Title Page
-
To be completed by the H&S Adviser or Nominated person prior to the start of construction work on site. Audit reports shall form part o f the CDM Health and Safety file.
-
Sensible Monitoring Audit Completed By:
-
Site Manager:
-
Contract Number:
-
Project Title:
-
Conducted on
Key Project Documentation
-
Any H&S actions identified shall be entered onto Audit / Inspection Action Log and brought to the urgent attention of the appropriate personnel as soon as possible. Contractor / Project Manager to be notified of actions required / taken.
-
1) Is the construction phase plan (CPP) in place, specific to this project and recommended for acceptance by the CDM Coordinator?
-
Comments:
-
Attach any images relevant to question 1 here.
-
2) Where appropriate has the F10 Notification of Project form?
-
Comments:
-
Attach any images relevant to question 2 here.
-
3) How the CPP Plan is actively promoted within the project?<br>(is it actively challenged / reviewed at the progress / H&S meetings ?)
-
Comments:
-
Attach any images relevant to question 3 here.
-
4) Have Health & Safety targets and objectives been set for the project and do they form part of the construction phase plan?<br>(There must be an indication of what needs to be done to maintain and improve health and safety in the project.)
-
Comments:
-
Attach any images relevant to question 4 here.
-
5) Is the Principal Contractors H&S Policy Statement displayed?<br>(Is it Posted on the main notice board?)
-
Comments:
-
Attach any images relevant to question 5 here.
-
6) Is there a procedure in place to monitor work practices, policies and procedures carried out by the contractor to ensure that employees are working to required standards?<br>(I.e. internal audits / inspections schedule and findings action log).
-
Comments:
-
Attach any images relevant to question 6 here.
-
7) How are accidents, incidents and near misses investigated, monitored and reported and does this include reference to the clients procedure requirements?
-
Comments:
-
Attach any images relevant to question 7 here.
Traffic Management Plan / Emergency Procedures
-
8) Is there an approved Traffic Management Plan for the project and how is the Traffic Management Plan communicated to the relevant persons?
-
Comments:
-
Attach any images relevant to question 8 here.
-
9) Has the plan been distributed to all the Emergency Services and have they all acknowledged receipt of the plan?
-
Comments:
-
Attach any images relevant to question 9 here.
-
10) Have Fire Risk Assessments been carried out for any premises occupied?
-
Comments:
-
Attach any images relevant to question 10 here.
-
11) Is there a plan in place including emergency contact numbers for fire control, evacuation plans / procedures?
-
Comments:
-
Attach any images relevant to question 11 here.
-
12) Are clear procedures in place to deal with emergencies particularly those that likely to cause serious and imminent danger?
-
Comments:
-
Attach any images relevant to question 12 here.
-
13) Are people's duties clearly defined in such procedures including those persons nominated as competent to deal with them?
-
Comments:
-
Attach any images relevant to question 13 here.
-
14) Are non-employee who could be affected by the emergency (e.g. contractors, public, visitors and persons sharing the workplace) advised on what action to take?
-
Comments:
-
Attach any images relevant to question 14 here.
CDM Risk Register
-
15) How is the CDM Risk Register managed, and maintained on site and is a link with the designers being maintained? <br>(check to ensure that the CDM risk register is based on the clients health and safety requirements)
-
Comments:
-
Attach any images relevant to question 15 here.
-
16) How are construction phase risks being addressed and managed?
-
Comments:
-
Attach any images relevant to question 16 here.
Temporary Work
-
17) What are the management arrangements for temporary works for the duration of the project? <br>(Procedures / responsibilities / design / documentation etc.)
-
Comments:
-
Attach any images relevant to question 17 here.
-
18) Has a Temporary Works Coordinator been formally appointed?
-
Comments:
-
Attach any images relevant to question 18 here.
-
19) Has a Register of Temporary Works been established?
-
Comments:
-
Attach any images relevant to question 19 here.
-
20) Are all temporary works being undertaken on site identified on the Temporary Works Register?
-
Comments:
-
Attach any images relevant to question 20 here.
-
21) Have all Temporary Work on the register been categorized to identify the required level of controls?
-
Comments:
-
Attach any images relevant to question 21 here.
