Title Page
-
Site conducted
-
Job Address:
-
Building Description:
-
Completed By :
-
Completed On :
1.0 Materials
-
1.1 - Window flashings are onsite
-
1.12 - Check bigger flashings required , garage, sliding doors etc
-
1.2 - 40x40 Prime moulding windows
-
1.3 - 31x11 Prime mouldings
-
1.4 - 4.5mm PVC joint moulding
-
1.5 - 42x11 Prime mouldings (cover strips)
-
1.6 - Cladding order delivered
-
1.7 - Check cladding specifications / all H flashings etc are onsite
-
1.8 - Are there eaves with in 450mm of boundry ? fire rating
-
1.9 - C/Class/ Timber delivery for framing soffits
-
1.91 - Are the correct size sheets delivered to site (ref cladding mark up)
2.0 Trades
-
2.1 - Sarking paper completed
-
2.2 - All roofing completed / check flashings around job
-
2.3 - Scaffolding has been organised
-
2.4 - External wires, take photos of all wires fixed with nails only
3.0 office
-
3.1 - Take photo of cladding orders / save to BT
-
3.2 - Supervisor agrees that any services that are not fixed to a nail (set location ) we will not be responsible for pulling through services to save patching
-
3.3 - Has supervisor signed off
-
3.4 - Is there adequate room in bin for cladding waste
-
3.5 - Has there been any changes to cladding plans
-
3.6 - Cladding mark up received / saved to BT
4.0 Defect Items:
-