Title Page

  • Site conducted:

  • Client:

  • Manager/Supervisor:

  • Operative:

  • Work Area:

  • Start Date:

  • Finish Date:

  • Drawing number & Revision Used:

  • Have all fixings been checked and are the right fixings in accordance with design and manufacture guidance?

  • Is SFS installed to the correct gridlines/datums?

  • Are the correct studs being used?(size/gauge)

  • Are studs fixed to the correct cross centre and plumb?

  • Are studs fixed to base and head track on both sides?

  • Are jambs the correct types with correct fixings and plumb?

  • Are the jambs, cills and lintels as per standard details?

  • Is the deflection head correctly installed?

  • Are deflection head screws central in the slot?

  • Is the head track fixed to sub-structure as per details?

  • Is the base track fixed to sub-structure as per details and DPC if required?

  • Are the Structural Openings as per dimensions?

  • Are the duct penetrations in the correct locations?

  • Are the Movement Joint in the correct location?

  • Are the Party Wall studs installed to the correct location?

  • Has work area left clean and tidy?

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.