Title Page
-
Site conducted
-
Contract Name
-
Contract Number
-
Date of Inspection
-
Inspection carried out by
-
Contractor
-
Location
-
Brief Description of Work Activity
-
Client
General
-
Site Tidiness
-
Storage of Material
undefined
-
-
Access to Work Areas
-
Traffic Management
-
Site Traffic Management
-
Protection - check site fence / pedestrian routes
-
Safety Notices & Signs
-
Fire Extinguishers
-
Health and Safety Folders up to date
-
First Aid Provisions + First Aiders
-
COSHH Store
-
Personnel
-
Are all site staff inducted
-
Method Statements and Risk Assessments appropriate for this weeks task and all relevant members of the site team signed on
-
Is the JSSP's displayed / communicated and all staff signed on (signed /thumbs up)
-
Use of PPE
-
Training Cards
-
CIF Covid Training Evident
-
Last Tool Box Talk completed, next possible topic
-
Subcontractors and Suppliers
-
Condition of Welfare Facilities
Welfare Facilities
-
Are welfare provisions in place, with the required stipulations (Drinking Water, Heat, Drying room, Warm Water + Soap)?
-
What is the condition of the Welfare Facilities?
-
Is the welfare conditions sufficient for number onsite and for the remainder of the project?
-
Are adequate Infection Prevention and control measure in place to assist in the prevention of the spread of COVID 19
Excavations / Shafts / Confined Spaces
-
Edge protection in place
-
Support and Stability
-
Access / Egress
-
Atmosphere Monitoring
-
Escape Sets - Check all emergency equipment
-
Permits to Work (Lift Dig Electrical)
-
Site Lighting / Task Lighting
Scaffolding
-
Has the scaffolding been constructed as part of the agreed set up and in line with the manufactures guidelines?
-
Is there evidence of a Temporary Works Design?
-
Is the overall condition of the scaffolding safe?
-
Is there evidence of a weekly Inspection by the scaffolding while it is in use?
-
If the scaffolding is not in use, has it been closed off and inspected by a competent person?
Plant and Equipment
-
Plant Maintenance, Inspection & Testing, Certificates
-
Cranes & Lifting appliances
-
Chains, slings and lifting Equipment
-
Excavation & Earth moving plant
-
Dumpers and other small plant
-
Visibility Aids, mirrors & beacons, reversing beacons
-
Banksmen and Slingers
-
LGV's and other vehicles
-
Safety Inspections - GA1 / GA2 / AF3 / LOLER / PUWER/ Excavation Inspections
-
Defects
Pumping & Discharge
-
Consented Discharge Points
-
Pump equipment & hoses
-
Silt Traps / Settlement Ponds / Clean cut off drains
Overall Condition of the Site
-
Site Safety Documentation
-
Access Tracks and Hardstands
-
Site Entrance
-
Site Compound
3rd Party Landowner
-
Any issues with the 3rd Party Landowner
-
Any security issues
Any Other Site Issues
-
Any other observations identified onsite?