RAMS Review Process
-
22) What are the project arrangements for RAMS review and acceptance between the client and the principal contractor?
-
Comments:
-
Attach any images relevant to question 22 here.
-
23) What are the pre-start arrangements between the principal contractor and their sub-contractor request for RAMS / COSHH etc.?
-
Comments:
-
Attach any images relevant to question 23 here.
Occupational Health Surveillance
-
24) Does your company have pre-start medical questionnaire, and is there a requirement for all new employees to answer the questions relating to their personal health?
-
Comment:
-
Attach any images relevant to question 24 here.
-
25) How do you manage and retain the questionnaires and what do you do if there are any issues arising?
-
Comment:
-
Attach any images relevant to question 25 here.
-
26) What are the controls in place for the exposure of your employees to vibration / noise related hazards?
-
Comment:
-
Attach any images relevant to question 26 here.
-
27) Does your induction training cover all known health, safety and occupational health hazards?<br>(Check induction presentation)
-
Comment:
-
Attach any images relevant to question 27 here.
-
28) Do you have a process in place to cover identification and selection of suitable PPE for the project, and do they cover: Noise, Dust / Fumes, Vibration and COSHH requirements etc.?
-
Comment:
-
Attach any images relevant to question 28 here.
-
29) Do you have an active policy for dealing with alcohol and drug abuse on site?
-
Comment:
-
Attach any images relevant to question 29 here.
Effective Communication
-
30) What process is in place to ensure SHE information reaches all levels of manager and employees?<br>(i.e. safety meetings, notice boards, SHE alerts, toolbox talks, safety triangle etc).
-
Comments:
-
Attach any images relevant to question 30 here.
-
31) Are third party / external communication lines out of the project effective?<br>(look particularly at accident notifications, information to contractors, agencies, visitors, others sharing the workplace or affected by work activities and temporary workers)
-
Comments:
-
Attach any images relevant to question 31 here.
-
32) How will the project workforce be updated on changes to current legislation, company directives and procedures?<br>(SHE alerts, tool box talks, best practice, safety stand down days, notice boards etc).
-
Comments:
-
Attach any images relevant to question 32 here.
Providing Effective Training, Information and Instruction
-
33) Has the contractor a system in place to demonstrate the safety technical competency of his employees and sub-contractors with regard to qualification knowledge and experience and is it recorded?<br>(Look at training matrix / competence assessments / training records).
-
Comments:
-
Attach any images relevant to question 33 here.
-
34) Has a matrix of roles & personnel been produced for the project?
-
Comments:
-
Attach any images relevant to question 34 here.
-
35) Do the job roles specify minimum requirements for competence experience, qualifications, knowledge & training?
-
Comments:
-
Attach any images relevant to question 35 here.
-
36) Do the job roles specify minimum requirements for competency requirements set out by the clients H&S sub group?
-
Comments:
-
Attach any images relevant to question 36 here.
-
37) Are arrangements in place for EUSR and site induction training to be carried out at all levels including sub-contractors?<br>- Is there and electronic database for EUSR training ? (See Register)<br>- How are renewal dates of cards checked?<br>- Who delivers the training? Do they advise you of renewal dates?<br>- What is the grace period allowed for temporary persons on-site?<br>(undertake a spot check of a person on-site)
-
Comments:
-
Attach any images relevant to question 37 here.
-
38) Has the necessary training been provided in relation to the tasks a person is required to perform?<br>(Look at specific training for individual work activities such as using machinery, hazardous substances, crane banksmen.)
-
Comments:
-
Attach any images relevant to question 38 here.
-
39) Have suitable project personnel been identified as the competent persons for receipt of permitry?<br>Check that they identified in the project control manual)
-
Comments:
-
Attach any images relevant to question 39 here.
-
40) How is the site general safety induction training for AGIs, Compressors and Terminals being addressed?
-
Comments:
-
Attach any images relevant to question 40 here.
-
41) Is there a system in place for ensuring contractor's employees and sub-contractors are qualified to appropriate standards for job roles in question 36 above?<br><br>a) Records of qualifications, training, knowledge and experience are maintained and available?<br>b) These records are updated to reflect changes in personnel?<br>c) What level of independent verification is undertaken of qualification / training certificates?<br>
-
Comments:
-
Attach any images relevant to question 41 here.
