Quality Control

  • Site conducted

  • Conducted on

  • Location
  • QES QC2_01 To QES QC2_09

  • Name of Firecrest QC Checker

  • Sheet Number: 1 of 9

  • Installtion Supervisor - Print Name - Company - Sign

  • Number Item Yes, No, First Off ITEM CHECKED of Photos I/D N/A QC Date Taken

QUALITY CONTROL CHECK SHEET

Sheet Number: 1 GROUND PREPARATION

  • Item ITEM CHECKED

  • 1_1 Remediation / SI Summary available

  • 1_2 Dilapidation photos taken

  • 1_3 Survey of remediation area following vegetation & soil strip recorded

  • 1_4 Fill materials specification acceptable

  • 1_5 Fill material analysis result inclusive of sample photos

  • 1_6 Fill material order details/Delivery note recorded from external supplier acceptable

  • 1_7 Capping material specification recorded & acceptable

  • 1_8 Capping material analysis result + Sample photos

  • 1_9 Capping material order details/Delivery note recorded

  • 1_10 Survey of cut and fill testing regime results acceptable

  • 1_11 Cut and fill operations final level acceptable

  • 1_12 Soft spots indicated if required

  • 1_13 Ground cleared to agreed condition

  • FOLLOWING QA CHECKS, DEFECT ACTION CLOSURE & PROCESS COMPLETION SIGN BELOW.

  • Sign:

  • Print:

  • Date:

Sheet Number: 2 GROUND PREPARATION

  • ITEM CHECKED

  • 2_1 Grid location(s) agreed / identified

  • 2_2 Excavation depth & width and surface finish acceptable to specification

  • 2_3 Membrane to specification acceptable

  • 2_4 Membrane Order Details / Delivery Note recorded acceptable

  • 2_5 Cover requirements to specification acceptable

  • 2_6 Ground cleared to agreed condition acceptable

  • 2_7 Contractor verification certification recorded

  • FOLLOWING QA CHECKS, DEFECT ACTION CLOSURE & PROCESS COMPLETION SIGN BELOW.

  • Sign:

  • Print:

  • Date:

Sheet Number: 3 GROUND PREPARATION

  • Item checked

  • 3_1 Grid location(s) agreed / identified

  • 3_2 Ground cleared to agreed condition

  • 3_4 Geo-grid as specified in place as specified

  • 3_5 Terram as specified in place as specified

  • 3_6 Ground levels layered up to approved correct level

  • 3_7 QC Sample test results (CBR, etc.) recorded & acceptable

  • 3_8 5 Metre grid record of levelled area recorded

  • 3_9 Contractor certification recorded

  • FOLLOWING QA CHECKS, DEFECT ACTION CLOSURE & PROCESS COMPLETION SIGN BELOW.

  • Sign:

  • Print:

  • Date:

Sheet Number: 4 GROUND PREPARATION

  • Item Checked

  • 4_1 Grid location(s) agreed / identified

  • 4_2 Sheet piling depth confirmed & checked

  • 4_3 Test results recorded

  • 4_4 Site cleared to agreed condition

  • 4_5 Contractor verification certificate

  • FOLLOWING QA CHECKS, DEFECT ACTION CLOSURE & PROCESS COMPLETION SIGN BELOW.

  • Sign:

  • Print:

  • Date:

Sheet Number: 5 GROUND PREPARATION

  • Item ITEM CHECKED

  • 5_1 Grid location(s) agreed / identified

  • 5_2 Level survey acceptable

  • 5_3 Toe excavation blinding/pitch agreed

  • 5_4 Basket configuration

  • 5_5 Stone specification

  • 5_6 Stone specification sample approved

  • 5_7 Stone Order Details/Delivery Note

  • 5_8 Foundations line & level acceptable

  • 5_9 Cube tests recorded if required

  • 5_10 Basket finish alignment & verticality acceptable

  • 5_11 Gabion anchoring system correct

  • 5_12 Finish levels correct

  • 5_12 Backfill stabilisation acceptable

  • 5_13 Ground cleared to agreed condition

  • FOLLOWING QA CHECKS, DEFECT ACTION CLOSURE & PROCESS COMPLETION SIGN BELOW.

  • Sign:

  • Print:

  • Date:

Sheet Number: 6 GROUND PREPARATION

  • Item Checked

  • 6_1 Grid location(s) agreed / identified

  • 6_2 Specification & Plan acceptable and recorded

  • 6_3 Grout delivery note acceptable

  • 6_4 Drilling Record recorded

  • 6_5 Site cleared to agreed condition

  • 6_6 Subcontractor verification certification recorded

  • Following QA checks, defect action closure & process completion sign below.

  • Sign:

  • Print:

  • Date:

Sheet Number: 7 GROUND PREPARATION

  • ITEM CHECKED

  • 7_1 Specification & Plan recorded

  • 7_2 Handover Certificate recorded

  • 7_3 Site Cleared to agreed condition

  • 7_4 Third party verification certification

  • FOLLOWING QA CHECKS, DEFECT ACTION CLOSURE & PROCESS COMPLETION SIGN BELOW.

  • Sign:

  • Print:

  • Date:

Sheet Number: 8 GROUND PREPARATION

  • ITEM CHECKED

  • 8_1 Level survey

  • 8_2 Grid location(s) agreed / identified

  • 8_3 Set out agreed

  • 8_4 Base levels

  • 8_5 Stone specification

  • 8_6 Stone specification sample approved

  • 8_7 Stone Order Details/Delivery Note

  • 8_8 Finished levels correct

  • 8_9 Base lining specification correct

  • 8_10 Base lining placed acceptable

  • 8_11 Surface lining specification

  • 8_12 Surface lining placed

  • 8_13 Subcontractor Completion certificate

  • FOLLOWING QA CHECKS, DEFECT ACTION CLOSURE & PROCESS COMPLETION SIGN BELOW.

  • Sign:

  • Print:

  • Date:

Sheet Number: 9 GROUND PREPARATION

  • ITEM CHECKED

  • 9_1 Party wall agreement in place

  • 9_2 Work area identified

  • 9_3 Set out agreed

  • 9_4 Base levels

  • 9_5 Existing wall survey recorded

  • 9_6 Vibration monitoring record

  • 9_7 Propping in place as required

  • 9_8 Fixing/anchor specification

  • 9_9 Fill specification

  • 9_10 Fixing/Anchor Order Details/Delivery

  • 9_11 Fill Details/Delivery Note

  • 9_12 Party wall secured

  • 9_13 Completion certificate from independent party recorded

  • FOLLOWING QA CHECKS, DEFECT ACTION CLOSURE & PROCESS COMPLETION SIGN BELOW.

  • Sign:

  • Print:

  • Date:

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.