Title Page

  • Audit Title

  • INSPECTION REPORT FOR MSSBs
    CVSG ASSET SERVICES PTY LTD
    ABN 62 128 821 698

INSPECTION DETAILS

  • Select date

  • NAME OF PERSON UNDERTAKING TESTS

  • NAME OF FACILITY?

  • SWITCHBOARD NUMBER

  • SWITCHBOARD TYPE

  • ASSET NO. BAR CODE AVAILABLE?

  • Enter barcode

INSPECTION

  • All electrical equipment & fittings in good condition?

  • Remove front panel, dust and clean components, remove accumulated rubbish and redundant wiring.

  • Check that all indicator lights are working.

  • Check fuse sizes correspond with those in the drawings.

  • Visually check all wiring and tidy up where necessary, check all connections including earthing.

  • Check chiller contactors thoroughly for signs of excessive arcing on contacts.

  • Check fire isolation relays, vibration switches, reverse phase relays, phase failure relays etc. check all contacts for signs of excessive pitting.

  • Check set point and operation of all motor running amps.

  • Provide details of follow up if required.

SWITCHBOARD ROOM / CUPBOARD

  • Check clearance around switchboard. Ensure rubbish, spare parts, stock etc does not infringe on mandatory clearances around switchboard.

  • Check effectiveness of ventilation of switch room

  • Vacuum clean floor space.

  • Provide detail of follow up if required.

SWITCHBOARD

  • Check effectiveness of ventilation of switchboard cubicles (if applicable). Clean and/or replace filter(s) if fitted.

  • Open and/or remove all doors, access panels, cable covers, escutcheon panels etc and carry out the following work: • Inspect for any evidence of dampness or condensation • Check operation of any heater and inspect any anticondensation finishes for signs of deterioration • Check for smells that might indicate overloading or deterioration of equipment/components. • Check for noises that might indicate electrical discharge, tracking or looseness of components or equipment that requires servicing eg contactors • Inspect insulation for signs of deterioration or tracking • Inspect switchgear, controls, cabling, busbars etc for dust build-up, signs of overheating/loose connections and general condition of equipment • Check any penetrations in the switchboard are sealed • Check for rodent/pest infestation. Treat and clean as required Close and/or reinstall doors, access panels, cable covers, escutcheon panels etc after the thermoscan and all other items have been completed. Ensure all fixings for panels etc are installed and securely tightened.

  • Check labels are legible and suitably attached. Refix any labels that have been dislodged.

  • Check circuit schedules are available and legible.

  • Clean all external surfaces of the switchboard to remove any dust.

  • Take tong ammeter readings of incoming supply and distribution cables.

  • A phase current.

  • B phase current

  • C Phase current

  • Provide detail of follow up if required.

SURGE DIVERTERS

  • • Inspect condition of surge diverters, where fitted, in accordance with manufacturer's instructions and report if less then 50% of life remaining • Inspect existing surge diverters to determine if they visually indicate the integrity of the surge diverter protection • Inspect all main switchboards to determine if surge diverters are fitted Report to Principal’s Representative your findings above.

  • Provide detail of follow up if required.

INSPECTION COMPLETE

  • Add signature

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.