-
42) What are the methods for communicating and recording receipt of RAMs, tool box talks etc for site operatives?
-
Comments:
-
Attach any images relevant to question 42 here.
Effective Liaison Arrangements
-
43) Is a safety group / committee in existence?<br>If not what are the arrangements for workforce consultation?
-
Comments:
-
Attach any images relevant to question 43 here.
Health & Safety Roles / Responsibilities & Accoutabilities
-
44) Have H&S responsibilities been allocated to project staff, for both client and contractors staff?
-
Comments:
-
Attach any images relevant to question 44 here.
-
45) How are personnel made aware of their responsibilities?
-
Comments:
-
Attach any images relevant to question 45 here.
-
46) Have suitable and sufficient H&S resource been allocated to the project?
-
Comments:
-
Attach any images relevant to question 46 here.
-
47) Do job all key descriptions specify health and safety responsibilities?
-
Comments:
-
Attach any images relevant to question 47 here.
-
48) What systems are in place to ensure that work activities are properly supervised?
-
Comments:
-
Attach any images relevant to question 48 here.
-
49) What are the pre-start arrangements between the Principal Contractor and their Sub-Contractor?<br>(Pre-start meets / requests for RAMs / COSHH etc.)
-
Comments:
-
Attach any images relevant to question 49 here.
-
50) Are health and safety items regularly included in management meetings? <br>(Look at minutes of progress meetings)
-
Comments:
-
Attach any images relevant to question 50 here.
-
51) Are health and safety requirements clearly spelt out when tendering, issuing contracts and ordering equipment and hiring plant?
-
Comments:
-
Attach any images relevant to question 51 here.
Provision of Safe Equipment
-
52) What are arrangements for the management of pre-inspection and inspection, maintenance and emergency repairs of plant and what records will be retained?
-
Comments:
-
Attach any images relevant to question 52 here.
-
53) How is lifting equipment controlled and managed for early works such as site establishment and pipe receipts?
-
Comments:
-
Attach any images relevant to question 53 here.
-
54) What is the process for preventing damaged equipment from being used?<br>(How is it quarantined and how effective is it)
-
Comments:
-
Attach any images relevant to question 54 here.
-
55) Are employees trained and instructed in the safe use of equipment?
-
Comments:
-
Attach any images relevant to question 55 here.
-
56) How are regular checks made to ensure that guards etc are being used correctly?
-
Comments:
-
Attach any images relevant to question 56 here.
Premises & Systems of Work
-
57) Have site rules, been established and do they identified prohibited / restricted areas, and how do you ensure compliance?
-
Comments:
-
Attach any images relevant to question 57 here.
-
58) How have First Aid provisions been addressed, and have First Aiders been appointed and communicated?
-
Comments:
-
Attach any images relevant to question 58 here.
-
59) Are welfare facilities available for all project staff and visitors?<br><br>a) Does this include transient site?<br>b) Were the welfare facilities accepted as suitable by the client before the works were allowed to start?
-
Comments:
-
Attach any images relevant to question 59 here.
Client SHE documentation / procedures at Site Project Offices
-
60) Has a client project Safety Advisor been appointed to assist the employer in complying with safety requirements?<br><br>a) Has he / she been briefed with regard to their roles and responsibilities?
-
Comments:
-
Attach any images relevant to question 60 here.
-
61) Has the clients H&S Policy Statement, Liability Insurance been posted on the notice board?
-
Comments:
-
Attach any images relevant to question 61 here.
-
62) What are the procedure for ensuring compliance with the clients accident / incident reporting procedure?
-
Comments:
-
Attach any images relevant to question 62 here.
-
63) Has an auditing and inspection program been established?
-
Comments:
-
Attach any images relevant to question 63 here.
-
64) Is the RAMs review process?
-
Comments:
-
Attach any images relevant to question 64 here.
-
65) Have the clients personnel been assessed for safety technical competence (STC) with regard to trained knowledge and experience and is it recorded?<br>(hard copies must be available with the clients project staff)
-
Comments:
-
Attach any images relevant to question 65 here.
Sign Off Audit
-
Print Name:
-
Signature:
-
Project Manager Name:
-
Signature:
-
Designation:
-
Select date