Title Page
-
Bridgfords Document No.
-
Audit Title
-
Site & Model
-
Prepared by
-
Fit out Duration
-
Project management /Contractors & Site Agent on site.
Initial Phase
-
Within 3 working days of site Survey request
-
Survey Request Date
-
Account manager to advise SDM of PM Allocation
-
Asbestos Survey Date
-
Within 7 calendar days of survey request.
-
Asbestos MGMT Report Date
-
Within 14 calendar days of Survey Request
-
Scope meeting Date
-
Within 21 calendar days of survey request.
Phase One Designs
-
Phase one design return date
-
Within 7 calendar days of scope meeting.
-
Drawing Amendment Minor (small amends to TC layout) Date
-
Within 2 working days of request.
-
Drawing Amendment major ( complete repositioning of layout/ racking layout amend) Date
-
Within 4 days of request.
-
Budget cost return date
-
Within 7 calendar days of scope meeting or drawing Amendment completion
Planning Phase 2
-
Actual cost return date
-
Within 14 calendar days of phase 1 drawing sign off or latest amendments to drawing.
-
Legal pack return date
-
Within 3 days of SDM request. (This must not be automatically sent and at SDM request only)
Project Phase
-
Carryout weekly site progress visits.Dates
-
At least 1 visit must be with an SDM
-
Handover Minor/Intermediate/Major - 25/15/5
-
Handover score
-
Snagging Completion date
-
Within 1 week of handover.
-
Extras completion date.
-
By SDM agreement - but must be completed by soft launch depending on request.
-
Site management, Good/Acceptable/Unacceptable
-
Site management
-
Site Health & Safety, Good/Acceptable/Unacceptable
-
Site Health & Safety
Financial Management
-
PO request to be generated.
-
£5k invoice to be raised.
-
2 weeks following full capex approval.
-
£20k invoice to be raise.
-
8 weeks before site commencement.
-
Email sent from Gary Worthington authorising build cost
-
90% handover invoice to be raised.
-
Within 1 week of handover.
-
Final account invoice to be raised.
-
Within 4 weeks of handover (SDM to settle account within 3 weeks of receipt)
Post Project Section
-
Has the site been signed off by building control
-
Has the O&M manual been completed with all certificates &Plans
-
Have the as built drawings been sent to Adrian Gaylard
-
Have the as built drawings been uploaded to the micad system
-
Signed off by SDM
-
Sign off by Principal contractor PM
-
Project summary completed by SDM.
-
Singed off by Gary Worthington
-
Sent to Adrian Bell for maintenance team file.