periodic testing done and documented (see table1 )
6.1.4 Lot acceptance testing/inspection
-
Does the definition of "Lot" as established by the supplier conform to the definition outlined by the spec
-
If the parts were shipped before completion of lot testing was this authorised by the customer in writing
-
Did the sampling plan meet spec and/or customer requirements
-
Was hardware held pending resolution of nonconformances noted during testing
-
Was lot testing required
-
Was lot testing preformed and documented
-
Was lot testing in conformance with spec with and/or customer requirements
6.1.5 Operator control and job acceptance
-
List the operators who preformed processing operations
-
Are the operators trained and approved
-
Are all operations, inspections and tests properly signed off or stamped and dated as required, by the correct operator or department
-
Describe
-
Does all processing, testing, and inspection conform to requirements
6.1.6 Certification and reports or test reports
-
Does certification show compliance to all the requirements and reflect actual data as required
-
Did this job comply with all the requirements
-
Certificate or test report no (NA if certificate raised after audit completed)
-
Certification or test report date ( NA if cert not raised)
-
Auditee
-
Auditor
Report of Audit findings
-
List findings
Evidence
-
Evidence submitted 1
-
Evidence submitted 2
-
Evidence submitted 3
-
Evidence submitted 4
-
Evidence submitted 5
-
Evidence submitted 6
-
Auditor