Title Page
-
Audit Title
-
INSPECTION REPORT FOR DISTRIBUTION BOARDS
CVSG ASSET SERVICES PTY LTD
ABN 62 128 821 698
INSPECTION DETAILS
-
Select date
-
NAME OF PERSON UNDERTAKING TESTS
-
NAME OF FACILITY?
-
SWITCHBOARD NUMBER
-
SWITCHBOARD TYPE
-
ASSET NO. BAR CODE AVAILABLE?
-
Enter barcode
INSPECTION
-
All electrical equipment & fittings in good condition?
-
Wiring and switches - Check general condition of conduits, connectors, switches and wiring especially in damp and outdoor areas.
-
Operation - Check to ensure all items of equipment are capable of satisfactory operation.
-
Contacts and relays - Check and clean contacts or relays. Notify the Principal’s Representative of any faulty contacts or relays that need replacement.
-
Fuses Check all fuses for correct rating. Check fuse connections are tight. Inspect fuse-links for signs of deterioration.
-
Electrical connections - Check connections at motors, switchboards and equipment subject to vibration. Re-tighten cable terminations as necessary
-
Interpole barriers - Inspect interpole barriers and shrouds where fitted.
-
Switchboard - Vacuum clean the switchboard interior and remove an rubbish.
-
Switchgear including ACBs, contactors, isolators, busties, controls, etc • Inspect indicating devices such as mechanical 'ON' and 'OFF' indicators, etc to ensure that they are in good order and operating correctly • Verify that interlocks and padlocking devices operate correctly and make adjustments where required eg castel key interlocks for main isolators and bus-tie switches, automatic transfer switches.
-
Provide details of follow up if required.
SWITCHBOARD ROOM / CUPBOARD
-
Check clearance around switchboard. Ensure rubbish, spare parts, stock etc does not infringe on mandatory clearances around switchboard.
-
Check clear access to and from exit doors for switch rooms
-
Check all exit doors are clearly labelled and are properly secured to prevent the entrance of an unauthorised person from outside whilst at all times allowing free escape from inside.
-
Check effectiveness of ventilation of switch room
-
Vacuum clean floor space.
-
Provide detail of follow up if required.
SWITCHBOARD
-
Check effectiveness of ventilation of switchboard cubicles (if applicable). Clean and/or replace filter(s) if fitted.
-
Open and/or remove all doors, access panels, cable covers, escutcheon panels etc and carry out the following work: • Inspect for any evidence of dampness or condensation • Check operation of any heater and inspect any anticondensation finishes for signs of deterioration • Check for smells that might indicate overloading or deterioration of equipment/components. • Check for noises that might indicate electrical discharge, tracking or looseness of components or equipment that requires servicing eg contactors • Inspect insulation for signs of deterioration or tracking • Inspect switchgear, controls, cabling, busbars etc for dust build-up, signs of overheating/loose connections and general condition of equipment • Check any penetrations in the switchboard are sealed • Check for rodent/pest infestation. Treat and clean as required Close and/or reinstall doors, access panels, cable covers, escutcheon panels etc after the thermoscan and all other items have been completed. Ensure all fixings for panels etc are installed and securely tightened.
-
Check labels are legible and suitably attached. Refix any labels that have been dislodged.
-
Check circuit schedules are available and legible.
-
Clean all external surfaces of the switchboard to remove any dust.
-
Take tong ammeter readings of incoming supply and distribution cables.
-
A phase current.
-
B phase current
-
C Phase current
-
Check that incoming current readings are balanced to within 10% between phases.
-
Provide detail of follow up if required.
SURGE DIVERTERS
-
• Inspect condition of surge diverters, where fitted, in accordance with manufacturer's instructions and report if less then 50% of life remaining • Inspect existing surge diverters to determine if they visually indicate the integrity of the surge diverter protection • Inspect all main switchboards to determine if surge diverters are fitted Report to Principal’s Representative your findings above.
-
Provide detail of follow up if required.
INSPECTION COMPLETE
-
Add signature