Information
-
Document No.
-
Audit Title
-
Client / Site
-
Conducted on
-
Prepared by
-
Location
-
Personnel
-
Date & time
Responsibilities / Paperwork
-
Has the PTW holder signed
-
Has the PTW authority signed and approved the PTW
-
Does everyone know there responsibilities under the PTW system
PTW Register
-
Is their a PTW register?
-
Is the PTW register used / current?
PTW Training
-
Are all persons responsible for implementing The PTW trained .
-
What training have they had ?
PTW Authority
-
Is the PTW authority controlling, coordinating, completing, monitoring and reviewing the PTW system?
-
Is the permit authoriser approving the authority to work?
-
Does the permit Authority know his responsibilities under the permit system ie close out and transfer of authority?
PTW Holder
-
Is the PTW holder gathering the information and completing the PTW in conjunction with the PTW Authoriser?
-
Is the PTW retained at the work location?
-
Have all parties signed onto the PTW?
-
Is the PTW closed out within 12 hour or passed on to the next shift
-
Do those involved understand how long a PTW can be opened for?
-
Did the permit holder close out the permit (sign)
Confined Space permit
-
Does the vessel meet the permit requirements for confined spaces?
-
Is the PTW retained at the work location?
-
Have all parties signed onto the PTW?
-
Is the PTW closed out within 24/12 hrs
-
Has the worker received confined space training?<br><br><br>
-
Has the gas testing been entered onto the permit
-
Do the people involved understand the gas testing requirements?
Working at Height Permit
-
Does the vessel meet the permit requirements for Working at heights?
-
Is the PTW holder gathering the information and completing the PTW in conjunction with the PTW Authoriser?
-
Is the PTW retained at the work location?
-
Have all parties signed onto the PTW?
-
Is the PTW closed out within the shift or 24 hrs
-
Are the workers trained in working at height?<br>
-
Is their a rescue plan in place?<br>
Use of Workbox Permit
-
Does the project meet the permit requirements Lifting?
-
Is the PTW holder gathering the information and completing the PTW in conjunction with the PTW Authoriser?
-
Is the PTW retained at the work location?
-
Have all parties signed onto the PTW?
-
Is the PTW closed out within 12 hrs
LOTO Permit
-
Does the vessel meet the permit requirements for Isolation
-
Is the PTW holder gathering the information and completing the PTW in conjunction with the PTW Authoriser?
-
Is the PTW retained at the work location?
-
Have all parties signed onto the PTW?
-
Is the PTW closed out within 12/24 hrs
-
Have the isolations been entered onto the permit?
Hot Works Permit
-
Does the vessel meet the permit requirements for Hot Works?
-
Is the PTW holder gathering the information and completing the PTW in conjunction with the PTW Authoriser?
-
Is the PTW retained at the work location?
-
Have all parties signed onto the PTW?
-
Is the PTW closed out within 12 hrs
Conclusion
Actions
-
Action 1
-
Action 2
-
Action 3
-
Signatures