Information
-
Document No.
-
Project Manager's Accountability Checklist
-
Client / Site
-
Conducted on
-
Prepared by
-
Location
Job Start Up
-
Revised Takeoff and Bid.
-
Select date
-
Reviewed the Contract Using the Contract Review Checklist.
-
Select date
-
Organized all information for the Foreman's Job Information Packet.
-
Select date
-
Conducted a Job Start Up Meeting with the Foreman using the Job Start Up Checklist.
-
Select date
-
Completed the Pre Job Tool & Equipment Checklist with the Foreman.
-
Select date
Job Preparation & Planning
-
Scheduled and Conducted the Pre Job Planning Meeting with key team members. Completed Pre Job Planning Meeting Checklist.
-
Select date
-
Prepared the Labor Budget by Cost Codes for each key activity.
-
Select date
-
Prepared a Labor Budget Tracking Sheet and showed the Foreman how to complete it.
-
Select date
-
Reviewed the Weekly Labor Report with the Foreman.
-
Select date
-
Investigated all "over budget" situations and make necessary corrections with the foreman to get back on budget.
-
Select date
-
Reviewed the GC's Project Scheduled and discussed it with the foreman.
-
Select date
-
Completed the Material and Equipment Buyout- Pricing Request.
-
Select date
-
Initiated Pre-Construction Shop Drawings, if required and submitted them to the architect for approval.
-
Select date
-
Prepared and submitted the Submittal Packet to the Architect and GC for their review and Approval. Prepare a Submittal Request Worksheet.
-
Select date
-
Initiated Requests for Information (RFI'S) and completed the RFI Form.
-
Select date
-
Developed a Site Specific Safety Plan with Foreman.
-
Select date
-
Reviewed on site Quality Control Program with the Foreman.
-
Select date
Managing the Project
-
Schedule initial meeting with GC to discuss issues and expectations for the upcoming project.
-
Select date
-
Order materials for project once prices have been established.
-
Select date
-
Processed Change Orders for extra work requests from the GC that changes the Scope of Work that was originally defined in the contract.
-
Select date
-
Completed and processed the "Extra Work to be Performed" form for work requested by the GC that is not defined in our Scope of Work.
-
Select date
-
Participated in the Weekly Project Meeting to review the status of the project.
-
Select date
-
Conducted Weekly Job Site visits. Completed Job Site Visit Report. Reviewed with Foreman
-
Select date
Job Close Out
-
Conducted Evaluation Meeting with GC and completed Customer Evaluation Checklist.
-
Select date
-
Completed the Project Close Out Checklist.
-
Select date
-
Scheduled and conducted Post Job Review Meeting. Completed Post Job Review Checklist.
-
Select date
-
Worked with Foreman to complete GC's Punch List on timely basis
-
Select date