Title Page

  • Audit Title

  • Client: Hoxton Press / Site: 554003

  • Conducted on

  • Prepared by

  • Location

1. Completed By Trade Contractor.

  • Detail of work to be carried out,

  • Area of site undergoing excavation, reduced level digging or penetration are described by map or drawing to be attached.

Precautions to be taken to avoid danger & damage to buried services such as Radar/CAT/Acoustic Wall Device:

  • CAT Scan Carried out:

  • Confirmation that the area to be disturbed has been surveyed. The coordinated drawing is up to date.

  • Are services marked up and do all understand the markings in relation to services ?

  • Has the CAT & GENNY and used in locating services ?

  • Confirm that the operators / Banksman and machine driver have been briefed on services and precautions.

  • ALL operators are aware that they should not deviate from the Method Statement. If services encountered during the works are different ( e.g. Type, location etc ) to those already identified they MUST stop work and consult the supervisor and services coordinator.

  • If using power tools or machinery within 500mm either side of the line of known buried services is unavoidable. Detail the additional control measures to be taken below:

  • Extra detailed control measures if needed:

  • Confirm that the service(s) (National Grid, BT etc) emergency contact details are known for immediate communications.

Trade Contractor Supervisor Confirmation:

  • Confirmation that the above items have been discussed with all those concerned and agreed with the information supplied.

Driver Confirmation:

  • I have discussed and agree with all items above.

Banksman Confirmation:

  • I have discussed and agree with all items above.

2. Services Co-ordinator Confirmation:

  • I have discussed and agree with all the items above. All operatives understand the precautions to be taken with the works:

3. Permit Closed Out:

  • All excavation(s) have been left in a safe and secure manner with appropriate barriers to prevent falls. Signage must be in place. If excavation has been back-filled, that it has the correct identification markings for services and is added to the drawings.

  • Photos taken to show exposed services:

  • Photos taken to show installed marked services:

  • All information is added to as built drawing:

  • Wates BSC name:

  • Contractor Supervisor name:

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.